Mountain Valley Pipeline, LLC; Notice of Revised Schedule for Environmental Review of the Southgate Project, 65806 [2019-25917]
Download as PDF
65806
Federal Register / Vol. 84, No. 230 / Friday, November 29, 2019 / Notices
was sent to affected landowners; federal,
state, and local government
representatives and agencies; elected
officials; Native American tribes; other
interested parties; and local libraries
and newspapers. All substantive
comments in response to the NOI will
be addressed in the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP19–512), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: November 22, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–25915 Filed 11–27–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–14–000]
khammond on DSKJM1Z7X2PROD with NOTICES
Mountain Valley Pipeline, LLC; Notice
of Revised Schedule for Environmental
Review of the Southgate Project
This notice identifies the Federal
Energy Regulatory Commission staff’s
revised schedule for the completion of
the final Environmental Impact
Statement (EIS) for Mountain Valley
Pipeline, LLC’s Southgate Project. The
first notice of schedule, issued on March
15, 2019, identified December 19, 2019
as the final EIS issuance date. However,
Mountain Valley filed additional
VerDate Sep<11>2014
16:49 Nov 27, 2019
Jkt 250001
information on October 23, 2019 that
included changes to the route and
revised data for resource impacts.
Because the supplemental information
needs further review and required an
additional notice to the landowners
affected by the route changes, issued on
November 15, 2019, Commission staff
has revised the schedule for issuance of
the final EIS.
Schedule for Environmental Review
Issuance of Notice of Availability of the
final EIS February 14, 2020
90-day Federal Authorization Decision
Deadline May 14, 2020
If a schedule change becomes
necessary, an additional notice will be
provided so that the relevant agencies
are kept informed of the project’s
progress.
Additional Information
In order to receive notification of the
issuance of the final EIS and to keep
track of all formal issuances and
submittals in specific dockets, the
Commission offers a free service called
eSubscription. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries, and direct links
to the documents. Go to www.ferc.gov/
docs-filing/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP19–14), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: November 22, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–25917 Filed 11–27–19; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC20–4–000.
Applicants: Tenaska Alabama II
Partners, L.P., Alabama Power
Company.
Description: Response of Southern
Company Services, Inc. on behalf of
Alabama Power Company, et al. to
October 23, 2019 letter requesting
additional information.
Filed Date: 11/21/19.
Accession Number: 20191121–5178.
Comments Due: 5 p.m. ET 12/5/19.
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG20–46–000.
Applicants: Acorn I Energy Storage,
LLC.
Description: Self-Certification of EWG
status of Acorn I Energy Storage, LLC.
Filed Date: 11/22/19.
Accession Number: 20191122–5057.
Comments Due: 5 p.m. ET 12/13/19.
Docket Numbers: EG20–47–000.
Applicants: Wildcat I Energy Storage,
LLC.
Description: Self-Certification of EWG
status of Wildcat I Energy Storage, LLC.
Filed Date: 11/22/19.
Accession Number: 20191122–5058.
Comments Due: 5 p.m. ET 12/13/19.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER18–552–002.
Applicants: Clean Energy Future—
Lordstown, LLC.
Description: Supplement to April 1,
2019 Notice of Non-Material Change in
Status of Clean Energy Future—
Lordstown, LLC.
Filed Date: 11/21/19.
Accession Number: 20191121–5181.
Comments Due: 5 p.m. ET 12/12/19.
Docket Numbers: ER20–28–002.
Applicants: MidAmerican Energy
Company.
Description: Tariff Amendment:
Second Amendment of Pending Tariff
Filing in ER20–28 to be effective 11/1/
2019.
Filed Date: 11/22/19.
Accession Number: 20191122–5001.
Comments Due: 5 p.m. ET 12/13/19.
Docket Numbers: ER20–270–001.
Applicants: Dynegy Oakland, LLC.
Description: Tariff Amendment: Errata
to Annual Reliability Must Run
E:\FR\FM\29NON1.SGM
29NON1
Agencies
[Federal Register Volume 84, Number 230 (Friday, November 29, 2019)]
[Notices]
[Page 65806]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-25917]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP19-14-000]
Mountain Valley Pipeline, LLC; Notice of Revised Schedule for
Environmental Review of the Southgate Project
This notice identifies the Federal Energy Regulatory Commission
staff's revised schedule for the completion of the final Environmental
Impact Statement (EIS) for Mountain Valley Pipeline, LLC's Southgate
Project. The first notice of schedule, issued on March 15, 2019,
identified December 19, 2019 as the final EIS issuance date. However,
Mountain Valley filed additional information on October 23, 2019 that
included changes to the route and revised data for resource impacts.
Because the supplemental information needs further review and required
an additional notice to the landowners affected by the route changes,
issued on November 15, 2019, Commission staff has revised the schedule
for issuance of the final EIS.
Schedule for Environmental Review
Issuance of Notice of Availability of the final EIS February 14, 2020
90-day Federal Authorization Decision Deadline May 14, 2020
If a schedule change becomes necessary, an additional notice will
be provided so that the relevant agencies are kept informed of the
project's progress.
Additional Information
In order to receive notification of the issuance of the final EIS
and to keep track of all formal issuances and submittals in specific
dockets, the Commission offers a free service called eSubscription.
This can reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP19-14), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC
website also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rule makings.
Dated: November 22, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-25917 Filed 11-27-19; 8:45 am]