Kaukauna Utilities; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 67263 [2019-26459]

Download as PDF Federal Register / Vol. 84, No. 236 / Monday, December 9, 2019 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 10674–017] khammond on DSKJM1Z7X2PROD with NOTICES Kaukauna Utilities; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New Major License. b. Project No.: 10674–017. c. Date filed: February 14, 2019. d. Applicant: Kaukauna Utilities. e. Name of Project: Kimberly Hydroelectric Project (Kimberly Project). f. Location: The Kimberly Project is located at the U.S. Army Corps of Engineers’ (Corps) Cedars Dam on the Lower Fox River in the Village of Kimberly in Outagamie County, Wisconsin. The proposed project boundary would include 0.0225 acres of federal land. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)–825(r). h. Applicant Contact: Mike Pedersen, Manager of Generation and Operations, Kaukauna Utilities, 777 Island Street, P.O. Box 1777, Kaukauna, WI 54130– 7077, (902) 766–05721. i. FERC Contact: Colleen Corballis, (202) 502–8598, colleen.corballis@ ferc.gov. j. Deadline for filing motions to intervene and protests, comments, recommendations, terms and conditions, and prescriptions: 60 days from the issuance date of this notice; reply comments are due 105 days from the issuance date of this notice. The Commission strongly encourages electronic filing. Please file motions to intervene and protests, comments, recommendations, terms and conditions, and prescriptions using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at VerDate Sep<11>2014 17:22 Dec 06, 2019 Jkt 250001 FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–10674–017. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted and is ready for environmental analysis at this time. l. The Kimberly Project consists of: (1) A 161-foot-long, 43-foot-wide, 61-foothigh reinforced concrete and brick masonry powerhouse located at the south abutment of the Corps’ Cedars Dam and containing three turbinegenerator units each rated at 723 kilowatts for a total installed capacity of 2.170 megawatts; (2) a 2.4-kilovolts (kV) to 34.5-kV step-up transformer; (3) a 320-foot-long, 2.4-kV transmission line; and (4) appurtenant facilities. The project is directly connected to a 34.5kV local distribution line, which is not part of the project. The average annual generation was 12,324,827 kilowatthours for the period 2011 to 2017. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. n. Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, and .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received PO 00000 Frm 00010 Fmt 4703 Sfmt 4703 67263 on or before the specified comment date for the particular application. All filings must (1) bear in all capital letters the title ‘‘PROTEST’’, ‘‘MOTION TO INTERVENE’’, ‘‘COMMENTS’’, ‘‘REPLY COMMENTS’’, ‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions or prescriptions must set forth their evidentiary basis and otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. o. A license applicant must file no later than 60 days following the date of issuance of this notice: (1) A copy of the water quality certification; (2) a copy of the request for certification, including proof of the date on which the certifying agency received the request; or (3) evidence of waiver of water quality certification. p. Procedural schedule: The application will be processed according to the following schedule. Revisions to the schedule will be made as appropriate. Commission issues Environmental Assessment—June 2020 Comments on Environmental Assessment—July 2020 Dated: December 3, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–26459 Filed 12–6–19; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\09DEN1.SGM 09DEN1

Agencies

[Federal Register Volume 84, Number 236 (Monday, December 9, 2019)]
[Notices]
[Page 67263]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-26459]



[[Page 67263]]

=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 10674-017]


Kaukauna Utilities; Notice of Application Accepted for Filing, 
Soliciting Motions To Intervene and Protests, Ready for Environmental 
Analysis, and Soliciting Comments, Recommendations, Terms and 
Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Major License.
    b. Project No.: 10674-017.
    c. Date filed: February 14, 2019.
    d. Applicant: Kaukauna Utilities.
    e. Name of Project: Kimberly Hydroelectric Project (Kimberly 
Project).
    f. Location: The Kimberly Project is located at the U.S. Army Corps 
of Engineers' (Corps) Cedars Dam on the Lower Fox River in the Village 
of Kimberly in Outagamie County, Wisconsin. The proposed project 
boundary would include 0.0225 acres of federal land.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Mike Pedersen, Manager of Generation and 
Operations, Kaukauna Utilities, 777 Island Street, P.O. Box 1777, 
Kaukauna, WI 54130-7077, (902) 766-05721.
    i. FERC Contact: Colleen Corballis, (202) 502-8598, 
[email protected].
    j. Deadline for filing motions to intervene and protests, comments, 
recommendations, terms and conditions, and prescriptions: 60 days from 
the issuance date of this notice; reply comments are due 105 days from 
the issuance date of this notice.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene and protests, comments, recommendations, terms and 
conditions, and prescriptions using the Commission's eFiling system at 
https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE, Washington, DC 20426. The first page of any filing should 
include docket number P-10674-017.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted and is ready for 
environmental analysis at this time.
    l. The Kimberly Project consists of: (1) A 161-foot-long, 43-foot-
wide, 61-foot-high reinforced concrete and brick masonry powerhouse 
located at the south abutment of the Corps' Cedars Dam and containing 
three turbine-generator units each rated at 723 kilowatts for a total 
installed capacity of 2.170 megawatts; (2) a 2.4-kilovolts (kV) to 
34.5-kV step-up transformer; (3) a 320-foot-long, 2.4-kV transmission 
line; and (4) appurtenant facilities. The project is directly connected 
to a 34.5-kV local distribution line, which is not part of the project. 
The average annual generation was 12,324,827 kilowatt-hours for the 
period 2011 to 2017.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's website at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    n. Anyone may submit comments, a protest, or a motion to intervene 
in accordance with the requirements of Rules of Practice and Procedure, 
18 CFR 385.210, .211, and .214. In determining the appropriate action 
to take, the Commission will consider all protests or other comments 
filed, but only those who file a motion to intervene in accordance with 
the Commission's Rules may become a party to the proceeding. Any 
comments, protests, or motions to intervene must be received on or 
before the specified comment date for the particular application.
    All filings must (1) bear in all capital letters the title 
``PROTEST'', ``MOTION TO INTERVENE'', ``COMMENTS'', ``REPLY COMMENTS'', 
``RECOMMENDATIONS,'' ``TERMS AND CONDITIONS,'' or ``PRESCRIPTIONS;'' 
(2) set forth in the heading the name of the applicant and the project 
number of the application to which the filing responds; (3) furnish the 
name, address, and telephone number of the person protesting or 
intervening; and (4) otherwise comply with the requirements of 18 CFR 
385.2001 through 385.2005. All comments, recommendations, terms and 
conditions or prescriptions must set forth their evidentiary basis and 
otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may 
obtain copies of the application directly from the applicant. A copy of 
any protest or motion to intervene must be served upon each 
representative of the applicant specified in the particular 
application. A copy of all other filings in reference to this 
application must be accompanied by proof of service on all persons 
listed in the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    o. A license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification.
    p. Procedural schedule: The application will be processed according 
to the following schedule. Revisions to the schedule will be made as 
appropriate.

Commission issues Environmental Assessment--June 2020
Comments on Environmental Assessment--July 2020


    Dated: December 3, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-26459 Filed 12-6-19; 8:45 am]
 BILLING CODE 6717-01-P