7548
Federal Register / Vol. 85, No. 27 / Monday, February 10, 2020 / Notices
Filed Date: 2/4/20.
Accession Number: 20200204–5000.
Comments Due: 5 p.m. ET 2/25/20.
Docket Numbers: ER20–947–000.
Applicants: NorthWestern
Corporation.
Description: § 205(d) Rate Filing: SA
767 8th Rev—NITSA with Basin Electric
Power Cooperative to be effective
2/5/2020.
Filed Date: 2/4/20.
Accession Number: 20200204–5001.
Comments Due: 5 p.m. ET 2/25/20.
Docket Numbers: ER20–948–000.
Applicants: Southwestern Public
Service Company.
Description: § 205(d) Rate Filing: SPS
Wholesale Fuel Factor Modification to
be effective 12/1/2019.
Filed Date: 2/4/20.
Accession Number: 20200204–5030.
Comments Due: 5 p.m. ET 2/25/20.
Docket Numbers: ER20–949–000.
Applicants: NorthWestern
Corporation.
Description: 2019 Post-Retirement
Benefits Other than Pensions of
Northwestern Corporation.
Filed Date: 2/3/20.
Accession Number: 20200203–5246.
Comments Due: 5 p.m. ET 2/24/20.
Docket Numbers: ER20–950–000.
Applicants: Public Service Company
of Colorado.
Description: § 205(d) Rate Filing: Joint
Dispatch Agreement Update to be
effective 4/5/2020.
Filed Date: 2/4/20.
Accession Number: 20200204–5060.
Comments Due: 5 p.m. ET 2/25/20.
Docket Numbers: ER20–951–000.
Applicants: Mid-Atlantic Interstate
Transmission, LL,PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
MAIT submits 8 ECSAs, Service
Agreement Nos. 5329, 5330, 5334, 5388,
5512, et al to be effective 4/4/2020.
Filed Date: 2/4/20.
Accession Number: 20200204–5079.
Comments Due: 5 p.m. ET 2/25/20.
Docket Numbers: ER20–952–000.
Applicants: NorthWestern
Corporation.
Description: § 205(d) Rate Filing: SA
305 15th Rev—NITSA with Stillwater
Mining Company to be effective
3/1/2020.
Filed Date: 2/4/20.
Accession Number: 20200204–5083.
Comments Due: 5 p.m. ET 2/25/20.
Docket Numbers: ER20–953–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, SA No. 5561; Queue No.
AC1–043 to be effective 1/14/2020.
VerDate Sep<11>2014
16:58 Feb 07, 2020
Jkt 250001
Filed Date: 2/4/20.
Accession Number: 20200204–5084.
Comments Due: 5 p.m. ET 2/25/20.
Docket Numbers: ER20–954–000.
Applicants: Ohio Power Company,
AEP Ohio Transmission Company, Inc.,
PJM Interconnection, L.L.C.
Description: § 205(d) Rate Filing: AEP
submits ILDSA, SA No. 1336 and 2
Facilities Agreements to be effective
4/4/2020.
Filed Date: 2/4/20.
Accession Number: 20200204–5088.
Comments Due: 5 p.m. ET 2/25/20.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
Time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: February 4, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–02556 Filed 2–7–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. RP20–481–000]
BP Energy Company v. Natural Gas
Pipeline Company of America LLC;
Notice of Complaint
Take notice that on January 31, 2020,
pursuant to Rule 206 of the Federal
Energy Regulatory Commission’s
(Commission) Rules of Practice and
Procedure, 18 CFR 385.206 (2019), BP
Energy Company, (Complainants) filed a
formal complaint against Natural Gas
Pipeline Company of America LLC,
(Respondent) requesting the
Commission to direct the Respondent to
follow its presently effective FERC Gas
Tariff (Tariff), Section 4 of the Natural
Gas Act (NGA), and the Commission’s
regulations thereunder, all as more fully
explained in the complaint.
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
The Complainant certifies that copies
of the complaint were served on
Respondent’s corporate representatives
designated on the Commission’s
Corporate Officials List.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an ‘‘eSubscription’’ link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on February 20, 2020.
Dated: February 4, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2020–02554 Filed 2–7–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 3063–021]
Blackstone Hydro Associates; Notice
Soliciting Scoping Comments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
E:\FR\FM\10FEN1.SGM
10FEN1
jbell on DSKJLSW7X2PROD with NOTICES
Federal Register / Vol. 85, No. 27 / Monday, February 10, 2020 / Notices
a. Type of Application: Subsequent
Minor License.
b. Project No.: 3063–021.
c. Date filed: July 31, 2019.
d. Applicant: Blackstone Hydro
Associates (BHA).
e. Name of Project: Central Falls
Hydroelectric Project.
f. Location: On the Blackstone River,
in the City of Central Falls, Providence
County, Rhode Island. No federal lands
are occupied by the project works or
located within the project boundary.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Mr. Robert
Leahy, 130 Prospect Street, Cambridge,
MA 02139; Phone at (617) 491–2320, or
email at rleahy@theshorelinecorp.com.
i. FERC Contact: John Baummer, 202–
502–6837, or john.baummer@ferc.gov.
j. Deadline for filing scoping
comments: March 1, 2020.
The Commission strongly encourages
electronic filing. Please file scoping
comments using the Commission’s
eFiling system at https://www.ferc.gov/
docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–3063–021.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application is not ready for
environmental analysis at this time.
l. The existing Central Falls Project
consists of: (1) A 190-foot-long, 24-foothigh, curved granite-masonry dam
(Valley Falls Dam); (2) an approximately
64.5-acre impoundment with a normal
maximum elevation of 49.5 feet
National Geodetic Vertical Datum of
1929 (NGVD 1929); (3) a granite block
and wood-framed gatehouse that is
adjacent to the dam and that contains
ten gates that are 9 feet wide by 6 feet
VerDate Sep<11>2014
16:58 Feb 07, 2020
Jkt 250001
tall; (4) a 290-foot-long, granite blocklined headrace; (5) an intake structure
with two 8-foot-high hydraulic gates
and 24-foot-wide, 11.5-foot-high,
inclined trashracks having 3-inch clear
bar spacing; (6) two 30-foot-long, 7-footdiameter penstocks; (7) an
approximately 53-foot-long, 32-footwide concrete powerhouse containing
two Allis-Chalmers tube turbines with a
total installed capacity of 700 kilowatts
(kW); (8) an approximately 1,200-footlong, 36-foot-wide tailrace; (9) two 480volt generator lead lines; and (10)
appurtenant facilities.
BHA operates the project as a run-ofriver facility, such that outflow from the
project approximates inflow. The
project bypasses approximately 0.3 mile
of the Blackstone River. A 108-cubic feet
per second (cfs) minimum flow is
released over the dam into the bypassed
reach. BHA discharges a continuous
minimum flow of 238 cfs, or inflow,
whichever is less, as measured at the
confluence of the tailrace and the river
channel. The average annual generation
of the project is approximately 1,230
megawatt-hours (MWh).
BHA proposes to: (1) Continue
operating the project in a run-of-river
mode; (2) retrofit the two existing
turbines with variable pitch blade
runners to allow for the project to be
operated at different flows; (3) install a
new bypassed flow pipe to provide a
minimum flow of 210 cfs to the
bypassed reach, approximately 215 feet
downstream of the dam; (4) install a
new 160-kW ‘‘fish friendly’’ turbinegenerator unit in the proposed bypassed
flow pipe to increase the project’s
capacity and provide downstream fish
passage; (5) install a new trashrack with
1-inch clear bar spacing in the headrace
to prevent fish impingement and
entrainment; (6) install a new
downstream fish passage facility in the
headrace, immediately upstream of the
new trashrack; (7) maintain a 13-cfs
aesthetic flow over the Valley Falls
Dam; (8) provide a flow of up to 3 cfs
to the adjacent historic canal; (9) install
an upstream eel passage facility at the
project dam; and (10) install 20 longeared bat boxes and implement a
Northern Long Eared Bat Management
and Protection Plan to protect bats. BHA
estimates the project enhancements will
result in an average annual generation of
approximately 3,200 MWh.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to address the
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
7549
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at 1485
High Street Central Falls, RI 02863.
n. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. Scoping Process.
Commission staff intend to prepare a
single Environmental Assessment (EA)
for the Central Falls Hydroelectric
Project in accordance with the National
Environmental Policy Act. The EA will
consider both site-specific and
cumulative environmental impacts and
reasonable alternatives to the proposed
action.
At this time, we do not anticipate
holding on-site public or agency scoping
meetings. Instead, we are soliciting your
comments and suggestions on the
preliminary list of issues and
alternatives to be addressed in the EA,
as described in scoping document 1
(SD1), issued January 31, 2020.
Copies of the SD1 outlining the
subject areas to be addressed in the EA
were distributed to the parties on the
Commission’s mailing list and the
applicant’s distribution list. Copies of
SD1 may be viewed on the web at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call 1–866–
208–3676 or for TTY, (202) 502–8659.
Dated: January 31, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–02580 Filed 2–7–20; 8:45 am]
BILLING CODE 6717–01–P
FEDERAL COMMUNICATIONS
COMMISSION
[WC Docket No. 10–90, CC Docket No. 01–
92; FCC 19–131; FRS 16472]
Connect America Fund; Developing a
Unified Intercarrier Compensation
Regime; Correction
Federal Communications
Commission.
ACTION: Notice; correction.
AGENCY:
The Federal Communications
Commission published a document in
the Federal Register of January 30,
2020, clarifying its interpretation of the
VoIP Symmetry Rule. The document
contained incorrect dates.
SUMMARY:
E:\FR\FM\10FEN1.SGM
10FEN1
Agencies
[Federal Register Volume 85, Number 27 (Monday, February 10, 2020)]
[Notices]
[Pages 7548-7549]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-02580]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3063-021]
Blackstone Hydro Associates; Notice Soliciting Scoping Comments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
[[Page 7549]]
a. Type of Application: Subsequent Minor License.
b. Project No.: 3063-021.
c. Date filed: July 31, 2019.
d. Applicant: Blackstone Hydro Associates (BHA).
e. Name of Project: Central Falls Hydroelectric Project.
f. Location: On the Blackstone River, in the City of Central Falls,
Providence County, Rhode Island. No federal lands are occupied by the
project works or located within the project boundary.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Mr. Robert Leahy, 130 Prospect Street,
Cambridge, MA 02139; Phone at (617) 491-2320, or email at
[email protected].
i. FERC Contact: John Baummer, 202-502-6837, or
[email protected].
j. Deadline for filing scoping comments: March 1, 2020.
The Commission strongly encourages electronic filing. Please file
scoping comments using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief
comments up to 6,000 characters, without prior registration, using the
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You
must include your name and contact information at the end of your
comments. For assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426. The first page of any filing should include
docket number P-3063-021.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application is not ready for environmental analysis at this
time.
l. The existing Central Falls Project consists of: (1) A 190-foot-
long, 24-foot-high, curved granite-masonry dam (Valley Falls Dam); (2)
an approximately 64.5-acre impoundment with a normal maximum elevation
of 49.5 feet National Geodetic Vertical Datum of 1929 (NGVD 1929); (3)
a granite block and wood-framed gatehouse that is adjacent to the dam
and that contains ten gates that are 9 feet wide by 6 feet tall; (4) a
290-foot-long, granite block-lined headrace; (5) an intake structure
with two 8-foot-high hydraulic gates and 24-foot-wide, 11.5-foot-high,
inclined trashracks having 3-inch clear bar spacing; (6) two 30-foot-
long, 7-foot-diameter penstocks; (7) an approximately 53-foot-long, 32-
foot-wide concrete powerhouse containing two Allis-Chalmers tube
turbines with a total installed capacity of 700 kilowatts (kW); (8) an
approximately 1,200-foot-long, 36-foot-wide tailrace; (9) two 480-volt
generator lead lines; and (10) appurtenant facilities.
BHA operates the project as a run-of-river facility, such that
outflow from the project approximates inflow. The project bypasses
approximately 0.3 mile of the Blackstone River. A 108-cubic feet per
second (cfs) minimum flow is released over the dam into the bypassed
reach. BHA discharges a continuous minimum flow of 238 cfs, or inflow,
whichever is less, as measured at the confluence of the tailrace and
the river channel. The average annual generation of the project is
approximately 1,230 megawatt-hours (MWh).
BHA proposes to: (1) Continue operating the project in a run-of-
river mode; (2) retrofit the two existing turbines with variable pitch
blade runners to allow for the project to be operated at different
flows; (3) install a new bypassed flow pipe to provide a minimum flow
of 210 cfs to the bypassed reach, approximately 215 feet downstream of
the dam; (4) install a new 160-kW ``fish friendly'' turbine-generator
unit in the proposed bypassed flow pipe to increase the project's
capacity and provide downstream fish passage; (5) install a new
trashrack with 1-inch clear bar spacing in the headrace to prevent fish
impingement and entrainment; (6) install a new downstream fish passage
facility in the headrace, immediately upstream of the new trashrack;
(7) maintain a 13-cfs aesthetic flow over the Valley Falls Dam; (8)
provide a flow of up to 3 cfs to the adjacent historic canal; (9)
install an upstream eel passage facility at the project dam; and (10)
install 20 long-eared bat boxes and implement a Northern Long Eared Bat
Management and Protection Plan to protect bats. BHA estimates the
project enhancements will result in an average annual generation of
approximately 3,200 MWh.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's website at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to address the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at 1485 High Street Central Falls, RI 02863.
n. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
o. Scoping Process.
Commission staff intend to prepare a single Environmental
Assessment (EA) for the Central Falls Hydroelectric Project in
accordance with the National Environmental Policy Act. The EA will
consider both site-specific and cumulative environmental impacts and
reasonable alternatives to the proposed action.
At this time, we do not anticipate holding on-site public or agency
scoping meetings. Instead, we are soliciting your comments and
suggestions on the preliminary list of issues and alternatives to be
addressed in the EA, as described in scoping document 1 (SD1), issued
January 31, 2020.
Copies of the SD1 outlining the subject areas to be addressed in
the EA were distributed to the parties on the Commission's mailing list
and the applicant's distribution list. Copies of SD1 may be viewed on
the web at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, call 1-866-208-3676 or
for TTY, (202) 502-8659.
Dated: January 31, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-02580 Filed 2-7-20; 8:45 am]