Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments: Green Mountain Power Corporation, 67937 [2019-26765]
Download as PDF
Federal Register / Vol. 84, No. 239 / Thursday, December 12, 2019 / Notices
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title COMMENTS, PROTEST,
MOTION TO INTERVENE,
RECOMMENDATIONS, or TERMS AND
CONDITIONS as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervenor must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
Dated: December 6, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–26763 Filed 12–11–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12766–007]
khammond on DSKJM1Z7X2PROD with NOTICES
Notice of Application Tendered for
Filing With the Commission and
Soliciting Additional Study Requests
and Establishing Procedural Schedule
for Relicensing and a Deadline for
Submission of Final Amendments:
Green Mountain Power Corporation
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New License
for Transmission Line Project.
b. Project No.: 12766–007.
c. Date filed: November 22, 2019.
d. Applicant: Green Mountain Power
Corporation (Green Mountain Power).
e. Name of Project: Clay Hill Road
Line 66 Transmission Project.
VerDate Sep<11>2014
17:56 Dec 11, 2019
Jkt 250001
f. Location: Along Clay Hill Road in
the town of Hartland, Windsor County,
Vermont. No federal lands are occupied
by the project works or located within
the project boundary.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: John Greenan,
Green Mountain Power Corporation,
2152 Post Road, Rutland, VT 05701;
Phone at (802) 770–2195, or email at
John.Greenan@
greenmountainpower.com.
i. FERC Contact: Bill Connelly at (202)
502–8587, or william.connelly@ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See 94
FERC 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: January 21, 2020.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, please send a paper
copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. The first
page of any filing should include docket
number P–12766–007.
m. The application is not ready for
environmental analysis at this time.
n. Project Description: The existing
Clay Hill Road Line 66 Transmission
Project consists of: (1) A 2.3-mile-long,
12.5-kilovolt, three-phase electrical line
mounted on top of Green Mountain
PO 00000
Frm 00027
Fmt 4703
Sfmt 9990
67937
Power Corporation’s regional
distribution line (Line 66) along Clay
Hill Road from Pole 115 to 62x; and (2)
appurtenant facilities. The project
serves as a primary transmission line for
the North Hartland Project No. 2816.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s website at
https://www.ferc.gov using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support. A copy is also available for
inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
preliminary schedule. Revisions to the
schedule will be made as appropriate.
Issue Deficiency Letter (if necessary)—
January 2020
Request Additional Information—
January 2020
Issue Acceptance Letter—April 2020
Issue Scoping Document 1 for
comments—May 2020
Request Additional Information (if
necessary)—July 2020
Issue Scoping Document 2—August
2020
Issue Notice of Ready for Environmental
Analysis—August 2020
Commission issues Environmental
Assessment—February 2021
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of the notice of ready for
environmental analysis.
Dated: December 6, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–26765 Filed 12–11–19; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\12DEN1.SGM
12DEN1
Agencies
[Federal Register Volume 84, Number 239 (Thursday, December 12, 2019)]
[Notices]
[Page 67937]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-26765]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12766-007]
Notice of Application Tendered for Filing With the Commission and
Soliciting Additional Study Requests and Establishing Procedural
Schedule for Relicensing and a Deadline for Submission of Final
Amendments: Green Mountain Power Corporation
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New License for Transmission Line Project.
b. Project No.: 12766-007.
c. Date filed: November 22, 2019.
d. Applicant: Green Mountain Power Corporation (Green Mountain
Power).
e. Name of Project: Clay Hill Road Line 66 Transmission Project.
f. Location: Along Clay Hill Road in the town of Hartland, Windsor
County, Vermont. No federal lands are occupied by the project works or
located within the project boundary.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: John Greenan, Green Mountain Power
Corporation, 2152 Post Road, Rutland, VT 05701; Phone at (802) 770-
2195, or email at [email protected].
i. FERC Contact: Bill Connelly at (202) 502-8587, or
[email protected].
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See 94 FERC 61,076
(2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: January 21, 2020.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at [email protected], (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, please send a paper copy
to: Secretary, Federal Energy Regulatory Commission, 888 First Street
NE, Washington, DC 20426. The first page of any filing should include
docket number P-12766-007.
m. The application is not ready for environmental analysis at this
time.
n. Project Description: The existing Clay Hill Road Line 66
Transmission Project consists of: (1) A 2.3-mile-long, 12.5-kilovolt,
three-phase electrical line mounted on top of Green Mountain Power
Corporation's regional distribution line (Line 66) along Clay Hill Road
from Pole 115 to 62x; and (2) appurtenant facilities. The project
serves as a primary transmission line for the North Hartland Project
No. 2816.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's website at https://www.ferc.gov using the eLibrary link.
Enter the docket number excluding the last three digits in the docket
number field to access the document. For assistance, contact FERC
Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. Procedural schedule and final amendments: The application will
be processed according to the following preliminary schedule. Revisions
to the schedule will be made as appropriate.
Issue Deficiency Letter (if necessary)--January 2020
Request Additional Information--January 2020
Issue Acceptance Letter--April 2020
Issue Scoping Document 1 for comments--May 2020
Request Additional Information (if necessary)--July 2020
Issue Scoping Document 2--August 2020
Issue Notice of Ready for Environmental Analysis--August 2020
Commission issues Environmental Assessment--February 2021
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: December 6, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-26765 Filed 12-11-19; 8:45 am]