Northern Natural Gas Company; Notice of Revised Schedule for Environmental Review of the Bushton to Clifton A-Line Abandonment Project, 62521-62522 [2019-24767]

Download as PDF Federal Register / Vol. 84, No. 221 / Friday, November 15, 2019 / Notices • threatened and endangered species; • cultural resources; • land use; • air quality and noise; • public safety; and • cumulative impacts. Commission staff will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present Commission staffs’ independent analysis of the issues. The EA will be available in electronic format in the public record through eLibrary 2 and the Commission’s website (https:// www.ferc.gov/industries/gas/enviro/ eis.asp). If eSubscribed, you will receive instant email notification when the EA is issued. The EA may be issued for an allotted public comment period. Commission staff will consider all comments on the EA before making recommendations to the Commission. To ensure Commission staff have the opportunity to address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2. With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the EA.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultation Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic Preservation Office, and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.4 The EA for this project will document findings 2 For instructions on connecting to eLibrary, refer to the last page of this notice. 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. VerDate Sep<11>2014 16:58 Nov 14, 2019 Jkt 250001 62521 on the impacts on historic properties and summarize the status of consultations under section 106. Dated: November 8, 2019. Kimberly D. Bose, Secretary. Environmental Mailing List [FR Doc. 2019–24815 Filed 11–14–19; 8:45 am] BILLING CODE 6717–01–P The environmental mailing list includes: Federal, state, and local government representatives and agencies; elected officials; Native American Tribes; libraries; newspapers; and other interested parties. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-ofway grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If the Commission issues the EA for an allotted public comment period, a Notice of Availability of the EA will be sent to the environmental mailing list and will provide instructions to access the electronic document on the FERC’s website (www.ferc.gov). If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please return the attached ‘‘Mailing List Update Form’’ (appendix 2). Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number in the ‘‘Docket Number’’ field, excluding the last three digits (i.e., CP19–512). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. Public sessions or site visits will be posted on the Commission’s calendar located at www.ferc.gov/EventCalendar/ EventsList.aspx along with other related information. PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP19–479–000] Northern Natural Gas Company; Notice of Revised Schedule for Environmental Review of the Bushton to Clifton ALine Abandonment Project This notice identifies the Federal Energy Regulatory Commission (FERC) staff’s revised schedule for the completion of the environmental assessment (EA) for Northern Natural Gas Company’s Bushton to Clifton ALine Abandonment Project. The first notice of schedule, issued on July 30, 2019, identified November 8, 2019 as the EA issuance date. Because affected landowners were inadvertently excluded from the environmental mailing list for the Notice of Intent to Prepare an Environmental Assessment for the Proposed Bushton to Clifton A-line Abandonment Project issued by the Commission on July 15, 2019, we have issued a supplemental notice on November 6, 2019 to provide all affected landowners an opportunity to comment in this proceeding. As a result, staff has revised the schedule for issuance of the EA to extend the comment period and give the public an expanded opportunity to participate in the project’s design and implementation. Schedule for Environmental Review Issuance of Notice of Availability of the EA—December 17, 2019 90-day Federal Authorization Decision Deadline—March 16, 2019 If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the E:\FR\FM\15NON1.SGM 15NON1 62522 Federal Register / Vol. 84, No. 221 / Friday, November 15, 2019 / Notices documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, select ‘‘General Search’’ from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP19–479), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: November 7, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–24767 Filed 11–14–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP19–474–000] are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP19–474), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Notice of Revised Schedule for Environmental Review of the Florida Gas Transmission Company, LLC Putnam Expansion Project Dated: November 7, 2019. Kimberly D. Bose, Secretary. This notice identifies the Federal Energy Regulatory Commission staff’s revised schedule for the completion of the environmental assessment (EA) for Florida Gas Transmission Company, LLC’s Putnam Expansion Project. The first notice of schedule, issued on August 14, 2019, identified November 8, 2019 as the EA issuance date. However, Florida Gas Transmission Company filed additional information on November 5, 2019 in response to Commission staff’s October 30, 2019 data request regarding an affected landowner comment that was filed in this proceeding. Because the requested information was necessary to complete the environmental review, staff has revised the schedule for issuance of the EA. BILLING CODE 6717–01–P [FR Doc. 2019–24766 Filed 11–14–19; 8:45 am] Schedule for Environmental Review Issuance of Notice of Availability of the EA—December 6, 2019 90-day Federal Authorization Decision Deadline—March 5, 2020 If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies VerDate Sep<11>2014 16:58 Nov 14, 2019 Jkt 250001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Number: PR20–6–000. Applicants: Pelico Pipeline, LLC. Description: Tariff filing per 284.123(b)(2)+(g): Pelico Pipeline, LLC Petition for Rate Approval & Revised SOC to be effective 11/1/2019. Filed Date: 11/6/19. Accession Number: 201911065050. Comments Due: 5 p.m. ET 11/27/19. 284.123(g) Protests Due: 5 p.m. ET 1/6/20. Docket Number: PR20–7–000. Applicants: Intrastate Gas LP. Description: Tariff filing per 284.123(b)(2)+(g): Regency Intrastate PO 00000 Frm 00021 Fmt 4703 Sfmt 4703 Gas LP Petition for Rate Approval & Revised SOC to be effective 11/1/2019. Filed Date: 11/6/19. Accession Number: 201911065050. Comments Due: 5 p.m. ET 11/27/19. 284.123(g) Protests Due: 5 p.m. ET 1/ 6/20. Docket Numbers: RP20–208–000. Applicants: Algonquin Gas Transmission, LLC. Description: § 4(d) Rate Filing: Nov 2019 Negotiated Rates Cleanup Filing to be effective 12/6/2019. Filed Date: 11/6/19. Accession Number: 20191106–5009. Comments Due: 5 p.m. ET 11/18/19. Docket Numbers: RP20–209–000. Applicants: Midcontinent Express Pipeline LLC. Description: § 4(d) Rate Filing: Balancing Service Charges Penalty Tolerance Filing to be effective 1/1/ 2020. Filed Date: 11/6/19. Accession Number: 20191106–5012. Comments Due: 5 p.m. ET 11/18/19. Docket Numbers: RP20–210–000. Applicants: Rockies Express Pipeline LLC. Description: § 4(d) Rate Filing: Neg Rate 2019–11–6 ConocoPhillips to be effective 11/6/2019. Filed Date: 11/6/19. Accession Number: 20191106–5060. Comments Due: 5 p.m. ET 11/18/19. Docket Numbers: RP20–211–000. Applicants: Transcontinental Gas Pipe Line Company, LLC. Description: § 4(d) Rate Filing: Momentum Rate Filing—Zone 5–5 to be effective 12/7/2019. Filed Date: 11/6/19. Accession Number: 20191106–5160. Comments Due: 5 p.m. ET 11/18/19. Docket Numbers: RP20–212–000. Applicants: Enable Mississippi River Transmission, LLC. Description: Compliance filing Offer of Settlement of MRT under RP20–131– 000 to be effective 12/1/2019. Filed Date: 11/6/19. Accession Number: 20191106–5165. Comments Due: 5 p.m. ET 11/18/19. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified date(s). Protests may be considered, but intervention is necessary to become a party to the proceeding. E:\FR\FM\15NON1.SGM 15NON1

Agencies

[Federal Register Volume 84, Number 221 (Friday, November 15, 2019)]
[Notices]
[Pages 62521-62522]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-24767]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-479-000]


Northern Natural Gas Company; Notice of Revised Schedule for 
Environmental Review of the Bushton to Clifton A-Line Abandonment 
Project

    This notice identifies the Federal Energy Regulatory Commission 
(FERC) staff's revised schedule for the completion of the environmental 
assessment (EA) for Northern Natural Gas Company's Bushton to Clifton 
A-Line Abandonment Project. The first notice of schedule, issued on 
July 30, 2019, identified November 8, 2019 as the EA issuance date.
    Because affected landowners were inadvertently excluded from the 
environmental mailing list for the Notice of Intent to Prepare an 
Environmental Assessment for the Proposed Bushton to Clifton A-line 
Abandonment Project issued by the Commission on July 15, 2019, we have 
issued a supplemental notice on November 6, 2019 to provide all 
affected landowners an opportunity to comment in this proceeding. As a 
result, staff has revised the schedule for issuance of the EA to extend 
the comment period and give the public an expanded opportunity to 
participate in the project's design and implementation.

Schedule for Environmental Review

Issuance of Notice of Availability of the EA--December 17, 2019
90-day Federal Authorization Decision Deadline--March 16, 2019

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the

[[Page 62522]]

documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, select ``General 
Search'' from the eLibrary menu, enter the selected date range and 
Docket Number excluding the last three digits (i.e., CP19-479), and 
follow the instructions. For assistance with access to eLibrary, the 
helpline can be reached at (866) 208-3676, TTY (202) 502-8659, or at 
[email protected]. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: November 7, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-24767 Filed 11-14-19; 8:45 am]
BILLING CODE 6717-01-P