Notice of Revised Schedule for Environmental Review of the Florida Gas Transmission Company, LLC Putnam Expansion Project, 62522 [2019-24766]

Download as PDF 62522 Federal Register / Vol. 84, No. 221 / Friday, November 15, 2019 / Notices documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, select ‘‘General Search’’ from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP19–479), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: November 7, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–24767 Filed 11–14–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP19–474–000] are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP19–474), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Notice of Revised Schedule for Environmental Review of the Florida Gas Transmission Company, LLC Putnam Expansion Project Dated: November 7, 2019. Kimberly D. Bose, Secretary. This notice identifies the Federal Energy Regulatory Commission staff’s revised schedule for the completion of the environmental assessment (EA) for Florida Gas Transmission Company, LLC’s Putnam Expansion Project. The first notice of schedule, issued on August 14, 2019, identified November 8, 2019 as the EA issuance date. However, Florida Gas Transmission Company filed additional information on November 5, 2019 in response to Commission staff’s October 30, 2019 data request regarding an affected landowner comment that was filed in this proceeding. Because the requested information was necessary to complete the environmental review, staff has revised the schedule for issuance of the EA. BILLING CODE 6717–01–P [FR Doc. 2019–24766 Filed 11–14–19; 8:45 am] Schedule for Environmental Review Issuance of Notice of Availability of the EA—December 6, 2019 90-day Federal Authorization Decision Deadline—March 5, 2020 If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies VerDate Sep<11>2014 16:58 Nov 14, 2019 Jkt 250001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Number: PR20–6–000. Applicants: Pelico Pipeline, LLC. Description: Tariff filing per 284.123(b)(2)+(g): Pelico Pipeline, LLC Petition for Rate Approval & Revised SOC to be effective 11/1/2019. Filed Date: 11/6/19. Accession Number: 201911065050. Comments Due: 5 p.m. ET 11/27/19. 284.123(g) Protests Due: 5 p.m. ET 1/6/20. Docket Number: PR20–7–000. Applicants: Intrastate Gas LP. Description: Tariff filing per 284.123(b)(2)+(g): Regency Intrastate PO 00000 Frm 00021 Fmt 4703 Sfmt 4703 Gas LP Petition for Rate Approval & Revised SOC to be effective 11/1/2019. Filed Date: 11/6/19. Accession Number: 201911065050. Comments Due: 5 p.m. ET 11/27/19. 284.123(g) Protests Due: 5 p.m. ET 1/ 6/20. Docket Numbers: RP20–208–000. Applicants: Algonquin Gas Transmission, LLC. Description: § 4(d) Rate Filing: Nov 2019 Negotiated Rates Cleanup Filing to be effective 12/6/2019. Filed Date: 11/6/19. Accession Number: 20191106–5009. Comments Due: 5 p.m. ET 11/18/19. Docket Numbers: RP20–209–000. Applicants: Midcontinent Express Pipeline LLC. Description: § 4(d) Rate Filing: Balancing Service Charges Penalty Tolerance Filing to be effective 1/1/ 2020. Filed Date: 11/6/19. Accession Number: 20191106–5012. Comments Due: 5 p.m. ET 11/18/19. Docket Numbers: RP20–210–000. Applicants: Rockies Express Pipeline LLC. Description: § 4(d) Rate Filing: Neg Rate 2019–11–6 ConocoPhillips to be effective 11/6/2019. Filed Date: 11/6/19. Accession Number: 20191106–5060. Comments Due: 5 p.m. ET 11/18/19. Docket Numbers: RP20–211–000. Applicants: Transcontinental Gas Pipe Line Company, LLC. Description: § 4(d) Rate Filing: Momentum Rate Filing—Zone 5–5 to be effective 12/7/2019. Filed Date: 11/6/19. Accession Number: 20191106–5160. Comments Due: 5 p.m. ET 11/18/19. Docket Numbers: RP20–212–000. Applicants: Enable Mississippi River Transmission, LLC. Description: Compliance filing Offer of Settlement of MRT under RP20–131– 000 to be effective 12/1/2019. Filed Date: 11/6/19. Accession Number: 20191106–5165. Comments Due: 5 p.m. ET 11/18/19. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified date(s). Protests may be considered, but intervention is necessary to become a party to the proceeding. E:\FR\FM\15NON1.SGM 15NON1

Agencies

[Federal Register Volume 84, Number 221 (Friday, November 15, 2019)]
[Notices]
[Page 62522]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-24766]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-474-000]


Notice of Revised Schedule for Environmental Review of the 
Florida Gas Transmission Company, LLC Putnam Expansion Project

    This notice identifies the Federal Energy Regulatory Commission 
staff's revised schedule for the completion of the environmental 
assessment (EA) for Florida Gas Transmission Company, LLC's Putnam 
Expansion Project. The first notice of schedule, issued on August 14, 
2019, identified November 8, 2019 as the EA issuance date. However, 
Florida Gas Transmission Company filed additional information on 
November 5, 2019 in response to Commission staff's October 30, 2019 
data request regarding an affected landowner comment that was filed in 
this proceeding. Because the requested information was necessary to 
complete the environmental review, staff has revised the schedule for 
issuance of the EA.

Schedule for Environmental Review

Issuance of Notice of Availability of the EA--December 6, 2019
90-day Federal Authorization Decision Deadline--March 5, 2020

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP19-474), and follow the 
instructions. For assistance with access to eLibrary, the helpline can 
be reached at (866) 208-3676, TTY (202) 502-8659, or at 
[email protected]. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: November 7, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-24766 Filed 11-14-19; 8:45 am]