Carthage Specialty Paperboard, Inc.; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments, 63872-63873 [2019-25028]

Download as PDF 63872 Federal Register / Vol. 84, No. 223 / Tuesday, November 19, 2019 / Notices the Federal Power Act and have that notice accepted before the agreement can be terminated; and (3) that a Transmission Provider may publicly indicate on its Open Access Same-Time Information System and in its Electric Quarterly Report that an interconnection request has been canceled and LGIA terminated, as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Petitioners. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the website that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern time on December 9, 2019. khammond on DSKJM1Z7X2PROD with NOTICES Dated: November 13, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–25016 Filed 11–18–19; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 16:47 Nov 18, 2019 Jkt 250001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 10887–030] Carthage Specialty Paperboard, Inc.; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests and Establishing Procedural Schedule for Relicensing and a Deadline for Submission of Final Amendments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New Minor License. b. Project No.: 10887–030. c. Date Filed: October 31, 2019. d. Applicant: Carthage Specialty Paperboard, Inc. e. Name of Project: Carthage Paper Maker Mill Hydroelectric Project. f. Location: On the Black River, near the Village of Carthage, Jefferson and Lewis Counties, New York. The project does not occupy federal land. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)–825(r). h. Applicant Contact: Martin Weller, Corporate Project Engineer, Ox Industries, Inc., 600 West Elm Avenue, Hanover, PA 17331; (717) 698–3329; and/or E. Steve O’Donnell, General Counsel, Ox Industries, Inc., 600 West Elm Avenue, Hanover, PA 17331; (717) 632–9580. i. FERC Contact: Monir Chowdhury at (202) 502–6736; or email at monir.chowdhury@ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: December 30, 2019. The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–10887–030. m. This application is not ready for environmental analysis at this time. n. The existing project consists of the following: (1) An 829-foot-long concrete gravity dam with a maximum height of 8 feet at a crest elevation of 726.4 feet above mean sea level (msl); (2) an impoundment with a surface area of about 158 acres and a storage capacity of 767 acre-feet at a normal pool elevation of 726.4 feet msl; (3) a forebay canal approximately 500 feet long, 58 feet wide, and 10 feet deep at the west bank of the river; (4) a masonry and concrete powerhouse 31 feet long, 25 feet wide, and approximately 45 feet high, containing one open flume turbine-generator unit with a rated capacity of 800 kilowatts; (5) an excavated 200-foot-long, 35-foot-wide tailrace; (6) a 750-foot-long generator lead that connects the powerhouse with a substation; and (7) appurtenant facilities. The Carthage Paper Maker Mill Project is operated in a run-of-river mode with an estimated average annual generation of 3,991 megawatt-hours between 2014 and 2018. o. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. E:\FR\FM\19NON1.SGM 19NON1 Federal Register / Vol. 84, No. 223 / Tuesday, November 19, 2019 / Notices Laurel Mountain, LLC, AES Ohio Generation, LLC, AES Redondo Beach, L.L.C., Indianapolis Power & Light Company, Mountain View Power Partners, LLC, Mountain View Power Partners IV, LLC, The Dayton Power and Light Company, 65HK 8me LLC, 67RK 8me LLC, 87RL 8me LLC, Antelope Big Sky Ranch LLC, Antelope DSR 1, LLC, Antelope DSR 2, LLC, Antelope DSR 3, LLC, Antelope Expansion 2, LLC, Bayshore Solar A, LLC, Bayshore Solar B, LLC, Bayshore Solar C, LLC, Beacon Solar 1, LLC, Beacon Solar 3, LLC, Beacon Solar 4, LLC, Central Antelope Dry Ranch C LLC, FTS Master Tenant 1, LLC, FTS Master Tenant 2, LLC, ID Solar 1, LLC, Latigo Wind Park, LLC, North Lancaster Ranch LLC, Pioneer Wind Park I LLC, Riverhead Solar Farm, LLC, San Pablo Raceway, LLC, Sandstone Solar LLC, Sierra Solar Greenworks LLC, Solverde 1, LLC, Summer Solar LLC, Western Antelope Dated: November 12, 2019. Blue Sky Ranch A LLC, Western Nathaniel J. Davis, Sr., Antelope Blue Sky Ranch B LLC, Deputy Secretary. Elevation Solar C LLC, Western Antelope Dry Ranch LLC. [FR Doc. 2019–25028 Filed 11–18–19; 8:45 am] Description: Supplement to June 25, BILLING CODE 6717–01–P 2019 Triennial Market Power Analysis of the AES MBR Affiliates for the Southwest Region. DEPARTMENT OF ENERGY Filed Date: 11/12/19. Accession Number: 20191112–5303. Federal Energy Regulatory Comments Due: 5 p.m. ET 12/3/19. Commission Docket Numbers: ER19–2473–000. Combined Notice of Filings #1 Applicants: Basin Electric Power Cooperative, Inc. Take notice that the Commission Description: Amendment to July 26, received the following electric rate 2019 Request for One-Time Waiver of filings: certain requirements under Attachment Docket Numbers: ER10–3145–012; O to MISO’s Open Access Transmission, ER10–1728–012; ER10–1800–013; Energy and Operating Reserve Markets ER10–3116–012; ER10–3120–012; Tariff of Basin Electric Power ER10–3128–012; ER10–3136–012; Cooperative. ER11–2036–012; ER11–2701–014; Filed Date: 11/6/19. ER13–1544–009; ER15–1579–014; Accession Number: 20191106–5044. ER15–1582–015; ER15–1914–016; Comments Due: 5 p.m. ET 11/27/19. ER15–2679–012; ER15–2680–012; Docket Numbers: ER20–116–000. ER15–760–015; ER15–762–016; ER16– Applicants: Evergy Metro, Inc. 1255–013; ER16–1609–006; ER16–1738– Description: Report Filing: 010; ER16–1901–010; ER16–1955–010; Supplemental Filing to a Notice of ER16–1956–010; ER16–1973–010; Succession, Vol. No. 4 to be effective N/ ER16–2201–009; ER16–2224–009; A. ER16–2541–009; ER16–2578–010; Filed Date: 11/12/19. ER16–468–010; ER16–474–011; ER16– Accession Number: 20191112–5260. 890–011; ER16–930–006; ER17–1864– Comments Due: 5 p.m. ET 12/3/19. 008; ER17–1871–008; ER17–1909–008; Docket Numbers: ER20–363–000. ER17–306–009; ER17–544–009; ER18– Applicants: Arizona Public Service 1667–003; ER18–2327–002; ER18–2492– Company. 004; ER19–1179–001; ER19–1473–001; Description: § 205(d) Rate Filing: ER19–1474–001; ER19–1597–001; Service Agreement No. 373 to be ER19–846–003; ER19–847–003. effective 10/15/2019. Applicants: AES Alamitos, LLC, AES Filed Date: 11/12/19. Accession Number: 20191112–5254. Alamitos Energy, LLC, AES Energy Comments Due: 5 p.m. ET 12/3/19. Storage, LLC, AES ES Gilbert, LLC, AES ES Tait, LLC, AES Huntington Beach, Docket Numbers: ER20–364–000. Applicants: Arizona Public Service L.L.C., AES Huntington Beach Energy, Company. LLC, AES Integrated Energy, LLC, AES khammond on DSKJM1Z7X2PROD with NOTICES p. Procedural schedule and final amendments: The application will be processed according to the following preliminary schedule. Revisions to the schedule will be made as appropriate. Issue Deficiency Letter (if necessary) December 2019 Request Additional Information December 2019 Issue Acceptance Letter March 2020 Issue Scoping Document 1 for comments April 2020 Request Additional Information (if necessary) June 2020 Issue Scoping Document 2 July 2020 Issue notice of ready for environmental analysis July 2020 Commission issues EA January 2021 Comments on EA February 2021 Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. VerDate Sep<11>2014 16:47 Nov 18, 2019 Jkt 250001 PO 00000 Frm 00037 Fmt 4703 Sfmt 4703 63873 Description: § 205(d) Rate Filing: Rate Schedule No. 301 to be effective 12/23/ 2019. Filed Date: 11/12/19. Accession Number: 20191112–5258. Comments Due: 5 p.m. ET 12/3/19. Docket Numbers: ER20–365–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original WMPA SA No 5522; Queue No. AE1–075 to be effective 10/14/2019. Filed Date: 11/13/19. Accession Number: 20191113–5011. Comments Due: 5 p.m. ET 12/4/19. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES20–8–000. Applicants: PJM Interconnection, L.L.C. Description: Application Under Section 204 of the Federal Power Act for Authorization to Issue Securities of PJM Interconnection, L.L.C. Filed Date: 11/12/19. Accession Number: 20191112–5274. Comments Due: 5 p.m. ET 12/3/19. Docket Numbers: ES20–9–000. Applicants: PJM Settlement, Inc. Description: Application Under Section 204 of the Federal Power Act for Authorization to Issue Securities of PJM Settlement, Inc. Filed Date: 11/12/19. Accession Number: 20191112–5292. Comments Due: 5 p.m. ET 12/3/19. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: November 13, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–25033 Filed 11–18–19; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\19NON1.SGM 19NON1

Agencies

[Federal Register Volume 84, Number 223 (Tuesday, November 19, 2019)]
[Notices]
[Pages 63872-63873]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-25028]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 10887-030]


Carthage Specialty Paperboard, Inc.; Notice of Application 
Tendered for Filing With the Commission and Soliciting Additional Study 
Requests and Establishing Procedural Schedule for Relicensing and a 
Deadline for Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New Minor License.
    b. Project No.: 10887-030.
    c. Date Filed: October 31, 2019.
    d. Applicant: Carthage Specialty Paperboard, Inc.
    e. Name of Project: Carthage Paper Maker Mill Hydroelectric 
Project.
    f. Location: On the Black River, near the Village of Carthage, 
Jefferson and Lewis Counties, New York. The project does not occupy 
federal land.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Martin Weller, Corporate Project Engineer, Ox 
Industries, Inc., 600 West Elm Avenue, Hanover, PA 17331; (717) 698-
3329; and/or E. Steve O'Donnell, General Counsel, Ox Industries, Inc., 
600 West Elm Avenue, Hanover, PA 17331; (717) 632-9580.
    i. FERC Contact: Monir Chowdhury at (202) 502-6736; or email at 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See, 94 FERC ] 
61,076 (2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: December 30, 2019.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at [email protected], (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, please send a paper copy 
to: Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE, Washington, DC 20426. The first page of any filing should include 
docket number P-10887-030.
    m. This application is not ready for environmental analysis at this 
time.
    n. The existing project consists of the following: (1) An 829-foot-
long concrete gravity dam with a maximum height of 8 feet at a crest 
elevation of 726.4 feet above mean sea level (msl); (2) an impoundment 
with a surface area of about 158 acres and a storage capacity of 767 
acre-feet at a normal pool elevation of 726.4 feet msl; (3) a forebay 
canal approximately 500 feet long, 58 feet wide, and 10 feet deep at 
the west bank of the river; (4) a masonry and concrete powerhouse 31 
feet long, 25 feet wide, and approximately 45 feet high, containing one 
open flume turbine-generator unit with a rated capacity of 800 
kilowatts; (5) an excavated 200-foot-long, 35-foot-wide tailrace; (6) a 
750-foot-long generator lead that connects the powerhouse with a 
substation; and (7) appurtenant facilities.
    The Carthage Paper Maker Mill Project is operated in a run-of-river 
mode with an estimated average annual generation of 3,991 megawatt-
hours between 2014 and 2018.
    o. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's website at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.

[[Page 63873]]

    p. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary schedule. Revisions 
to the schedule will be made as appropriate.

Issue Deficiency Letter (if necessary) December 2019
Request Additional Information December 2019
Issue Acceptance Letter March 2020
Issue Scoping Document 1 for comments April 2020
Request Additional Information (if necessary) June 2020
Issue Scoping Document 2 July 2020
Issue notice of ready for environmental analysis July 2020
Commission issues EA January 2021
Comments on EA February 2021
    Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: November 12, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-25028 Filed 11-18-19; 8:45 am]