Download as PDF Federal Register / Vol. 85, No. 20 / Thursday, January 30, 2020 / Notices 8. If any of the above-captioned market-based rate sellers does not wish to continue having market-based rate authority, it may file a notice of cancellation with the Commission pursuant to section 205 of the FPA to cancel its market-based rate tariff. The Commission orders: (A) Within fifteen days of the date of issuance of this order, each public utility listed in the caption of this order shall file with the Commission all delinquent Electric Quarterly Reports. If a public utility subject to this order fails to make the filings required in this order, the Commission will revoke that public utility’s market-based rate authorization and will terminate its electric market-based rate tariff. The Secretary is hereby directed, upon expiration of the filing deadline in this order, to promptly issue a notice, effective on the date of issuance, listing the public utilities whose tariffs have been revoked for failure to comply with the requirements of this order and the Commission’s Electric Quarterly Report filing requirements. (B) The Secretary is hereby directed to publish this order in the Federal Register. By the Commission. Issued: January 23, 2020. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2020–01590 Filed 1–29–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP20–10–000] khammond on DSKJM1Z7X2PROD with NOTICES Rover Pipeline LLC; Notice of Schedule for Environmental Review of the Wick Meter and Regulator Station Project On November 1, 2019, Rover Pipeline LLC (Rover) filed an application in Docket No. CP20–10–000 requesting a Certificate of Public Convenience and Necessity pursuant to Section 7(c) of the Natural Gas Act to construct, own, and operate a new meter station. The Wick Meter and Regulator Station Project (Project) would allow for the delivery of natural gas supplies from gathering facilities, under development by Eureka Midstream, LLC, for transportation on the Rover pipeline system, and it would be located along Rover’s Sherwood Lateral Pipeline in Tyler County, West Virginia. On November 19, 2019, the Federal Energy Regulatory Commission VerDate Sep<11>2014 16:56 Jan 29, 2020 Jkt 250001 (Commission or FERC) issued its Notice of Application for the Project. Among other things, that notice alerted agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on a request for a federal authorization within 90 days of the date of issuance of the Commission staff’s Environmental Assessment (EA) for the Project. This instant notice identifies the FERC staff’s planned schedule for the completion of the EA for the Project. Schedule for Environmental Review Issuance of EA: March 13, 2020. 90-day Federal Authorization Decision Deadline: June 11, 2020. If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. Project Description The Wick Meter and Regulator Station Project would consist of an ultrasonic meter skid and other ancillary facilities in Tyler County, West Virginia. The ancillary facilities would include piping and valves, electronic flow measurement devices, flow conditioners, instrumentation, telemetry, gas analysis devices, gas quality monitoring devices, flow control valves, condensate storage tank, and other related equipment. Rover would use about 2.1 acres of land to construct the station, of which 0.9 acre would be fenced and maintained for operation of the station. Background On January 21, 2020, the Commission issued a Notice of Intent to Prepare an Environmental Assessment for the Proposed Wick Meter and Regulator Station Project and Request for Comments on Environmental Issues (NOI). The NOI was sent to affected landowners; federal, state, and local government agencies; elected officials; environmental and public interest groups; Native American tribes; other interested parties. To date, no comments have been received in response to the NOI. All substantive comments will be addressed in the EA. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document PO 00000 Frm 00049 Fmt 4703 Sfmt 4703 5415 summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP20–10), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: January 24, 2020. Kimberly D. Bose, Secretary. [FR Doc. 2020–01689 Filed 1–29–20; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 1432–015] PB Energy, Inc.; Notice of Termination of License (Minor Project) by Implied Surrender and Soliciting Comments, Protests, and Motions To Intervene Take notice that the following hydroelectric proceeding has been initiated by the Commission: a. Type of Proceeding: Termination of License by Implied Surrender. b. Project No.: 1432–015. c. Date Initiated: January 24, 2020. d. Licensee: PB Energy, Inc. e. Name and Location of Project: The Dry Spruce Bay Hydroelectric Project located on an unnamed stream near Port Bailey in Kodiak Island Borough County, Alaska. f. Filed Pursuant to: Standard Article 24. g. Licensee Contact Information: PB Energy, Inc., P.O. Box KPY, Kodiak, Alaska 99697. h. FERC Contact: Kim Nguyen, (202) 502–6105, kim.nguyen@ferc.gov. i. Deadline for filing comments, motions to intervene and protests, is thirty (30) days from the issuance date of this notice by the Commission. The Commission strongly encourages electronic filing. Please file motions to intervene, protests, and comments using the Commission’s eFiling system at E:\FR\FM\30JAN1.SGM 30JAN1

Agencies

[Federal Register Volume 85, Number 20 (Thursday, January 30, 2020)]
[Notices]
[Page 5415]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-01689]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP20-10-000]


Rover Pipeline LLC; Notice of Schedule for Environmental Review 
of the Wick Meter and Regulator Station Project

    On November 1, 2019, Rover Pipeline LLC (Rover) filed an 
application in Docket No. CP20-10-000 requesting a Certificate of 
Public Convenience and Necessity pursuant to Section 7(c) of the 
Natural Gas Act to construct, own, and operate a new meter station. The 
Wick Meter and Regulator Station Project (Project) would allow for the 
delivery of natural gas supplies from gathering facilities, under 
development by Eureka Midstream, LLC, for transportation on the Rover 
pipeline system, and it would be located along Rover's Sherwood Lateral 
Pipeline in Tyler County, West Virginia.
    On November 19, 2019, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for the completion of the 
EA for the Project.

Schedule for Environmental Review

    Issuance of EA: March 13, 2020.
    90-day Federal Authorization Decision Deadline: June 11, 2020.
    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The Wick Meter and Regulator Station Project would consist of an 
ultrasonic meter skid and other ancillary facilities in Tyler County, 
West Virginia. The ancillary facilities would include piping and 
valves, electronic flow measurement devices, flow conditioners, 
instrumentation, telemetry, gas analysis devices, gas quality 
monitoring devices, flow control valves, condensate storage tank, and 
other related equipment. Rover would use about 2.1 acres of land to 
construct the station, of which 0.9 acre would be fenced and maintained 
for operation of the station.

Background

    On January 21, 2020, the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed Wick Meter and 
Regulator Station Project and Request for Comments on Environmental 
Issues (NOI). The NOI was sent to affected landowners; federal, state, 
and local government agencies; elected officials; environmental and 
public interest groups; Native American tribes; other interested 
parties. To date, no comments have been received in response to the 
NOI. All substantive comments will be addressed in the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP20-10), and follow the 
instructions. For assistance with access to eLibrary, the helpline can 
be reached at (866) 208-3676, TTY (202) 502-8659, or at 
[email protected]. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: January 24, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-01689 Filed 1-29-20; 8:45 am]
 BILLING CODE 6717-01-P