Southern California Edison Company; Notice of Application Tendered for Filing With the Commission And Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 2121-2122 [2020-00387]
Download as PDF
2121
Federal Register / Vol. 85, No. 9 / Tuesday, January 14, 2020 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 15021–000]
lotter on DSKBCFDHB2PROD with NOTICES
Bard College, New York; Notice of
Application Tendered for Filing With
the Commission and Soliciting
Additional Study Requests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Exemption
from Licensing.
b. Project No.: 15021–000.
c. Date Filed: December 23, 2019.
d. Applicant: Bard College, New York.
e. Name of Project: Annandale Micro
Hydropower Project.
f. Location: On Saw Kill, a tributary of
the Hudson River, in the Town of Red
Hook, Dutchess County, New York. The
project does not occupy federal land.
g. Filed Pursuant to: Public Utility
Regulatory Policies Act of 1978, 16
U.S.C. 2705, 2708 (2018), amended by
the Hydropower Regulatory Efficiency
Act of 2013, Public Law 113–23, 127
Stat. 493 (2013).
h. Applicant Contact: Randy Clum,
Director, Buildings and Grounds, Bard
College, 30 Campus Road, Annandaleon-Hudson, NY 12504; and/or Joel
Herm/Jan Borchert, Current Hydro, Inc.,
P.O. Box 224, Rhinebeck, NY 12572.
i. FERC Contact: Monir Chowdhury at
(202) 502–6736; or email at
monir.chowdhury@ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
VerDate Sep<11>2014
18:41 Jan 13, 2020
Jkt 250001
l. Deadline for filing additional study
requests and requests for cooperating
agency status: March 9, 2020.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, please send a paper
copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. The first
page of any filing should include docket
number P–15021–000.
m. This application is not ready for
environmental analysis at this time.
n. The proposed project would consist
of: (1) An existing 240-foot-long dam
that impounds a 3-acre reservoir; (2)
three new 6-foot-diameter, 9.5-foot-high
concrete cylindrical tanks, each housing
a 4-kilowatt gravitational vortex turbinegenerator unit; (3) a new 240-volt, 60foot-long transmission line; and (4)
appurtenant facilities. The project is
estimated to generate an average of 61
megawatt-hours annually. The applicant
proposes to operate the project in a runof-river mode.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate
(e.g., if there are no deficiencies or a
need for additional information, the
schedule would be shortened).
Issue Notice of Acceptance ..
Issue Scoping Document 1
for comments.
Comments on Scoping Document 1.
Issue Scoping Document 2 (if
necessary).
PO 00000
Frm 00018
Fmt 4703
March 2020.
April 2020.
Issue Notice of Ready for Environmental Analysis.
Commission issues EA .........
June 2020.
December
2020.
Dated: January 8, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–00388 Filed 1–13–20; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 298–081]
Southern California Edison Company;
Notice of Application Tendered for
Filing With the Commission And
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 298–081.
c. Date Filed: December 23, 2019.
d. Applicant: Southern California
Edison Company.
e. Name of Project: Kaweah
Hydroelectric Project.
f. Location: The existing project is
located on the Kaweah River and East
Fork Kaweah River in Tulare County,
California. The project occupies 176.26
acres of public lands administered by
the Bureau of Land Management. The
project incorporates non-project
facilities (diversion structures and water
conveyance facilities) located within
Sequoia National Park, which are
authorized by a National Park Service
special use permit.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Wayne P. Allen,
Principle Manager, Hydro Licensing and
Implementation, Southern California
Edison Company, 1515 Walnut Grove
Avenue, Rosemead, CA 91770, (626)
302–9741 or email at wayne.allen@
sce.com.
i. FERC Contact: Jim Hastreiter, (503)
552–2760 or james.hastreiter@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. The Project Description: The
Kaweah Project has three developments
consisting of the following components.
May 2020.
Kaweah No. 1
June 2020.
This development consists of: (1) A
20-foot-long and 6-foot-high concrete
Sfmt 4703
E:\FR\FM\14JAN1.SGM
14JAN1
2122
Federal Register / Vol. 85, No. 9 / Tuesday, January 14, 2020 / Notices
diversion dam on the East Fork Kaweah
River, (2) a 30,723-foot-long steel flume,
(3) a forebay tank, (4) a 3,340-foot-long
penstock, and (4) a powerhouse with an
impulse turbine rated at 2.25 megawatts
(MW).
Kaweah No. 2
This development consists of: (1) A
161-foot-long and 7-foot-high masonry
diversion dam on the Kaweah River, (2)
a 16,738-foot-long concrete-lined ditch,
(3) a 3,822-foot-long steel flume, (4) a
1,047-foot-long steel pipe, (5) a forebay,
(6) a 1,012-foot-long buried penstock,
and (7) a powerhouse with a Francis
turbine rated at 1.8 MW.
lotter on DSKBCFDHB2PROD with NOTICES
Kaweah No. 3
This development consists of: (1) A
2,580 foot-long concrete-lined flume, (2)
an embankment forebay, (3) a 3,151
foot-long penstock, and (4) a
powerhouse with two impulse turbines
rated at a combined 4.8 MW.
The project has a primary 4.09-milelong transmission line extending from
the Kaweah No. 3 powerhouse to a
substation, and two tap lines (120-footlong and 0.4-mile-long) connecting
Kaweah No. 1 and No. 2 powerhouses,
respectively, to the primary line, and
appurtenant facilities.
Non-project Facilities
The project makes use of several nonproject facilities located in Sequoia
National Park. These facilities comprise
portions of Kaweah No. 1 and No. 3
developments: (1) Two diversion
structures on the Middle Fork and
Marble Fork Kaweah Rivers, (2) a
21,000-foot-long steel flume that is the
initial section of flowline which
conveys water to the Kaweah No. 3
powerhouse, and (3) four small
reservoirs on the East Fork Kaweah
River. These facilities are operated
under a special use permit (Permit No.
PWR–SEKI–6000–2016–015) issued to
SCE by the National Park Service, which
expires on September 8, 2026.
The project developments operate
independently of one another and in a
run-of-river mode. Water captured by
the diversion structures is transported
through connecting conveyance
facilities and penstocks to the
powerhouses for power generation and
then returned to the river at the
tailraces. A portion of the water in
Kaweah No. 1 and No. 2 flowlines is
used to meet downstream contractual
obligations for water delivery with pre1914 water users.
The project forebays and diversion
pools have minimal water storage
capability of about 13 acre-feet (AF).
The four small non-project reservoirs
VerDate Sep<11>2014
18:41 Jan 13, 2020
Jkt 250001
located on tributaries to the East Fork
Kaweah River upstream of the Kaweah
No. 1 diversion dam and within the
Sequoia National Park store a maximum
of 1,153 AF of water, which is used to
generate power at the Kaweah No. 1
powerhouse.
The project diversions create two
bypassed river reaches. The Kaweah No.
1 development bypasses streamflow
around 4.7 miles of the East Fork
Kaweah River from the diversion dam to
the confluence with the Kaweah River.
The Kaweah No. 2 development
bypasses streamflow around 4.1 miles of
the Kaweah River from the diversion
dam to the Kaweah No. 2 powerhouse
tailrace.
The volume and timing of streamflow
diverted is a function of inflow,
minimum flow and ramping rate
requirements of the existing license, and
the flow required to maintain sufficient
head in the water conveyance facilities
(flowlines) to meet downstream water
delivery contractual obligations. The
Kaweah No.1 development flowline has
a maximum hydraulic capacity of 24
cubic feet per second (cfs), the Kaweah
No. 2 development flowline has a
maximum hydraulic capacity of 87 cfs,
and the Kaweah No. 3 development
flowline has a maximum hydraulic
capacity of 97 cfs. To maintain
sufficient head pressure to meet
downstream water deliveries, SCE must
maintain at least 1 cfs flow through the
Kaweah No. 1 development and 3 cfs
through the Kaweah No. 2 development.
SCE is proposing to modify the
existing project boundary to encompass
all facilities necessary for operation and
maintenance of the project, while
removing lands that are not related to
project functions. SCE proposes to
include the existing Kaweah No. 1
forebay access road as a project facility.
SCE proposes to remove part of the
ramping rate requirement when
increasing flows below the Kaweah No.
1 and No. 2 diversion dams. The
ramping rate in the existing license
requires increasing and decreasing flows
below Kaweah No. 1 and No. 2
powerhouses to not be altered at a rate
greater than 30 percent of the existing
stream flow per hour.
SCE also proposes to modify license
article 405 to eliminate the need for
future modification requests to resource
agencies. Historically, SCE has
requested approval from California
Department of Fish and Wildlife and
U.S. Fish and Wildlife Service (FWS) to
temporarily reduce minimum flow
releases below Kaweah No. 1 diversion
and Kaweah No. 2 diversion when
projected inflows were approaching the
combined flow necessary to meet both
PO 00000
Frm 00019
Fmt 4703
Sfmt 9990
water supply and minimum flow release
requirements. These flow modifications
were necessary to ensure compliance
with required minimum flows based on
uncertainty in actual runoff and inflow.
SCE further proposes to remove
required protective measures for the
elderberry shrub, the host plant for the
federally threatened valley elderberry
longhorn beetle (Desmocerus
californicus dimorphus). In 2014, the
FWS determined that Tulare County
was no longer considered within the
valley elderberry longhorn beetle’s
range.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). A copy is also
available for inspection and
reproduction at the address in item (h)
above.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Notice of Acceptance/Notice
of Ready for Environmental
Analysis.
Filing of recommendations,
preliminary terms and conditions, and fishway prescriptions.
Commission issues Draft EA
Comments on Draft EA .........
Modified terms and conditions.
Commission issues Final EA
Target date
February
2020.
April 2020.
October 2020.
November
2020.
January 2021.
April 2021.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: January 8, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020–00387 Filed 1–13–20; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\14JAN1.SGM
14JAN1
Agencies
[Federal Register Volume 85, Number 9 (Tuesday, January 14, 2020)]
[Notices]
[Pages 2121-2122]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-00387]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 298-081]
Southern California Edison Company; Notice of Application
Tendered for Filing With the Commission And Establishing Procedural
Schedule for Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 298-081.
c. Date Filed: December 23, 2019.
d. Applicant: Southern California Edison Company.
e. Name of Project: Kaweah Hydroelectric Project.
f. Location: The existing project is located on the Kaweah River
and East Fork Kaweah River in Tulare County, California. The project
occupies 176.26 acres of public lands administered by the Bureau of
Land Management. The project incorporates non-project facilities
(diversion structures and water conveyance facilities) located within
Sequoia National Park, which are authorized by a National Park Service
special use permit.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Wayne P. Allen, Principle Manager, Hydro
Licensing and Implementation, Southern California Edison Company, 1515
Walnut Grove Avenue, Rosemead, CA 91770, (626) 302-9741 or email at
[email protected].
i. FERC Contact: Jim Hastreiter, (503) 552-2760 or
[email protected].
j. This application is not ready for environmental analysis at this
time.
k. The Project Description: The Kaweah Project has three
developments consisting of the following components.
Kaweah No. 1
This development consists of: (1) A 20-foot-long and 6-foot-high
concrete
[[Page 2122]]
diversion dam on the East Fork Kaweah River, (2) a 30,723-foot-long
steel flume, (3) a forebay tank, (4) a 3,340-foot-long penstock, and
(4) a powerhouse with an impulse turbine rated at 2.25 megawatts (MW).
Kaweah No. 2
This development consists of: (1) A 161-foot-long and 7-foot-high
masonry diversion dam on the Kaweah River, (2) a 16,738-foot-long
concrete-lined ditch, (3) a 3,822-foot-long steel flume, (4) a 1,047-
foot-long steel pipe, (5) a forebay, (6) a 1,012-foot-long buried
penstock, and (7) a powerhouse with a Francis turbine rated at 1.8 MW.
Kaweah No. 3
This development consists of: (1) A 2,580 foot-long concrete-lined
flume, (2) an embankment forebay, (3) a 3,151 foot-long penstock, and
(4) a powerhouse with two impulse turbines rated at a combined 4.8 MW.
The project has a primary 4.09-mile-long transmission line
extending from the Kaweah No. 3 powerhouse to a substation, and two tap
lines (120-foot-long and 0.4-mile-long) connecting Kaweah No. 1 and No.
2 powerhouses, respectively, to the primary line, and appurtenant
facilities.
Non-project Facilities
The project makes use of several non-project facilities located in
Sequoia National Park. These facilities comprise portions of Kaweah No.
1 and No. 3 developments: (1) Two diversion structures on the Middle
Fork and Marble Fork Kaweah Rivers, (2) a 21,000-foot-long steel flume
that is the initial section of flowline which conveys water to the
Kaweah No. 3 powerhouse, and (3) four small reservoirs on the East Fork
Kaweah River. These facilities are operated under a special use permit
(Permit No. PWR-SEKI-6000-2016-015) issued to SCE by the National Park
Service, which expires on September 8, 2026.
The project developments operate independently of one another and
in a run-of-river mode. Water captured by the diversion structures is
transported through connecting conveyance facilities and penstocks to
the powerhouses for power generation and then returned to the river at
the tailraces. A portion of the water in Kaweah No. 1 and No. 2
flowlines is used to meet downstream contractual obligations for water
delivery with pre-1914 water users.
The project forebays and diversion pools have minimal water storage
capability of about 13 acre-feet (AF). The four small non-project
reservoirs located on tributaries to the East Fork Kaweah River
upstream of the Kaweah No. 1 diversion dam and within the Sequoia
National Park store a maximum of 1,153 AF of water, which is used to
generate power at the Kaweah No. 1 powerhouse.
The project diversions create two bypassed river reaches. The
Kaweah No. 1 development bypasses streamflow around 4.7 miles of the
East Fork Kaweah River from the diversion dam to the confluence with
the Kaweah River. The Kaweah No. 2 development bypasses streamflow
around 4.1 miles of the Kaweah River from the diversion dam to the
Kaweah No. 2 powerhouse tailrace.
The volume and timing of streamflow diverted is a function of
inflow, minimum flow and ramping rate requirements of the existing
license, and the flow required to maintain sufficient head in the water
conveyance facilities (flowlines) to meet downstream water delivery
contractual obligations. The Kaweah No.1 development flowline has a
maximum hydraulic capacity of 24 cubic feet per second (cfs), the
Kaweah No. 2 development flowline has a maximum hydraulic capacity of
87 cfs, and the Kaweah No. 3 development flowline has a maximum
hydraulic capacity of 97 cfs. To maintain sufficient head pressure to
meet downstream water deliveries, SCE must maintain at least 1 cfs flow
through the Kaweah No. 1 development and 3 cfs through the Kaweah No. 2
development.
SCE is proposing to modify the existing project boundary to
encompass all facilities necessary for operation and maintenance of the
project, while removing lands that are not related to project
functions. SCE proposes to include the existing Kaweah No. 1 forebay
access road as a project facility.
SCE proposes to remove part of the ramping rate requirement when
increasing flows below the Kaweah No. 1 and No. 2 diversion dams. The
ramping rate in the existing license requires increasing and decreasing
flows below Kaweah No. 1 and No. 2 powerhouses to not be altered at a
rate greater than 30 percent of the existing stream flow per hour.
SCE also proposes to modify license article 405 to eliminate the
need for future modification requests to resource agencies.
Historically, SCE has requested approval from California Department of
Fish and Wildlife and U.S. Fish and Wildlife Service (FWS) to
temporarily reduce minimum flow releases below Kaweah No. 1 diversion
and Kaweah No. 2 diversion when projected inflows were approaching the
combined flow necessary to meet both water supply and minimum flow
release requirements. These flow modifications were necessary to ensure
compliance with required minimum flows based on uncertainty in actual
runoff and inflow.
SCE further proposes to remove required protective measures for the
elderberry shrub, the host plant for the federally threatened valley
elderberry longhorn beetle (Desmocerus californicus dimorphus). In
2014, the FWS determined that Tulare County was no longer considered
within the valley elderberry longhorn beetle's range.
l. Locations of the Application: A copy of the application is
available for review at the Commission in the Public Reference Room or
may be viewed on the Commission's website at https://www.ferc.gov using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). A copy is also available for inspection and reproduction at
the address in item (h) above.
m. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Procedural Schedule: The application will be processed according
to the following preliminary Hydro Licensing Schedule. Revisions to the
schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Notice of Acceptance/Notice of Ready for February 2020.
Environmental Analysis.
Filing of recommendations, preliminary April 2020.
terms and conditions, and fishway
prescriptions.
Commission issues Draft EA................ October 2020.
Comments on Draft EA...................... November 2020.
Modified terms and conditions............. January 2021.
Commission issues Final EA................ April 2021.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: January 8, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-00387 Filed 1-13-20; 8:45 am]
BILLING CODE 6717-01-P