Texas Eastern Transmission, L.P.; Notice of Schedule for Environmental Review of the Cameron Extension Project, 65805-65806 [2019-25915]
Download as PDF
Federal Register / Vol. 84, No. 230 / Friday, November 29, 2019 / Notices
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–14973–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s website at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–14973) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: November 22, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–25909 Filed 11–27–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER20–443–000]
Dated: November 22, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
khammond on DSKJM1Z7X2PROD with NOTICES
Acorn I Energy Storage, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
[FR Doc. 2019–25911 Filed 11–27–19; 8:45 am]
BILLING CODE 6717–01–P
This is a supplemental notice in the
above-referenced Rosewater Acorn I
Energy Storage, LLC’s application for
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
VerDate Sep<11>2014
16:49 Nov 27, 2019
Jkt 250001
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is December 12,
2019.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an eSubscription link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–512–000]
Texas Eastern Transmission, L.P.;
Notice of Schedule for Environmental
Review of the Cameron Extension
Project
On September 26, 2019, Texas Eastern
Transmission, L.P. (Texas Eastern) filed
an application in Docket No. CP19–512–
000 requesting a Certificate of Public
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
65805
Convenience and Necessity pursuant to
Section 7(c) of the Natural Gas Act to
construct and operate certain natural gas
pipeline facilities in Louisiana. The
proposed project is known as the
Cameron Extension Project (Project),
and would provide 750 million cubic
feet per day of firm transportation
service.
On October 9, 2019, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
Issuance of EA—March 9, 2020.
90-day Federal Authorization Decision
Deadline—June 7, 2020.
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
Texas Eastern proposes to construct
and operate a new compressor station
(East Calcasieu Compressor Station) in
Calcasieu Parish, Louisiana. The new
compressor station is comprised of one
30,000 ISO-rated horsepower, natural
gas-driven turbine compressor unit and
related appurtenances. The Project
would also consist of three new delivery
meter and regulatory stations in
Cameron, Beauregard, and Jefferson
Davis Parishes, Louisiana; installation of
0.2 mile of 30-inch-diameter piping to
interconnect with TransCameron
Pipeline, LLC’s pipeline system in
Cameron Parish, Louisiana; installation
of miscellaneous equipment at the Gillis
Compressor Station in Beauregard
Parish, Louisiana; modifications to
existing internal pipeline inspection
launcher and receiver facilities and two
new bypass facilities at existing sites
along Texas Eastern’s Line 41; and other
related auxiliary facilities and
appurtenances.
Background
On November 8, 2019, the
Commission issued a Notice of Intent to
Prepare an Environmental Assessment
for the Proposed Cameron Extension
Project and Request for Comments on
Environmental Issues (NOI). The NOI
E:\FR\FM\29NON1.SGM
29NON1
65806
Federal Register / Vol. 84, No. 230 / Friday, November 29, 2019 / Notices
was sent to affected landowners; federal,
state, and local government
representatives and agencies; elected
officials; Native American tribes; other
interested parties; and local libraries
and newspapers. All substantive
comments in response to the NOI will
be addressed in the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP19–512), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: November 22, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–25915 Filed 11–27–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–14–000]
khammond on DSKJM1Z7X2PROD with NOTICES
Mountain Valley Pipeline, LLC; Notice
of Revised Schedule for Environmental
Review of the Southgate Project
This notice identifies the Federal
Energy Regulatory Commission staff’s
revised schedule for the completion of
the final Environmental Impact
Statement (EIS) for Mountain Valley
Pipeline, LLC’s Southgate Project. The
first notice of schedule, issued on March
15, 2019, identified December 19, 2019
as the final EIS issuance date. However,
Mountain Valley filed additional
VerDate Sep<11>2014
16:49 Nov 27, 2019
Jkt 250001
information on October 23, 2019 that
included changes to the route and
revised data for resource impacts.
Because the supplemental information
needs further review and required an
additional notice to the landowners
affected by the route changes, issued on
November 15, 2019, Commission staff
has revised the schedule for issuance of
the final EIS.
Schedule for Environmental Review
Issuance of Notice of Availability of the
final EIS February 14, 2020
90-day Federal Authorization Decision
Deadline May 14, 2020
If a schedule change becomes
necessary, an additional notice will be
provided so that the relevant agencies
are kept informed of the project’s
progress.
Additional Information
In order to receive notification of the
issuance of the final EIS and to keep
track of all formal issuances and
submittals in specific dockets, the
Commission offers a free service called
eSubscription. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries, and direct links
to the documents. Go to www.ferc.gov/
docs-filing/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP19–14), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: November 22, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–25917 Filed 11–27–19; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC20–4–000.
Applicants: Tenaska Alabama II
Partners, L.P., Alabama Power
Company.
Description: Response of Southern
Company Services, Inc. on behalf of
Alabama Power Company, et al. to
October 23, 2019 letter requesting
additional information.
Filed Date: 11/21/19.
Accession Number: 20191121–5178.
Comments Due: 5 p.m. ET 12/5/19.
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG20–46–000.
Applicants: Acorn I Energy Storage,
LLC.
Description: Self-Certification of EWG
status of Acorn I Energy Storage, LLC.
Filed Date: 11/22/19.
Accession Number: 20191122–5057.
Comments Due: 5 p.m. ET 12/13/19.
Docket Numbers: EG20–47–000.
Applicants: Wildcat I Energy Storage,
LLC.
Description: Self-Certification of EWG
status of Wildcat I Energy Storage, LLC.
Filed Date: 11/22/19.
Accession Number: 20191122–5058.
Comments Due: 5 p.m. ET 12/13/19.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER18–552–002.
Applicants: Clean Energy Future—
Lordstown, LLC.
Description: Supplement to April 1,
2019 Notice of Non-Material Change in
Status of Clean Energy Future—
Lordstown, LLC.
Filed Date: 11/21/19.
Accession Number: 20191121–5181.
Comments Due: 5 p.m. ET 12/12/19.
Docket Numbers: ER20–28–002.
Applicants: MidAmerican Energy
Company.
Description: Tariff Amendment:
Second Amendment of Pending Tariff
Filing in ER20–28 to be effective 11/1/
2019.
Filed Date: 11/22/19.
Accession Number: 20191122–5001.
Comments Due: 5 p.m. ET 12/13/19.
Docket Numbers: ER20–270–001.
Applicants: Dynegy Oakland, LLC.
Description: Tariff Amendment: Errata
to Annual Reliability Must Run
E:\FR\FM\29NON1.SGM
29NON1
Agencies
[Federal Register Volume 84, Number 230 (Friday, November 29, 2019)]
[Notices]
[Pages 65805-65806]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-25915]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP19-512-000]
Texas Eastern Transmission, L.P.; Notice of Schedule for
Environmental Review of the Cameron Extension Project
On September 26, 2019, Texas Eastern Transmission, L.P. (Texas
Eastern) filed an application in Docket No. CP19-512-000 requesting a
Certificate of Public Convenience and Necessity pursuant to Section
7(c) of the Natural Gas Act to construct and operate certain natural
gas pipeline facilities in Louisiana. The proposed project is known as
the Cameron Extension Project (Project), and would provide 750 million
cubic feet per day of firm transportation service.
On October 9, 2019, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
Environmental Assessment (EA) for the Project. This instant notice
identifies the FERC staff's planned schedule for the completion of the
EA for the Project.
Schedule for Environmental Review
Issuance of EA--March 9, 2020.
90-day Federal Authorization Decision Deadline--June 7, 2020.
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
Texas Eastern proposes to construct and operate a new compressor
station (East Calcasieu Compressor Station) in Calcasieu Parish,
Louisiana. The new compressor station is comprised of one 30,000 ISO-
rated horsepower, natural gas-driven turbine compressor unit and
related appurtenances. The Project would also consist of three new
delivery meter and regulatory stations in Cameron, Beauregard, and
Jefferson Davis Parishes, Louisiana; installation of 0.2 mile of 30-
inch-diameter piping to interconnect with TransCameron Pipeline, LLC's
pipeline system in Cameron Parish, Louisiana; installation of
miscellaneous equipment at the Gillis Compressor Station in Beauregard
Parish, Louisiana; modifications to existing internal pipeline
inspection launcher and receiver facilities and two new bypass
facilities at existing sites along Texas Eastern's Line 41; and other
related auxiliary facilities and appurtenances.
Background
On November 8, 2019, the Commission issued a Notice of Intent to
Prepare an Environmental Assessment for the Proposed Cameron Extension
Project and Request for Comments on Environmental Issues (NOI). The NOI
[[Page 65806]]
was sent to affected landowners; federal, state, and local government
representatives and agencies; elected officials; Native American
tribes; other interested parties; and local libraries and newspapers.
All substantive comments in response to the NOI will be addressed in
the EA.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP19-512), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC
website also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rule makings.
Dated: November 22, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-25915 Filed 11-27-19; 8:45 am]
BILLING CODE 6717-01-P