Target set Identification and Development for Nuclear Power Plants, 70578-70579 [2019-27606]
Download as PDF
lotter on DSKBCFDHB2PROD with NOTICES
70578
Federal Register / Vol. 84, No. 246 / Monday, December 23, 2019 / Notices
involving a complete loss of SFP water
inventory, based on an adiabatic heatup
analysis of the limiting fuel assembly for
decay heat, shows that within 10
months after permanent cessation of
power operations, the time for the
limiting fuel assembly to reach 900 °C
is 10 hours after the assemblies have
been uncovered assuming a loss of all
cooling means.
The only analyzed beyond-designbasis accident scenario that progresses
to a condition where a significant offsite
release might occur, involves the highly
unlikely event where the SFP drains in
such a way that all modes of cooling or
heat transfer are assumed to be
unavailable, which is referred to as an
adiabatic heatup of the spent fuel. The
licensee’s analysis of this beyonddesign-basis accident shows that within
10 months after permanent cessation of
power operations, more than 10 hours
would be available between the time the
fuel is initially uncovered (at which
time adiabatic heatup is conservatively
assumed to begin), until the fuel
cladding reaches a temperature of
900 °C, which is the temperature
associated with rapid cladding
oxidation and the potential for a
significant radiological release. This
analysis conservatively does not include
the period of time from the initiating
event causing a loss of SFP water
inventory until all cooling means are
lost.
The NRC staff has verified the
licensee’s analyses and its calculations.
The analyses provide reasonable
assurance that in granting the requested
exemptions to the licensee, there is no
design-basis accident that will result in
an offsite radiological release exceeding
the EPA early phase PAGs at the
exclusion area boundary. In the highly
unlikely event of a beyond-design-basis
accident affecting the SFP that results in
a complete loss of heat removal via all
modes of heat transfer, there will be
over 10 hours available before an offsite
release might occur and, therefore, at
least 10 hours to initiate appropriate
mitigating actions to restore a means of
heat removal to the spent fuel. If a
radiological release were projected to
occur under this highly unlikely
scenario, a minimum of 10 hours is
considered sufficient time for offsite
authorities to implement protective
actions using a CEMP approach to
protect the health and safety of the
public.
Exemptions from the offsite EP
requirements in 10 CFR part 50 have
previously been approved by the NRC
when the site-specific analyses show
that at least 10 hours is available
following a loss of SFP coolant
VerDate Sep<11>2014
19:32 Dec 20, 2019
Jkt 250001
inventory with no air cooling (or other
methods of removing decay heat) until
cladding of the hottest fuel assembly
reaches the rapid oxidation temperature.
The NRC staff concluded in its
previously granted exemptions, as it
does with the licensee’s requested EP
exemptions, that if a minimum of 10
hours is available to initiate mitigative
actions consistent with plant
conditions, or if needed, for offsite
authorities to implement protective
actions using a CEMP approach, then
formal offsite radiological emergency
preparedness plans, required under 10
CFR part 50, are not necessary at
permanently shutdown and defueled
facilities.
Additionally, Pilgrim committed to
maintaining SFP makeup strategies in
its letters to the NRC dated November
30 and December 4, 2018, and February
14 and February 18, 2019. The multiple
strategies for providing makeup to the
SFP include: Using existing plant
systems for inventory makeup; an
internal strategy that relies on the fire
protection system with redundant
pumps (one diesel-driven and electric
motor-driven); and onsite diesel fire
truck that can take suction from the
Cape Cod Bay. These strategies will
continue to be required as License
Condition 3.K, ‘‘Mitigation Strategy
License Condition,’’ of Renewed Facility
License No. DPR–35 for Pilgrim.
Considering the very low probability of
beyond-design-basis accidents affecting
the SFP, these diverse strategies provide
multiple methods to obtain additional
makeup or spray to the SFP before the
onset of any postulated offsite
radiological release.
For all of the reasons stated above, the
NRC staff finds that the licensee’s
requested exemptions meet the
underlying purpose of all of the
standards in 10 CFR 50.47(b), and
requirements in 10 CFR 50.47(c)(2) and
10 CFR part 50, Appendix E, and satisfy
the special circumstances provision in
10 CFR 50.12(a)(2)(ii) in view of the
greatly reduced risk of offsite
radiological consequences associated
with the permanently shutdown and
defueled state of the Pilgrim facility 10
months after the facility permanently
ceases operation.
The NRC staff has concluded that the
exemptions being granted by this action
will maintain an acceptable level of
emergency preparedness at Pilgrim and,
if needed, that there is reasonable
assurance that adequate offsite
protective measures can and will be
taken by State and local government
agencies using a CEMP approach in the
highly unlikely event of a radiological
emergency at Pilgrim. Since the
PO 00000
Frm 00086
Fmt 4703
Sfmt 4703
underlying purpose of the rules, as
exempted, would continue to be
achieved, even with the elimination of
the requirements under 10 CFR part 50
to maintain formal offsite radiological
emergency preparedness plans and the
reduction in the scope of the onsite EP
activities at Pilgrim, the special
circumstances required by 10 CFR
50.12(a)(2)(ii) exist.
E. Environmental Considerations
In accordance with 10 CFR 51.31(a),
the Commission has determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment as discussed in the
NRC staff’s Finding of No Significant
Impact and associated Environmental
Assessment published in the Federal
Register on December 18, 2019 (84 FR
69396).
IV. Conclusions
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12, the licensee’s request for
exemptions from certain EP
requirements in 10 CFR 50.47(b), 10
CFR 50.47(c)(2), and 10 CFR part 50,
Appendix E, Section IV, and as
summarized in Enclosure 2 to SECY–
19–0078, are authorized by law, will not
present an undue risk to the public
health and safety, and are consistent
with the common defense and security.
Also, special circumstances are present.
Therefore, the Commission hereby
grants the licensee’s exemptions from
certain EP requirements in 10 CFR
50.47(b), 10 CFR 50.47(c)(2), and 10 CFR
part 50, Appendix E, Section IV, as
discussed and evaluated in detail in the
NRC staff’s safety evaluation dated
December 18, 2019. The exemptions are
effective as of 10 months after
permanent cessation of power
operations.
Dated at Rockville, Maryland, this 18th day
of December, 2019.
For the Nuclear Regulatory Commission.
Craig G. Erlanger,
Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2019–27658 Filed 12–20–19; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2019–0233]
Target set Identification and
Development for Nuclear Power Plants
Nuclear Regulatory
Commission.
AGENCY:
E:\FR\FM\23DEN1.SGM
23DEN1
Federal Register / Vol. 84, No. 246 / Monday, December 23, 2019 / Notices
ACTION:
Regulatory guide; issuance.
The U.S. Nuclear Regulatory
Commission (NRC) is issuing Revision 1
to Regulatory Guide (RG) 5.81, ‘‘Target
set Identification and Development for
Nuclear Power Plants,’’ as a final RG.
RG 5.81 provides guidance the NRC
considers acceptable for applicant or
licensee analysis, development,
documentation, and reevaluation of
target set elements and target sets,
including preventive operator actions
that may be credited to prevent core
damage (e.g., non-localized fuel melting,
and/or core destruction) or loss of spent
fuel coolant and exposure of spent fuel.
This revision of the guide (Revision 1)
clarifies issues that have been identified
through interactions with stakeholders
and inspection activities since the
original publication of the guide.
DATES: Revision 1 to RG 5.81 is available
on December 23, 2019.
ADDRESSES: Revision 1 to RG 5.81
contains Official Use Only—Security
Related Information (OUO–SRI).
Therefore, this RG is being withheld
from public disclosure, but is available
to those affected licensees, stakeholders
who have established a need to know
and cleared stakeholders who have
access authorization. For access to RG
5.81, contact the individuals listed in
the FOR FURTHER INFORMATION CONTACT
section.
SUMMARY:
FOR FURTHER INFORMATION CONTACT:
Wesley Held, Office of Nuclear Security
and Insident Response, U.S. Nuclear
Regulatory Commission, telephone:
301–287–3591, email: Wesley.Held@
nrc.gov; or Mekonen Bayssie,Office of
Nuclear Regulatory Research; telephone:
301–415–1699, email: Mekonen.
Bayssie@nrc.gov. Alternatively, you may
make suggestions or comments on RG
5.81 via email to: RegulatoryGuide
DevelopmentBranch.Resource@nrc.gov.
Please do not include any potentially
classified or sensitive information in
your email.
SUPPLEMENTARY INFORMATION:
lotter on DSKBCFDHB2PROD with NOTICES
I. Discussion
The NRC is issuing a revision to an
existing guide in the NRC’s ‘‘Regulatory
Guide’’ series. This series was
developed to describe and make
available to the public information
regarding methods that are acceptable to
the NRC staff for implementing specific
parts of the agency’s regulations,
techniques that the NRC staff uses in
evaluating specific issues or postulated
events, and data that the NRC staff
needs in its review of applications for
permits and licenses.
VerDate Sep<11>2014
19:32 Dec 20, 2019
Jkt 250001
Regulatory Guide 5.81 provides
licensees with guidance on meeting the
requirements described in section
73.55(f) of title 10 of the Code of Federal
Regulations (10 CFR),’’Target Sets.’’
Specifically, it sets forth approaches
that the NRC considers acceptable for
use by applicants or licensees in
analyzing, developing, documenting,
and evaluating target set elements and
target sets, including operator actions
that may be credited to prevent core
damage (e.g., non-localized fuel melting,
and/or core destruction) or loss of spent
fuel coolant and exposure of spent fuel.
This revision of RG 5.81 (Revision 1)
incorporates lessons learned from
operating experience. Specifically, this
revision clarifies issues that have been
identified through interactions with
stakeholders and inspection activities
since the original publication of the
guide.
II. Additional Information
Regulatory Guide 5.81 contains OUO–
SRI information. Accordingly, this RG is
being withheld from public disclosure.
It will be made available to those
affected licensees and stakeholders who
have an established need-to-know for
access to the RG. The NRC did not
announce the availability of the draft RG
for public comment because the guide
contains OUO–SRI information.
Nonetheless, the NRC is issuing this
notice to inform the public of the
issuance of this revision to the RG.
On August 14, 2018, the NRC issued
a memorandum (ADAMS Accession No.
ML19324F694) transmitting the draft
regulatory guide for comment to
stakeholders who have an established
need-to-know for access to the
document. The stakeholders’ comment
period closed on October, 15, 2018. The
NRC received 20 comments from
stakeholders. The comments and the
associated agency responses to the
publc comments contain OUO–SRI
information and are not available to the
public. These comment responses can
be obtained by those licensees and
stakeholders who have established a
need-to-know for access to the
regulatory guide. For access to RG 5.81
or the comments and comment
resolution documment, contact the
individuals listed in the FOR FURTHER
INFORMATION CONTACT section.
III. Congressional Review Act
This RG is a rule as defined in the
Congressional Review Act (5 U.S.C.
801–808). However, the Office of
Management and Budget has not found
it to be a major rule as defined in the
Congressional Review Act.
PO 00000
Frm 00087
Fmt 4703
Sfmt 4703
70579
IV. Backfitting
This RG provides applicants or
licensees with guidance to meet the
requirements set forth in 10 CFR 73.55,
‘‘Requirements for Physical Protection
of Licensed Activities in Nuclear Power
Reactors Against Radiological
Sabotage.’’ Issuance of this regulatory
guide does not constitute backfitting as
defined in 10 CFR 50.109, ‘‘Backfitting,’’
or affect issue finality of any approval
issued under 10 CFR part 52, Licenses,
Certificates, and Approvals for Nuclear
Power Plants,’’ because as explained in
Section D., ‘‘Implementation,’’ of the
regulatory guide, NRC staff does not
intend to use the guidance in this
regulatory guide to support NRC staff
actions in a manner that would
constitute backfitting. If, in the future,
the NRC seeks to impose a position in
this regulatory guidein a manner that
constitutes backfitting or affects the
issue finality for a Part 52 approval,
then the NRC will address the
backfitting provision in 10 CFR 50.109
or the applicable issue finality provision
in Part 52 respectively.
Dated at Rockville, Maryland, this 17th day
of December 2019.
For the Nuclear Regulatory Commission.
Thomas H. Boyce,
Chief, Regulatory Guidance and Generic
Issues Branch, Division of Engineering, Office
of Nuclear Regulatory Research.
[FR Doc. 2019–27606 Filed 12–20–19; 8:45 am]
BILLING CODE 7590–01–P
OFFICE OF PERSONNEL
MANAGEMENT
President’s Commission on White
House Fellowships Advisory
Committee: Closed Meeting
President’s Commission on
White House Fellowships, Office of
Personnel Management.
ACTION: Notice of meeting.
AGENCY:
The President’s Commission
on White House Fellowships (PCWHF)
was established by an Executive Order
in 1964. The PCWHF is an advisory
committee composed of Special
Government Employees appointed by
the President.
The meeting is closed.
Name of Committee: President’s
Commission on White House
Fellowships Mid-Year Meeting.
Date: January 15–16, 2020.
Time: 8:00 a.m.–5:30 p.m.
Place Eisenhower Executive Office
Building, 1650 Pennsylvania Ave. NW,
Washington, DC 20502.
Agenda: The Commission holds a
mid-year meeting to talk with current
SUMMARY:
E:\FR\FM\23DEN1.SGM
23DEN1
Agencies
[Federal Register Volume 84, Number 246 (Monday, December 23, 2019)]
[Notices]
[Pages 70578-70579]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-27606]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2019-0233]
Target set Identification and Development for Nuclear Power
Plants
AGENCY: Nuclear Regulatory Commission.
[[Page 70579]]
ACTION: Regulatory guide; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing
Revision 1 to Regulatory Guide (RG) 5.81, ``Target set Identification
and Development for Nuclear Power Plants,'' as a final RG. RG 5.81
provides guidance the NRC considers acceptable for applicant or
licensee analysis, development, documentation, and reevaluation of
target set elements and target sets, including preventive operator
actions that may be credited to prevent core damage (e.g., non-
localized fuel melting, and/or core destruction) or loss of spent fuel
coolant and exposure of spent fuel. This revision of the guide
(Revision 1) clarifies issues that have been identified through
interactions with stakeholders and inspection activities since the
original publication of the guide.
DATES: Revision 1 to RG 5.81 is available on December 23, 2019.
ADDRESSES: Revision 1 to RG 5.81 contains Official Use Only--Security
Related Information (OUO-SRI). Therefore, this RG is being withheld
from public disclosure, but is available to those affected licensees,
stakeholders who have established a need to know and cleared
stakeholders who have access authorization. For access to RG 5.81,
contact the individuals listed in the FOR FURTHER INFORMATION CONTACT
section.
FOR FURTHER INFORMATION CONTACT: Wesley Held, Office of Nuclear
Security and Insident Response, U.S. Nuclear Regulatory Commission,
telephone: 301-287-3591, email: [email protected]; or Mekonen
Bayssie,Office of Nuclear Regulatory Research; telephone: 301-415-1699,
email: [email protected]. Alternatively, you may make suggestions
or comments on RG 5.81 via email to:
[email protected]. Please do not
include any potentially classified or sensitive information in your
email.
SUPPLEMENTARY INFORMATION:
I. Discussion
The NRC is issuing a revision to an existing guide in the NRC's
``Regulatory Guide'' series. This series was developed to describe and
make available to the public information regarding methods that are
acceptable to the NRC staff for implementing specific parts of the
agency's regulations, techniques that the NRC staff uses in evaluating
specific issues or postulated events, and data that the NRC staff needs
in its review of applications for permits and licenses.
Regulatory Guide 5.81 provides licensees with guidance on meeting
the requirements described in section 73.55(f) of title 10 of the Code
of Federal Regulations (10 CFR),''Target Sets.'' Specifically, it sets
forth approaches that the NRC considers acceptable for use by
applicants or licensees in analyzing, developing, documenting, and
evaluating target set elements and target sets, including operator
actions that may be credited to prevent core damage (e.g., non-
localized fuel melting, and/or core destruction) or loss of spent fuel
coolant and exposure of spent fuel.
This revision of RG 5.81 (Revision 1) incorporates lessons learned
from operating experience. Specifically, this revision clarifies issues
that have been identified through interactions with stakeholders and
inspection activities since the original publication of the guide.
II. Additional Information
Regulatory Guide 5.81 contains OUO-SRI information. Accordingly,
this RG is being withheld from public disclosure. It will be made
available to those affected licensees and stakeholders who have an
established need-to-know for access to the RG. The NRC did not announce
the availability of the draft RG for public comment because the guide
contains OUO-SRI information. Nonetheless, the NRC is issuing this
notice to inform the public of the issuance of this revision to the RG.
On August 14, 2018, the NRC issued a memorandum (ADAMS Accession
No. ML19324F694) transmitting the draft regulatory guide for comment to
stakeholders who have an established need-to-know for access to the
document. The stakeholders' comment period closed on October, 15, 2018.
The NRC received 20 comments from stakeholders. The comments and the
associated agency responses to the publc comments contain OUO-SRI
information and are not available to the public. These comment
responses can be obtained by those licensees and stakeholders who have
established a need-to-know for access to the regulatory guide. For
access to RG 5.81 or the comments and comment resolution documment,
contact the individuals listed in the FOR FURTHER INFORMATION CONTACT
section.
III. Congressional Review Act
This RG is a rule as defined in the Congressional Review Act (5
U.S.C. 801-808). However, the Office of Management and Budget has not
found it to be a major rule as defined in the Congressional Review Act.
IV. Backfitting
This RG provides applicants or licensees with guidance to meet the
requirements set forth in 10 CFR 73.55, ``Requirements for Physical
Protection of Licensed Activities in Nuclear Power Reactors Against
Radiological Sabotage.'' Issuance of this regulatory guide does not
constitute backfitting as defined in 10 CFR 50.109, ``Backfitting,'' or
affect issue finality of any approval issued under 10 CFR part 52,
Licenses, Certificates, and Approvals for Nuclear Power Plants,''
because as explained in Section D., ``Implementation,'' of the
regulatory guide, NRC staff does not intend to use the guidance in this
regulatory guide to support NRC staff actions in a manner that would
constitute backfitting. If, in the future, the NRC seeks to impose a
position in this regulatory guidein a manner that constitutes
backfitting or affects the issue finality for a Part 52 approval, then
the NRC will address the backfitting provision in 10 CFR 50.109 or the
applicable issue finality provision in Part 52 respectively.
Dated at Rockville, Maryland, this 17th day of December 2019.
For the Nuclear Regulatory Commission.
Thomas H. Boyce,
Chief, Regulatory Guidance and Generic Issues Branch, Division of
Engineering, Office of Nuclear Regulatory Research.
[FR Doc. 2019-27606 Filed 12-20-19; 8:45 am]
BILLING CODE 7590-01-P