Texas Eastern Transmission LP; Notice of Schedule for Environmental Review of the Bailey East Mine Project, 56451-56452 [2019-22998]

Download as PDF Federal Register / Vol. 84, No. 204 / Tuesday, October 22, 2019 / Notices also serve a copy of the document on that resource agency. k. Description of Request: Duke Energy Carolinas, LLC proposes to allow the expansion of Lake James Marina from the existing 68 boat slips to a total of 240 boat slips. The marina would also serve as a staging area for dock construction and shoreline stabilization activities. The marina would continue to be operated as a True Public Marina, providing public restrooms, a fuel dock, a waste pump station, and marina store. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE, Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1–866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. Agencies may obtain copies of the application directly from the applicant. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214, respectively. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Documents: Any filing must (1) bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person VerDate Sep<11>2014 17:02 Oct 21, 2019 Jkt 250001 commenting, protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary basis. Any filing made by an intervenor must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 385.2010. Dated: October 16, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–23003 Filed 10–21–19; 8:45 am] BILLING CODE 6717–01–P 56451 Project Description Texas Eastern proposes excavate and elevate sections of four natural gas transmission pipelines due to longwall mining activities in Marshall County, West Virginia. The project would allow for safe and efficient operation of Texas Eastern’s existing pipeline facilities for the duration of the longwall mining activities planned by CONSOL Energy Inc. in the area beneath Texas Eastern’s pipelines. The four mainline segments will remain in-service and be elevated using sandbags and skids for about 2 years until the longwall mining activities have completed and any potential ground subsidence has settled. Background DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP19–501–000] Texas Eastern Transmission LP; Notice of Schedule for Environmental Review of the Bailey East Mine Project On August 19, 2019, Texas Eastern Transmission LP (Texas Eastern) filed an application in Docket No. CP19–501– 000 requesting a Certificate of Public Convenience and Necessity pursuant to Section 7(c) of the Natural Gas Act to construct and operate certain natural gas pipeline facilities. The proposed project, known as the Bailey East Mine Project (Project), would ensure safe and efficient operation of existing Texas Eastern pipeline facilities for the duration of planned longwall mining activities. On September 3, 2019, the Federal Energy Regulatory Commission (Commission or FERC) issued its Notice of Application for the Project. Among other things, that notice alerted agencies issuing federal authorizations of the requirement to complete all necessary reviews and to reach a final decision on a request for a federal authorization within 90 days of the date of issuance of the Commission staff’s Environmental Assessment (EA) for the Project. This instant notice identifies the FERC staff’s planned schedule for the completion of the EA for the Project. Schedule for Environmental Review Issuance of EA—January 28, 2020 90-day Federal Authorization Decision Deadline—April 27, 2020 If a schedule change becomes necessary, additional notice will be provided so that the relevant agencies are kept informed of the Project’s progress. PO 00000 Frm 00041 Fmt 4703 Sfmt 4703 On October 3, 2019, the Commission issued a Notice of Intent to Prepare an Environmental Assessment for the Proposed Bailey East Mine Project and Request for Comments on Environmental Issues (NOI). The NOI was sent to affected landowners; federal, state, and local government agencies; elected officials; environmental and public interest groups; Native American tribes; other interested parties; and local libraries and newspapers. In response to the NOI, the Commission received no comments to date. All substantive comments will be addressed in the EA. Additional Information In order to receive notification of the issuance of the EA and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the ‘‘eLibrary’’ link, select ‘‘General Search’’ from the eLibrary menu, enter the selected date range and ‘‘Docket Number’’ excluding the last three digits (i.e., CP19–501), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. E:\FR\FM\22OCN1.SGM 22OCN1 56452 Federal Register / Vol. 84, No. 204 / Tuesday, October 22, 2019 / Notices Dated: October 16, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–22998 Filed 10–21–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 4492–003] Montgomery Worsted Mills, City Winery Hudson Valley LLC; Notice of Transfer of Exemption 1. On June 11, 2019, as supplemented July 16, 2019, Montgomery Worsted Mills, exemptee for the Montgomery Worsted Mills Hydroelectric Project No. 4492, filed a letter notifying the Commission that the project was transferred from the Montgomery Worsted Mills to City Winery Hudson Valley LLC. The exemption from licensing was originally issued on September 29, 1981.1 The project is located on the Wallkill River, Orange County, NY. The transfer of an exemption does not require Commission approval. 2. City Winery Hudson Valley LLC is now the exemptee of the Worsted Mills Hydroelectric Project No. 4492. All correspondence must be forwarded to: Mr. Dylan Rocke, City Winery Hudson Valley LLC, 23 Factory Street, Montgomery, NY 12549, Phone: 201– 403–1549, Email: dilan@citywinery.com. Dated: October 16, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–23005 Filed 10–21–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC19–142–000. Applicants: Energy Center Dover LLC, DB Energy Assets, LLC. Description: Supplement to September 26, 2019 Joint Application for Authorization Under Section 203 of the Federal Power Act, et al. of Energy Center Dover LLC, et al. Filed Date: 10/11/19. 1 Steinberger Bros., Inc./Montgomery Worsted Mills, 16 FERC ¶ 62,610 (1981). VerDate Sep<11>2014 17:02 Oct 21, 2019 Jkt 250001 Accession Number: 20191011–5109. Comments Due: 5 p.m. ET 10/25/19. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER16–1255–014; ER15–2679–013; ER15–2680–013; ER15–762–017; ER16–1609–007; ER16– 1738–011; ER16–1901–011; ER16–1955– 011; ER16–2201–010; ER16–2224–010; ER16–2541–010; ER16–2578–011; ER16–468–011; ER16–474–012; ER16– 890–012; ER17–1864–009; ER17–1871– 009; ER17–1909–009; ER17–306–010; ER17–544–010; ER18–1667–004; ER18– 2327–003; ER18–2492–005; ER19–846– 004; ER19–847–004. Applicants: Antelope Big Sky Ranch LLC, Antelope DSR 1, LLC, Antelope DSR 2, LLC, Antelope DSR 3, LLC, Antelope Expansion 2, LLC, Bayshore Solar B, LLC, Bayshore Solar A, LLC, Bayshore Solar C, LLC, Beacon Solar 1, LLC, Beacon Solar 3, LLC, Beacon Solar 4, LLC, Central Antelope Dry Ranch C LLC, Elevation Solar C LLC, FTS Master Tenant 1, LLC, FTS Master Tenant 2, LLC, ID Solar 1, LLC, Latigo Wind Park, LLC, North Lancaster Ranch LLC, Pioneer Wind Park I, LLC, Riverhead Solar Farm, LLC, San Pablo Raceway, LLC, Sandstone Solar LLC, Sierra Solar Greenworks LLC, Solverde 1, LLC, Summer Solar LLC, Western Antelope Blue Sky Ranch A LLC, Western Antelope Blue Sky Ranch B LLC, Western Antelope Dry Ranch LLC, 65HK 8me LLC, 67RK 8me LLC, 87RL 8me LLC. Description: Supplement to June 28, 2019 Triennial Market Power Analysis for the Northwest Region of Antelope Big Sky Ranch LLC, et al. Filed Date: 10/15/19. Accession Number: 20191015–5371. Comments Due: 5 p.m. ET 11/5/19. Docket Numbers: ER19–2383–002. Applicants: AEP Texas Inc. Description: Tariff Amendment: SA772 AEPTX-Karankawa Wind Interconnection Agr 1st Amend & Restat—Amendment to be effective 6/ 20/2019. Filed Date: 10/16/19. Accession Number: 20191016–5160. Comments Due: 5 p.m. ET 11/6/19. Docket Numbers: ER19–956–001. Applicants: Midcontinent Independent System Operator, Inc., ITC Midwest LLC. Description: Tariff Amendment: 2019–10–16_Amendment to ITCM Intangible Plant Filing to be effective 1/ 1/2020. Filed Date: 10/16/19. Accession Number: 20191016–5056. Comments Due: 5 p.m. ET 10/28/19. Docket Numbers: ER20–122–000. PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 Applicants: Crowned Ridge Interconnection, LLC. Description: Baseline eTariff Filing: Crowned Ridge Interconnection, LLC Application for Market-Based Rates to be effective 12/4/2019. Filed Date: 10/15/19. Accession Number: 20191015–5323. Comments Due: 5 p.m. ET 11/5/19. Docket Numbers: ER20–123–000. Applicants: J. Aron & Company LLC. Description: § 205(d) Rate Filing: CIS & NW Cat 2 Notice to be effective 10/ 16/2019. Filed Date: 10/15/19. Accession Number: 20191015–5358. Comments Due: 5 p.m. ET 11/5/19. Docket Numbers: ER20–124–000. Applicants: Evergy Missouri West, Inc. Description: Tariff Cancellation: Request for Cancellation, KCP&L GMO Vol. 28 (MBR) Tariff Title Database to be effective 12/16/2019. Filed Date: 10/15/19. Accession Number: 20191015–5359. Comments Due: 5 p.m. ET 11/5/19. Docket Numbers: ER20–125–000. Applicants: Evergy Missouri West, Inc. Description: Tariff Cancellation: Request for Cancellation, KCP&L GMO Vol. 33 (CB) Tariff Title Database to be effective 12/16/2019. Filed Date: 10/15/19. Accession Number: 20191015–5361. Comments Due: 5 p.m. ET 11/5/19. Docket Numbers: ER20–126–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Amendment to Original ISA No. 4401, Queue No. AA1–095 to be effective 1/ 25/2016. Filed Date: 10/16/19. Accession Number: 20191016–5077. Comments Due: 5 p.m. ET 11/6/19. Docket Numbers: ER20–127–000. Applicants: PacifiCorp. Description: § 205(d) Rate Filing: BPA Construct Agmt for Lost Creek BAA Move to be effective 12/16/2019. Filed Date: 10/16/19. Accession Number: 20191016–5105. Comments Due: 5 p.m. ET 11/6/19. Docket Numbers: ER20–128–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Orginal ISA SA No. 5492; Queue No. AE2–272 to be effective 9/17/2019. Filed Date: 10/16/19. Accession Number: 20191016–5106. Comments Due: 5 p.m. ET 11/6/19. Take notice that the Commission received the following qualifying facility filings: E:\FR\FM\22OCN1.SGM 22OCN1

Agencies

[Federal Register Volume 84, Number 204 (Tuesday, October 22, 2019)]
[Notices]
[Pages 56451-56452]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-22998]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-501-000]


Texas Eastern Transmission LP; Notice of Schedule for 
Environmental Review of the Bailey East Mine Project

    On August 19, 2019, Texas Eastern Transmission LP (Texas Eastern) 
filed an application in Docket No. CP19-501-000 requesting a 
Certificate of Public Convenience and Necessity pursuant to Section 
7(c) of the Natural Gas Act to construct and operate certain natural 
gas pipeline facilities. The proposed project, known as the Bailey East 
Mine Project (Project), would ensure safe and efficient operation of 
existing Texas Eastern pipeline facilities for the duration of planned 
longwall mining activities.
    On September 3, 2019, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for the completion of the 
EA for the Project.

Schedule for Environmental Review

Issuance of EA--January 28, 2020
90-day Federal Authorization Decision Deadline--April 27, 2020

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Texas Eastern proposes excavate and elevate sections of four 
natural gas transmission pipelines due to longwall mining activities in 
Marshall County, West Virginia. The project would allow for safe and 
efficient operation of Texas Eastern's existing pipeline facilities for 
the duration of the longwall mining activities planned by CONSOL Energy 
Inc. in the area beneath Texas Eastern's pipelines. The four mainline 
segments will remain in-service and be elevated using sandbags and 
skids for about 2 years until the longwall mining activities have 
completed and any potential ground subsidence has settled.

Background

    On October 3, 2019, the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed Bailey East Mine 
Project and Request for Comments on Environmental Issues (NOI). The NOI 
was sent to affected landowners; federal, state, and local government 
agencies; elected officials; environmental and public interest groups; 
Native American tribes; other interested parties; and local libraries 
and newspapers. In response to the NOI, the Commission received no 
comments to date. All substantive comments will be addressed in the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP19-501), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.


[[Page 56452]]


    Dated: October 16, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-22998 Filed 10-21-19; 8:45 am]
 BILLING CODE 6717-01-P