Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process, 56454-56455 [2019-23004]

Download as PDF 56454 Federal Register / Vol. 84, No. 204 / Tuesday, October 22, 2019 / Notices eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–2206–089. Comments emailed to Commission staff are not considered part of the Commission record. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person whose name appears on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. Description of Request: The licensee requests Commission approval of a non-project use of project lands and water for the construction and operation of a municipal water treatment plant. The proposed construction would affect 0.34 acres of project land. The Town of Norwood and Union County, North Carolina seek to withdrawal an instantaneous maximum daily withdrawal of 49.0 million gallons of water per day (MGD), with an annual average withdrawal of 19.6 MGD from Lake Tillery. A maximum monthly average of 23.3 MGD of the water withdrawn from the proposed intake would be transferred out of the Yadkin River Basin into the Rocky River Basin. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE, Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call (866) 208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and VerDate Sep<11>2014 17:45 Oct 21, 2019 Jkt 250001 reproduction at the address in item (h) above. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’; ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests, must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: October 16, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–23002 Filed 10–21–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process Project Nos. Midwest Hydro, LLC ............. Midwest Hydro, LLC ............. Midwest Hydro, LLC ............. PO 00000 Frm 00044 Fmt 4703 Sfmt 4703 2347–051 2348–042 2373–012 Project Nos. STS Hydropower, LLC ......... 2446–051 a. Type of Filing: Notices of Intent to File License Applications and Request to Use the Traditional Licensing Process. b. Project Nos.: 2347–051, 2348–042, 2373–012, and 2446–051. c. Date Filed: August 30, 2019. d. Submitted By: Eagle Creek Renewable Energy, LLC, on behalf of Midwest Hydro, LLC (Midwest Hydro) and STS Hydropower, LLC (STS Hydropower). e. Name of Projects: Janesville Central, Beloit, Rockton, and Dixon Hydroelectric Projects. f. Location: The four existing projects are located on the Rock River. The Dixon Project is located at river mile (RM) 87 in Lee and Ogle Counties, Illinois. The Rockton Project is located at RM 159 in Winnebago County, Illinois. The Beloit Project is located at RM 163 in Rock County, Wisconsin. The Janesville Central Project is located at RM 180 in Rock County, Wisconsin. No federal lands are occupied by the project works or located within the respective project boundaries. g. Filed Pursuant to: 18 CFR 5.3 of the Commission’s regulations. h. Potential Applicant Contact: Michael Scarzello, Regulatory Director, Eagle Creek Renewable Energy, LLC, 116 N State Street, P.O. Box 167, Neshkoro, WI 54960-0167; phone: 973– 998–8400; email—Michael.Scarzello@ eaglecreekre.com. i. FERC Contact: Laura Washington at (202) 502–6072; or email at Laura. Washington@ferc.gov. j. Midwest Hydro and STS Hydropower filed separate requests to use the Traditional Licensing Process on August 30, 2019. Midwest Hydro and STS Hydropower provided public notice of their requests on August 30, 2019. In a letter dated October 16, 2019, the Director of the Division of Hydropower Licensing approved the requests to use the Traditional Licensing Process. k. With this notice, we are initiating informal consultation with the U.S. Fish and Wildlife Service and/or National Oceanic and Atmospheric Administration (NOAA) Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, part 402; and NOAA Fisheries under section 305(b) of the Magnuson-Stevens Fishery Conservation and Management Act and implementing regulations at 50 CFR 600.920. We are also initiating consultation the Wisconsin and Illinois E:\FR\FM\22OCN1.SGM 22OCN1 Federal Register / Vol. 84, No. 204 / Tuesday, October 22, 2019 / Notices State Historic Preservation Officers, as required by section 106, National Historical Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating Midwest Hydro and STS Hydropower as the Commission’s non-federal representatives for carrying out informal consultation, pursuant to section 7 of the Endangered Species Act and section 305(b) of the Magnuson-Stevens Fishery Conservation and Management Act; and consultation pursuant to section 106 of the National Historic Preservation Act. m. Midwest Hydro and STS Hydropower filed Pre-Application Documents (PAD); including a proposed process plan and schedule for each project with the Commission, pursuant to 18 CFR 5.6 of the Commission’s regulations. n. A copy of the PADs are available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s website (https://www.ferc.gov), using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCONline Support@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). A copy is also available for inspection and reproduction at the address in paragraph h. o. The licensees state their unequivocal intent to submit an application for a new license for Project Nos. 2347, 2348, 2373, and 2446. Pursuant to 18 CFR 16.8, 16.9, and 16.10, each application for a new license and any competing license applications must be filed with the Commission at least 24 months prior to the expiration of the existing license. All applications for license for these projects must be filed by August 31, 2022. p. Register online at https://www.ferc .gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances related to these or other pending projects. For assistance, contact FERC Online Support. Dated: October 16, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–23004 Filed 10–21–19; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 17:45 Oct 21, 2019 Jkt 250001 docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER20–122–000] Crowned Ridge Interconnection, LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Crowned Ridge Interconnection, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is November 5, 2019. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 5 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The filings in the above-referenced proceeding are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for electronic review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the website that enables subscribers to receive email notification when a document is added to a subscribed PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 56455 Dated: October 16, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–22970 Filed 10–21–19; 8:45 am] BILLING CODE 6717–01–P FEDERAL TRADE COMMISSION Agency Information Collection Activities; Submission to the Office of Management and Budget for Review and Approval; Comment Request Federal Trade Commission. Notice. AGENCY: ACTION: The Federal Trade Commission (‘‘FTC’’ or ‘‘Commission’’) requests that the Office of Management and Budget (‘‘OMB’’) extend for an additional three years the current Paperwork Reduction Act (‘‘PRA’’) clearance for information collection requirements in its Energy Labeling Rule. The existing clearance expires on November 30, 2019. DATES: Comments must be submitted on or before November 21, 2019. ADDRESSES: Comments in response to this notice should be submitted to the OMB Desk Officer for the Federal Trade Commission within 30 days of this notice. You may submit comments using any of the following methods: Electronic: Write ‘‘Energy Labeling Rule, PRA Comment, FTC File No. R611004,’’ on your comment and file your comment online at https:// www.regulations.gov, by following the instructions on the web-based form. Email: MBX.OMB.OIRA.Submission@ OMB.eop.gov. Mail: Office of Information and Regulatory Affairs, Office of Management and Budget, Attention: Desk Officer for the Federal Trade Commission, New Executive Office Building, Docket Library, Room 10102, 725 17th Street NW, Washington, DC 20503. SUMMARY: FOR FURTHER INFORMATION CONTACT: Hampton Newsome, (202) 326–2889, Attorney, Division of Enforcement, Bureau of Consumer Protection, Federal Trade Commission, 600 Pennsylvania Avenue NW, Washington, DC 20580. SUPPLEMENTARY INFORMATION: Pursuant to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.), the FTC has submitted to the Office of Management and Budget (‘‘OMB’’) this request for E:\FR\FM\22OCN1.SGM 22OCN1

Agencies

[Federal Register Volume 84, Number 204 (Tuesday, October 22, 2019)]
[Notices]
[Pages 56454-56455]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-23004]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Intent To File License Application, Filing of Pre-
Application Document, and Approving Use of the Traditional Licensing 
Process

------------------------------------------------------------------------
                                                           Project Nos.
------------------------------------------------------------------------
Midwest Hydro, LLC......................................        2347-051
Midwest Hydro, LLC......................................        2348-042
Midwest Hydro, LLC......................................        2373-012
STS Hydropower, LLC.....................................        2446-051
------------------------------------------------------------------------

    a. Type of Filing: Notices of Intent to File License Applications 
and Request to Use the Traditional Licensing Process.
    b. Project Nos.: 2347-051, 2348-042, 2373-012, and 2446-051.
    c. Date Filed: August 30, 2019.
    d. Submitted By: Eagle Creek Renewable Energy, LLC, on behalf of 
Midwest Hydro, LLC (Midwest Hydro) and STS Hydropower, LLC (STS 
Hydropower).
    e. Name of Projects: Janesville Central, Beloit, Rockton, and Dixon 
Hydroelectric Projects.
    f. Location: The four existing projects are located on the Rock 
River. The Dixon Project is located at river mile (RM) 87 in Lee and 
Ogle Counties, Illinois. The Rockton Project is located at RM 159 in 
Winnebago County, Illinois. The Beloit Project is located at RM 163 in 
Rock County, Wisconsin. The Janesville Central Project is located at RM 
180 in Rock County, Wisconsin. No federal lands are occupied by the 
project works or located within the respective project boundaries.
    g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
    h. Potential Applicant Contact: Michael Scarzello, Regulatory 
Director, Eagle Creek Renewable Energy, LLC, 116 N State Street, P.O. 
Box 167, Neshkoro, WI 54960[hyphen]0167; phone: 973-998-8400; email_
[email protected]
    i. FERC Contact: Laura Washington at (202) 502-6072; or email at 
[email protected].
    j. Midwest Hydro and STS Hydropower filed separate requests to use 
the Traditional Licensing Process on August 30, 2019. Midwest Hydro and 
STS Hydropower provided public notice of their requests on August 30, 
2019. In a letter dated October 16, 2019, the Director of the Division 
of Hydropower Licensing approved the requests to use the Traditional 
Licensing Process.
    k. With this notice, we are initiating informal consultation with 
the U.S. Fish and Wildlife Service and/or National Oceanic and 
Atmospheric Administration (NOAA) Fisheries under section 7 of the 
Endangered Species Act and the joint agency regulations thereunder at 
50 CFR, part 402; and NOAA Fisheries under section 305(b) of the 
Magnuson-Stevens Fishery Conservation and Management Act and 
implementing regulations at 50 CFR 600.920. We are also initiating 
consultation the Wisconsin and Illinois

[[Page 56455]]

State Historic Preservation Officers, as required by section 106, 
National Historical Preservation Act, and the implementing regulations 
of the Advisory Council on Historic Preservation at 36 CFR 800.2.
    l. With this notice, we are designating Midwest Hydro and STS 
Hydropower as the Commission's non-federal representatives for carrying 
out informal consultation, pursuant to section 7 of the Endangered 
Species Act and section 305(b) of the Magnuson-Stevens Fishery 
Conservation and Management Act; and consultation pursuant to section 
106 of the National Historic Preservation Act.
    m. Midwest Hydro and STS Hydropower filed Pre-Application Documents 
(PAD); including a proposed process plan and schedule for each project 
with the Commission, pursuant to 18 CFR 5.6 of the Commission's 
regulations.
    n. A copy of the PADs are available for review at the Commission in 
the Public Reference Room or may be viewed on the Commission's website 
(https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket 
number, excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). A copy is also available for inspection and reproduction at 
the address in paragraph h.
    o. The licensees state their unequivocal intent to submit an 
application for a new license for Project Nos. 2347, 2348, 2373, and 
2446. Pursuant to 18 CFR 16.8, 16.9, and 16.10, each application for a 
new license and any competing license applications must be filed with 
the Commission at least 24 months prior to the expiration of the 
existing license. All applications for license for these projects must 
be filed by August 31, 2022.
    p. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to these or other pending projects. For assistance, contact 
FERC Online Support.

    Dated: October 16, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-23004 Filed 10-21-19; 8:45 am]