Limited-Scope Supplemental Environmental Impact Statement: City of Burlington, Chittenden County, Vermont, 4758 [2020-01333]

Download as PDF 4758 Federal Register / Vol. 85, No. 17 / Monday, January 27, 2020 / Notices entity submitting the comments. Submissions that do not contain business confidential information should have a file name identifying the person or entity submitting the comments. We emphasize that submitters are strongly encouraged to file comments through www.regulations.gov. You must make arrangements for any alternative method of submission with Yvonne Jamison at (202) 395–9666 in advance of transmitting a comment. You can find general information about USTR at www.ustr.gov. As noted, we will publish nonconfidential versions of submissions in the docket for public inspection. You can view submissions on www.regulations.gov by entering the relevant docket number in the search field on the home page. Jeffrey Gerrish, Deputy United States Trade Representative, Office of the U.S. Trade Representative. [FR Doc. 2020–01260 Filed 1–24–20; 8:45 am] BILLING CODE 3290–F0–P DEPARTMENT OF TRANSPORTATION Federal Highway Administration Limited-Scope Supplemental Environmental Impact Statement: City of Burlington, Chittenden County, Vermont Federal Highway Administration (FHWA), DOT. ACTION: Notice of intent to prepare a Limited-Scope Supplemental Environmental Impact Statement. AGENCY: The FHWA is issuing this notice to advise the public that a Limited-Scope Supplemental Environmental Impact Statement will be prepared for the proposed Southern Connector/Champlain Parkway project in the City of Burlington, Chittenden County, Vermont. FOR FURTHER INFORMATION CONTACT: Rob Sikora, Environmental Program Manager, Federal Highway Administration, 87 State Street, Room 216, Montpelier, Vermont 05602. Telephone: (802) 828–4573. SUPPLEMENTARY INFORMATION: The FHWA, in cooperation with the Vermont Agency of Transportation (VTrans) and the City of Burlington, will prepare a Limited-Scope Supplemental Environmental Impact Statement (EIS) for the Burlington Southern Connector/ Champlain Parkway between Interstate 189 and Main Street in Burlington, Vermont. khammond on DSKJM1Z7X2PROD with NOTICES SUMMARY: VerDate Sep<11>2014 16:54 Jan 24, 2020 Jkt 250001 The Southern Connector/Champlain Parkway project has a long history with National Environmental Policy Act (NEPA) reviews dating back to the 1970’s. The most recent NEPA document for the project was a Final Supplemental EIS approved by FHWA on September 22, 2009 and a Record of Decision (ROD) issued on January 13, 2010 identifying the Selected Alternative and the reasons for its selection. On October 11, 2019, the FHWA published a notice to rescind the ROD in order to re-evaluate the project’s impacts to low-income and minority populations in accordance with 23 CFR 771.129. Based on the environmental reevaluation, FHWA has determined that a Limited-Scope Supplemental EIS should be prepared for the project to address changes subsequent to 2010 in FHWA guidance and methodology for performing environmental justice analyses, updated demographic information contained in the latest available census data, and to provide additional opportunities for meaningful public involvement. The Supplemental EIS will be limited in the scope of issues, and only assess impacts to low-income and minority populations. Based on the Executive Order 12898 Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations, and FHWA’s ‘‘Guidance on Environmental Justice and NEPA,’’ it is FHWA’s policy to identify and address any disproportionately high and adverse effects of FHWA actions on the health or environment of low-income and minority populations to the greatest extent practicable and permitted by law. The Supplemental EIS review will also address a limited portion of the project along the Pine Street section of the Selected Alternative, between Maple Street and Main Street. Public involvement is a critical component of the National Environmental Policy Act (NEPA) review and Federal-aid highway project development process. A Draft LimitedScope Supplemental EIS will be made available for review and comment by Federal and state resource agencies and the public. A public hearing will be held at an accessible location in Burlington at the time the document is made available. In addition to the public hearing, and as needed during the project’s NEPA review, FHWA will work with VTrans and the City of Burlington to plan, organize and provide public involvement opportunities and project status updates through the project website, local media, and a project open house. Public notice will be given of the time and PO 00000 Frm 00137 Fmt 4703 Sfmt 4703 place of public meetings and hearings through local newspapers and the project website at https:// champlainparkway.com/. No formal scoping meeting is planned at this time. Following approval of the Draft LimitedScope Supplemental EIS, FHWA plans to issue a combined Final LimitedScope Supplemental EIS/ROD. (Catalog of Federal Domestic Assistance Program Number 20.205, Highway Planning and Construction. The regulations implementing Executive Order 12372 regarding intergovernmental consultation on Federal programs and activities apply to this program.) Issued on: January 16, 2020. Matthew R. Hake, Division Administrator, Montpelier, Vermont. [FR Doc. 2020–01333 Filed 1–24–20; 8:45 am] BILLING CODE 4910–22–P DEPARTMENT OF TRANSPORTATION Federal Motor Carrier Safety Administration [Docket No. FMCSA–2012–0154; FMCSA– 2012–0332; FMCSA–2013–0122; FMCSA– 2013–0123] Qualification of Drivers; Exemption Applications; Hearing Federal Motor Carrier Safety Administration (FMCSA), DOT. ACTION: Notice of renewal of exemptions; request for comments. AGENCY: FMCSA announces its decision to renew exemptions for 12 individuals from the hearing requirement in the Federal Motor Carrier Safety Regulations (FMCSRs) for interstate commercial motor vehicle (CMV) drivers. The exemptions enable these hard of hearing and deaf individuals to continue to operate CMVs in interstate commerce. DATES: The exemptions were applicable on January, 14, 2020. The exemptions expire on January 14, 2022. Comments must be received on or before February 26, 2020. ADDRESSES: You may submit comments identified by the Federal Docket Management System (FDMS) Docket No. FMCSA–2012–0154, Docket No. FMCSA–2012–0332, Docket No. FMCSA–2013–0122, or Docket No. FMCSA–2013–0123 using any of the following methods: • Federal eRulemaking Portal: Go to https://www.regulations.gov. Follow the online instructions for submitting comments. • Mail: Docket Operations; U.S. Department of Transportation, 1200 New Jersey Avenue SE, West Building SUMMARY: E:\FR\FM\27JAN1.SGM 27JAN1

Agencies

[Federal Register Volume 85, Number 17 (Monday, January 27, 2020)]
[Notices]
[Page 4758]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-01333]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Federal Highway Administration


Limited-Scope Supplemental Environmental Impact Statement: City 
of Burlington, Chittenden County, Vermont

AGENCY: Federal Highway Administration (FHWA), DOT.

ACTION: Notice of intent to prepare a Limited-Scope Supplemental 
Environmental Impact Statement.

-----------------------------------------------------------------------

SUMMARY: The FHWA is issuing this notice to advise the public that a 
Limited-Scope Supplemental Environmental Impact Statement will be 
prepared for the proposed Southern Connector/Champlain Parkway project 
in the City of Burlington, Chittenden County, Vermont.

FOR FURTHER INFORMATION CONTACT: Rob Sikora, Environmental Program 
Manager, Federal Highway Administration, 87 State Street, Room 216, 
Montpelier, Vermont 05602. Telephone: (802) 828-4573.

SUPPLEMENTARY INFORMATION: The FHWA, in cooperation with the Vermont 
Agency of Transportation (VTrans) and the City of Burlington, will 
prepare a Limited-Scope Supplemental Environmental Impact Statement 
(EIS) for the Burlington Southern Connector/Champlain Parkway between 
Interstate 189 and Main Street in Burlington, Vermont.
    The Southern Connector/Champlain Parkway project has a long history 
with National Environmental Policy Act (NEPA) reviews dating back to 
the 1970's. The most recent NEPA document for the project was a Final 
Supplemental EIS approved by FHWA on September 22, 2009 and a Record of 
Decision (ROD) issued on January 13, 2010 identifying the Selected 
Alternative and the reasons for its selection. On October 11, 2019, the 
FHWA published a notice to rescind the ROD in order to re-evaluate the 
project's impacts to low-income and minority populations in accordance 
with 23 CFR 771.129. Based on the environmental re-evaluation, FHWA has 
determined that a Limited-Scope Supplemental EIS should be prepared for 
the project to address changes subsequent to 2010 in FHWA guidance and 
methodology for performing environmental justice analyses, updated 
demographic information contained in the latest available census data, 
and to provide additional opportunities for meaningful public 
involvement.
    The Supplemental EIS will be limited in the scope of issues, and 
only assess impacts to low-income and minority populations. Based on 
the Executive Order 12898 Federal Actions to Address Environmental 
Justice in Minority Populations and Low-Income Populations, and FHWA's 
``Guidance on Environmental Justice and NEPA,'' it is FHWA's policy to 
identify and address any disproportionately high and adverse effects of 
FHWA actions on the health or environment of low-income and minority 
populations to the greatest extent practicable and permitted by law. 
The Supplemental EIS review will also address a limited portion of the 
project along the Pine Street section of the Selected Alternative, 
between Maple Street and Main Street.
    Public involvement is a critical component of the National 
Environmental Policy Act (NEPA) review and Federal-aid highway project 
development process. A Draft Limited-Scope Supplemental EIS will be 
made available for review and comment by Federal and state resource 
agencies and the public. A public hearing will be held at an accessible 
location in Burlington at the time the document is made available. In 
addition to the public hearing, and as needed during the project's NEPA 
review, FHWA will work with VTrans and the City of Burlington to plan, 
organize and provide public involvement opportunities and project 
status updates through the project website, local media, and a project 
open house. Public notice will be given of the time and place of public 
meetings and hearings through local newspapers and the project website 
at https://champlainparkway.com/. No formal scoping meeting is planned 
at this time. Following approval of the Draft Limited-Scope 
Supplemental EIS, FHWA plans to issue a combined Final Limited-Scope 
Supplemental EIS/ROD.

(Catalog of Federal Domestic Assistance Program Number 20.205, 
Highway Planning and Construction. The regulations implementing 
Executive Order 12372 regarding intergovernmental consultation on 
Federal programs and activities apply to this program.)

    Issued on: January 16, 2020.
Matthew R. Hake,
Division Administrator, Montpelier, Vermont.
[FR Doc. 2020-01333 Filed 1-24-20; 8:45 am]