Notice of Application; Sabine Pass Liquefaction, LLC, Sabine Pass LNG, L.P., 55307-55308 [2019-22524]

Download as PDF Federal Register / Vol. 84, No. 200 / Wednesday, October 16, 2019 / Notices 55307 1060TH—MEETING, OPEN MEETING—Continued [October 17, 2019, 10:00 a.m.] Item No. Docket No. Company H–3 ................. P–2079–081 ........................................................ Placer County Water Agency. CERTIFICATES C–1 ................. C–2 ................. CP19–52–000 ..................................................... CP18–186–000 ................................................... Issued: October 10, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. A free webcast of this event is available through https:// ferc.capitolconnection.org/. Anyone with internet access who desires to view this event can do so by navigating to www.ferc.gov’s Calendar of Events and locating this event in the Calendar. The event will contain a link to its webcast. The Capitol Connection provides technical support for the free webcasts. It also offers access to this event via television in the DC area and via phone bridge for a fee. If you have any questions, visit https:// ferc.capitolconnection.org/ or contact Shirley Al-Jarani at 703–993–3104. Immediately following the conclusion of the Commission Meeting, a press briefing will be held in the Commission Meeting Room. Members of the public may view this briefing in the designated overflow room. This statement is intended to notify the public that the press briefings that follow Commission meetings may now be viewed remotely at Commission headquarters, but will not be telecast through the Capitol Connection service. [FR Doc. 2019–22673 Filed 10–11–19; 4:15 pm] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP19–515–000] khammond on DSKJM1Z7X2PROD with NOTICES Notice of Application; Sabine Pass Liquefaction, LLC, Sabine Pass LNG, L.P. Take notice that on September 27, 2019, Sabine Pass Liquefaction, LLC (Sabine Pass Liquefaction) and Sabine Pass LNG, L.P. (Sabine Pass LNG), 700 Milam Street, Suite 1900, Houston, TX 77002, filed an application under section 3(a) of the Natural Gas Act for an amendment to the authorizations granted by the Commission on April 16, 2012, in Docket No. CP11–72–000, as amended, which authorized the Sabine VerDate Sep<11>2014 17:10 Oct 15, 2019 Jkt 250001 Natural Gas Pipeline Company of America LLC. Transcontinental Gas Pipe Line Company, LLC. Pass Liquefaction Project in Cameron Parish, Louisiana (Liquefaction Project), and the authorization granted by the Commission on April 6, 2015, in Docket No. CP13–552–000, which authorized an expansion of the Liquefaction Project (Liquefaction Expansion Project). Specifically, Sabine Pass Liquefaction and Sabine Pass LNG request authorization to increase the total liquefied natural gas production capacity of the Liquefaction Project and the Liquefaction Expansion Project from approximately 1,509 billion cubic feet per year (Bcf/y) to 1,661.94 Bcf/y, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this application may be directed to Karri Mahmoud, Cheniere Energy, Inc. 700 Milam Street, Suite 1900, Houston, Texas 77002, by telephone at (713) 375– 5000, or by email at karri.mahmoud@ cheniere.com. Pursuant to section 157.9 of the Commission’s rules (18 CFR 157.9), within 90 days of this Notice, the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 3 copies of filings made with the Commission and must provide a copy to the applicant and to every other party. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s E:\FR\FM\16OCN1.SGM 16OCN1 55308 Federal Register / Vol. 84, No. 200 / Wednesday, October 16, 2019 / Notices environmental mailing list, and will be notified of any meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission and will not have the right to seek court review of the Commission’s final order. As of the February 27, 2018 date of the Commission’s order in Docket No. CP16–4–001, the Commission will apply its revised practice concerning out-of-time motions to intervene in any new Natural Gas Act section 3 or section 7 proceeding.1 Persons desiring to become a party to a certificate proceeding are to intervene in a timely manner. If seeking to intervene out-oftime, the movant is required to show good cause why the time limitation should be waived, and should provide justification by reference to factors set forth in Rule 214(d)(1) of the Commission’s Rules and Regulations.2 The Commission strongly encourages electronic filings of comments, protests, and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 3 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Comment Date: 5:00 p.m. Eastern Time on October 30, 2019. Dated: October 9, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–22524 Filed 10–15–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Effectiveness of Exempt Wholesale Generator and Status khammond on DSKJM1Z7X2PROD with NOTICES Wilton Wind Energy II, LLC Roadrunner Solar Project, LLC. High Lonesome Wind Power, LLC. Grazing Yak Solar, LLC ....... Caden Energix Hickory LLC EG19–145– 000 EG19–146– 000 EG19–147– 000 EG19–148– 000 EG19–149– 000 1 Tennessee Gas Pipeline Company, L.L.C., 162 FERC 61,167 at 50 (2018). 2 18 CFR 385.214(d)(1). VerDate Sep<11>2014 17:10 Oct 15, 2019 Jkt 250001 East Blackland Solar Project 1 LLC. RE Maplewood LLC ............. RE Maplewood 2 LLC .......... Hickory Run Energy, LLC .... Lapetus Energy Project, LLC Palmer Solar, LLC ................ South Field Energy LLC ....... DWW Solar II, LLC .............. Wright Solar Park LLC ......... EG19–150– 000 EG19–151– 000 EG19–152– 000 EG19–153– 000 EG19–154– 000 EG19–155– 000 EG19–156– 000 EG19–157– 000 EG19–158– 000 Take notice that during the month of September 2019, the status of the abovecaptioned entities as Exempt Wholesale Generators became effective by operation of the Commission’s regulations. 18 CFR 366.7(a) (2019). Dated: October 9, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–22525 Filed 10–15–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG20–7–000. Applicants: Lincoln Clean Energy, LLC. Description: Notice of SelfCertification of Willow Creek Wind, LLC. Filed Date: 10/7/19. Accession Number: 20191007–5139. Comments Due: 5 p.m. ET 10/28/19. Docket Numbers: EG20–8–000. Applicants: Lincoln Clean Energy, LLC. Description: Notice of SelfCertification of EG of Plum Creek Wind, LLC. Filed Date: 10/7/19. Accession Number: 20191007–5140. Comments Due: 5 p.m. ET 10/28/19. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER19–469–002. Applicants: PJM Interconnection, L.L.C. Description: Compliance filing: Filing to Request Change to Effective Date from 12/3/2019 to 12/31/9998 to be effective 12/31/9998. PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 Filed Date: 10/8/19. Accession Number: 20191008–5112. Comments Due: 5 p.m. ET 10/29/19. Docket Numbers: ER19–2463–001. Applicants: Utah Red Hills Renewable Park, LLC. Description: Notice of Non-Material Change in Status of Utah Red Hills Renewable Park, LLC. Filed Date: 10/7/19. Accession Number: 20191007–5162. Comments Due: 5 p.m. ET 10/28/19. Docket Numbers: ER20–17–000. Applicants: Tenaska Pennsylvania Partners, LLC. Description: Report Filing: Informational Filing Regarding Upstream Change in Control and Request for Waiver to be effective N/A. Filed Date: 10/4/19. Accession Number: 20191004–5121. Comments Due: 5 p.m. ET 10/25/19. Docket Numbers: ER20–45–000. Applicants: PJM Interconnection, L.L.C. Description: Compliance filing: Revisions to OA, Schedule 6, sec 1.5 re: Commission’s 8/30/2019 order in EL19– 61 to be effective 1/1/2020. Filed Date: 10/7/19. Accession Number: 20191007–5145. Comments Due: 5 p.m. ET 10/28/19. Docket Numbers: ER20–46–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2019–10–08_SA 3359 METC-IsabellaIsabella II MPFCA (J717 J728) to be effective 9/24/2019. Filed Date: 10/8/19. Accession Number: 20191008–5040. Comments Due: 5 p.m. ET 10/29/19. Docket Numbers: ER20–47–000. Applicants: Nevada Power Company. Description: § 205(d) Rate Filing: Amended and Restate Rate Schedule Facilities Agreement to be effective 12/ 8/2019. Filed Date: 10/8/19. Accession Number: 20191008–5086. Comments Due: 5 p.m. ET 10/29/19. Docket Numbers: ER20–49–000. Applicants: Mid-Atlantic Interstate Transmission, LLC, PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: MAIT submits OIA SA No. 4577 to be effective 12/7/2019. Filed Date: 10/8/19. Accession Number: 20191008–5097. Comments Due: 5 p.m. ET 10/29/19. Docket Numbers: ER20–50–000. Applicants: Louisville Gas and Electric Company. Description: § 205(d) Rate Filing: EKPC West Shelby CIAC to be effective 12/9/2019. E:\FR\FM\16OCN1.SGM 16OCN1

Agencies

[Federal Register Volume 84, Number 200 (Wednesday, October 16, 2019)]
[Notices]
[Pages 55307-55308]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-22524]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-515-000]


Notice of Application; Sabine Pass Liquefaction, LLC, Sabine Pass 
LNG, L.P.

    Take notice that on September 27, 2019, Sabine Pass Liquefaction, 
LLC (Sabine Pass Liquefaction) and Sabine Pass LNG, L.P. (Sabine Pass 
LNG), 700 Milam Street, Suite 1900, Houston, TX 77002, filed an 
application under section 3(a) of the Natural Gas Act for an amendment 
to the authorizations granted by the Commission on April 16, 2012, in 
Docket No. CP11-72-000, as amended, which authorized the Sabine Pass 
Liquefaction Project in Cameron Parish, Louisiana (Liquefaction 
Project), and the authorization granted by the Commission on April 6, 
2015, in Docket No. CP13-552-000, which authorized an expansion of the 
Liquefaction Project (Liquefaction Expansion Project).
    Specifically, Sabine Pass Liquefaction and Sabine Pass LNG request 
authorization to increase the total liquefied natural gas production 
capacity of the Liquefaction Project and the Liquefaction Expansion 
Project from approximately 1,509 billion cubic feet per year (Bcf/y) to 
1,661.94 Bcf/y, all as more fully set forth in the application which is 
on file with the Commission and open to public inspection. The filing 
is available for review at the Commission in the Public Reference Room 
or may be viewed on the Commission's website at https://www.ferc.gov 
using the ``eLibrary'' link. Enter the docket number excluding the last 
three digits in the docket number field to access the document. For 
assistance, contact FERC at [email protected] or call toll-
free, (866) 208-3676 or TTY, (202) 502-8659.
    Any questions regarding this application may be directed to Karri 
Mahmoud, Cheniere Energy, Inc. 700 Milam Street, Suite 1900, Houston, 
Texas 77002, by telephone at (713) 375-5000, or by email at 
[email protected].
    Pursuant to section 157.9 of the Commission's rules (18 CFR 157.9), 
within 90 days of this Notice, the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a Notice of 
Schedule for Environmental Review will serve to notify federal and 
state agencies of the timing for the completion of all necessary 
reviews, and the subsequent need to complete all federal authorizations 
within 90 days of the date of issuance of the Commission staff's EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 3 copies of filings made with the Commission and must provide a 
copy to the applicant and to every other party. Only parties to the 
proceeding can ask for court review of Commission orders in the 
proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's

[[Page 55308]]

environmental mailing list, and will be notified of any meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission and will not have the right to seek court review of the 
Commission's final order.
    As of the February 27, 2018 date of the Commission's order in 
Docket No. CP16-4-001, the Commission will apply its revised practice 
concerning out-of-time motions to intervene in any new Natural Gas Act 
section 3 or section 7 proceeding.\1\ Persons desiring to become a 
party to a certificate proceeding are to intervene in a timely manner. 
If seeking to intervene out-of-time, the movant is required to show 
good cause why the time limitation should be waived, and should provide 
justification by reference to factors set forth in Rule 214(d)(1) of 
the Commission's Rules and Regulations.\2\
---------------------------------------------------------------------------

    \1\ Tennessee Gas Pipeline Company, L.L.C., 162 FERC 61,167 at 
50 (2018).
    \2\ 18 CFR 385.214(d)(1).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filings of comments, 
protests, and interventions in lieu of paper using the eFiling link at 
https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 3 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE, Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on October 30, 2019.

    Dated: October 9, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-22524 Filed 10-15-19; 8:45 am]
BILLING CODE 6717-01-P