Maverick Wind Project, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization, 64887-64888 [2019-25525]

Download as PDF Federal Register / Vol. 84, No. 227 / Monday, November 25, 2019 / Notices Crawford Compressor Station contained in Environmental Condition 31 of the Leach XPress Certificate Order. The proposed amended noise condition would allow Columbia to operate the Ceredo CS at the reduced maximum noise levels that result from the proposed amended full load operations, all as more fully described in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this application should be directed to Sorana Linder, Director, Modernization & Certificates, Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 700, Houston, Texas 77002–2700, Phone: 832–320–5209; or email: Sorana_linder@tcenergy.com. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding, or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list VerDate Sep<11>2014 17:31 Nov 22, 2019 Jkt 250001 maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 3 copies of filings made in the proceeding with the Commission and must provide a copy to the applicant and to every other party. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, and will be notified of any meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission and will not have the right to seek court review of the Commission’s final order. As of the February 27, 2018 date of the Commission’s order in Docket No. CP16–4–001, the Commission will apply its revised practice concerning out-of-time motions to intervene in any new Natural Gas Act section 3 or section 7 proceeding.1 Persons desiring to become a party to a certificate proceeding are to intervene in a timely manner. If seeking to intervene out-oftime, the movant is required to ‘‘show good cause why the time limitation should be waived,’’ and should provide justification by reference to factors set forth in Rule 214(d)(1) of the Commission’s Rules and Regulations.2 The Commission strongly encourages electronic filings of comments, protests 1 Tennessee Gas Pipeline Company, L.L.C., 162 FERC ¶ 61,167 at ¶ 50 (2018). 2 18 CFR 385.214(d)(1). PO 00000 Frm 00068 Fmt 4703 Sfmt 4703 64887 and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 3 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE, Washington, DC 20426. Comment Date: 5:00 p.m. Eastern Time on December 10, 2019. Dated: November 19, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–25531 Filed 11–22–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER20–383–000] Maverick Wind Project, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced Maverick Wind Project, LLC’s application for marketbased rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is December 9, 2019. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. E:\FR\FM\25NON1.SGM 25NON1 64888 Federal Register / Vol. 84, No. 227 / Monday, November 25, 2019 / Notices Persons unable to file electronically should submit an original and 5 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The filings in the above-referenced proceeding are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for electronic review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the website that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: November 19, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–25525 Filed 11–22–19; 8:45 am] BILLING CODE 6717–01–P ENVIRONMENTAL PROTECTION AGENCY [EPA–HQ–OECA–2012–0679; FRL–10002– 41–OMS] Information Collection Request Submitted to OMB for Review and Approval; Comment Request; NESHAP for Petroleum Refineries: Catalytic Cracking Units, Catalytic Reforming Units, and Sulfur Recovery Units (Renewal) Environmental Protection Agency (EPA). ACTION: Notice. AGENCY: The Environmental Protection Agency (EPA) has submitted an information collection request (ICR), NESHAP for Petroleum Refineries: Catalytic Cracking Units, Catalytic Reforming Units, and Sulfur Recovery Units (EPA ICR Number 1844.11, OMB Control Number 2060–0554), to the Office of Management and Budget (OMB) for review and approval in accordance with the Paperwork Reduction Act. This is a proposed extension of the ICR, which is currently approved through January 31, 2020. Public comments were previously requested, via the Federal Register, on May 6, 2019 during a 60-day comment period. This notice allows for an additional 30 days for public comments. A fuller description of the ICR is given below, including its estimated burden and cost to the public. An agency may SUMMARY: VerDate Sep<11>2014 17:31 Nov 22, 2019 Jkt 250001 neither conduct nor sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number. DATES: Additional comments may be submitted on or before December 26, 2019. ADDRESSES: Submit your comments, referencing Docket ID Number EPA– HQ–OECA–2012–0679, to: (1) EPA online using www.regulations.gov (our preferred method), or by email to docket.oeca@epa.gov, or by mail to: EPA Docket Center, Environmental Protection Agency, Mail Code 28221T, 1200 Pennsylvania Ave. NW, Washington, DC 20460; and (2) OMB via email to oira_submission@omb.eop.gov. Address comments to OMB Desk Officer for EPA. EPA’s policy is that all comments received will be included in the public docket without change, including any personal information provided, unless the comment includes profanity, threats, information claimed to be Confidential Business Information (CBI), or other information whose disclosure is restricted by statute. FOR FURTHER INFORMATION CONTACT: Patrick Yellin, Monitoring, Assistance, and Media Programs Division, Office of Compliance, Mail Code 2227A, Environmental Protection Agency, 1200 Pennsylvania Ave. NW, Washington, DC 20460; telephone number: (202) 564– 2970; fax number: (202) 564–0050; email address: yellin.patrick@epa.gov. SUPPLEMENTARY INFORMATION: Supporting documents, which explain in detail the information that the EPA will be collecting, are available in the public docket for this ICR. The docket can be viewed online at www.regulations.gov, or in person at the EPA Docket Center, WJC West, Room 3334, 1301 Constitution Ave. NW, Washington, DC. The telephone number for the Docket Center is 202–566–1744. For additional information about EPA’s public docket, visit: https:// www.epa.gov/dockets. Abstract: The National Emission Standards for Hazardous Air Pollutants (NESHAP) for the Petroleum Refineries: Catalytic Cracking Units, Catalytic Reforming Units, and Sulfur Recovery Units apply to three types of affected units at major source petroleum refineries: Fluid catalytic cracking units (FCCU) for catalyst regeneration, catalytic reforming units (CRU), and sulfur recovery units (SRU). The rule also includes requirements for by-pass lines associated with the three affected units. Owners and operators of affected units are required to comply with PO 00000 Frm 00069 Fmt 4703 Sfmt 9990 reporting and record keeping requirements for the General Provisions (40 CFR part 63, subpart A), as well as for the applicable standards in 40 CFR part 63, subpart UUU. This includes submitting initial notifications, performance tests and periodic reports and results, and maintaining records of the operation of an affected facility. These reports are used by EPA to determine compliance with these standards. Form Numbers: None. Respondents/affected entities: Petroleum refineries that operate catalytic cracking units, catalytic reforming units, and sulfur recovery units. Respondent’s obligation to respond: Mandatory (40 CFR part 63). Estimated number of respondents: 142 (total). Frequency of response: Semiannually. Total estimated burden: 17,500 hours (per year). Burden is defined at 5 CFR 1320.3(b). Total estimated cost: $10,800,000 (per year), includes $8,780,000 annualized capital or operation & maintenance costs. Changes in the estimates: There is a moderate decrease in burden in this ICR compared to the previous ICR. The decrease in the burden and cost estimates occurred because refineries are assumed to have implemented the initial 2015 rule compliance activities since the standard has been in effect for more than three years. The previous ICR reflected those burdens and costs associated with the initial activities for subject facilities. This includes conducting performance test(s) and establishing or revising recordkeeping systems. This ICR, by in large, reflects the on-going burden and costs for existing facilities. Activities for existing sources include 5-year performance tests, continuous monitoring of pollutants, and the submission of semiannual reports. This ICR also corrects the Agency burden from the prior ICR to account for burden for review of submitted RATA for units using CEMS. Courtney Kerwin, Director, Regulatory Support Division. [FR Doc. 2019–25485 Filed 11–22–19; 8:45 am] BILLING CODE 6560–50–P E:\FR\FM\25NON1.SGM 25NON1

Agencies

[Federal Register Volume 84, Number 227 (Monday, November 25, 2019)]
[Notices]
[Pages 64887-64888]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-25525]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. ER20-383-000]


Maverick Wind Project, LLC; Supplemental Notice That Initial 
Market-Based Rate Filing Includes Request for Blanket Section 204 
Authorization

    This is a supplemental notice in the above-referenced Maverick Wind 
Project, LLC's application for market-based rate authority, with an 
accompanying rate tariff, noting that such application includes a 
request for blanket authorization, under 18 CFR part 34, of future 
issuances of securities and assumptions of liability.
    Any person desiring to intervene or to protest should file with the 
Federal Energy Regulatory Commission, 888 First Street NE, Washington, 
DC 20426, in accordance with Rules 211 and 214 of the Commission's 
Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone 
filing a motion to intervene or protest must serve a copy of that 
document on the Applicant.
    Notice is hereby given that the deadline for filing protests with 
regard to the applicant's request for blanket authorization, under 18 
CFR part 34, of future issuances of securities and assumptions of 
liability, is December 9, 2019.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper, using the FERC Online links at https://www.ferc.gov. To facilitate electronic service, persons with internet 
access who will eFile a document and/or be listed as a contact for an 
intervenor must create and validate an eRegistration account using the 
eRegistration link. Select the eFiling link to log on and submit the 
intervention or protests.

[[Page 64888]]

    Persons unable to file electronically should submit an original and 
5 copies of the intervention or protest to the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426.
    The filings in the above-referenced proceeding are accessible in 
the Commission's eLibrary system by clicking on the appropriate link in 
the above list. They are also available for electronic review in the 
Commission's Public Reference Room in Washington, DC. There is an 
eSubscription link on the website that enables subscribers to receive 
email notification when a document is added to a subscribed docket(s). 
For assistance with any FERC Online service, please email 
[email protected]. or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.

    Dated: November 19, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-25525 Filed 11-22-19; 8:45 am]
 BILLING CODE 6717-01-P