Southern Nuclear Operating Company Inc.; Vogtle Electric Generating Plant Units 3 and 4; Inspections, Tests, Analyses, and Acceptance Criteria, 55183-55184 [2019-22383]

Download as PDF Federal Register / Vol. 84, No. 199 / Tuesday, October 15, 2019 / Notices tone phone to participate in this meeting. Any interested person may dial the toll-free access number 1–888–324– 9238 or toll access number 1–517–308– 9132, and then the numeric participant passcode: 3403297, to participate in this meeting by telephone for both days. The WebEx link is https://nasaenterprise. webex.com , the meeting number is 909 467 766, and the password is Exploration@2019 (case sensitive) for both days. The agenda for the meeting includes the following topics: —Human Exploration and Operations Overview —Low Earth Orbit Commercialization —Commercial Crew —Launch Services Program —Exploration Systems Development —Advanced Exploration Systems (Deep Space Exploration) khammond on DSKJM1Z7X2PROD with NOTICES Attendees will be requested to sign a register and to comply with NASA Kennedy Space Center security requirements, including the presentation of a valid picture ID to NASA Security before access to NASA Kennedy Space Center. To attend the meeting in person, attendees that are U.S. citizens and Permanent Residents (green card holders) are requested to provide full name and citizenship status no less than 3 working days prior to the meeting. Foreign nationals attending this meeting will be required to provide a copy of their passport and visa in addition to providing the following information no less than 15 days prior to the meeting: Full name; gender; date/ place of birth; citizenship; passport information (number, country, telephone); visa information (number, type, expiration date); employer/ affiliation information (name of institution, address, country, telephone); title/position of attendee. Information should be sent to Dr. Bette Siegel via email at bette.siegel@ nasa.gov. It is imperative that the meeting be held on these dates to accommodate the scheduling priorities of the key participants. Patricia Rausch, Advisory Committee Management Officer, National Aeronautics and Space Administration. [FR Doc. 2019–22336 Filed 10–11–19; 8:45 am] BILLING CODE 7510–13–P VerDate Sep<11>2014 16:25 Oct 11, 2019 Jkt 250001 NATIONAL AERONAUTICS AND SPACE ADMINISTRATION [Notice: (19–066)] NASA Advisory Council; Meeting. National Aeronautics and Space Administration. ACTION: Notice of meeting. AGENCY: In accordance with the Federal Advisory Committee Act, as amended, the National Aeronautics and Space Administration (NASA) announces a meeting of the NASA Advisory Council (NAC). DATES: Thursday, October 31, 2019, 10:30 a.m.–5:00 p.m.; and Friday, November 1, 2019, 8:30 a.m.–12:00 noon, Eastern Time. ADDRESSES: NASA Kennedy Space Center, Headquarters Building, Conference Room 7212, Kennedy Space Center, Florida 32899. FOR FURTHER INFORMATION CONTACT: Ms. Marcia Joseph, NAC Administrative Officer, NASA Headquarters, Washington, DC 20546, (202) 358–4717 or marcia.joseph@nasa.gov. SUPPLEMENTARY INFORMATION: This meeting will be open to the public up to the capacity of the meeting room. This meeting is also available telephonically and by WebEx. You must use a touch-tone phone to participate in this meeting. Any interested person may dial the toll-free number 1–888–324– 3866 or toll number 1–517–308–9316 and then the numeric passcode 5441938, followed by the # sign, on both days. NOTE: If dialing in, please ‘‘mute’’ your phone. To join via WebEx, the link is https://nasaenterprise.webex.com/. The meeting number on October 31 is 903 420 221 and the meeting password is NAC31oct19! (case sensitive); the meeting number on November 1 is 902 236 617 and the meeting password is NAC1nov19! (case sensitive). The agenda for the meeting will include reports from the following: — Aeronautics Committee — Human Exploration and Operations Committee — Regulatory and Policy Committee — Science Committee — STEM Engagement Committee — Technology, Innovation and Engineering Committee Attendees will be requested to sign a register and to comply with NASA Kennedy Space Center security requirements, including the presentation of a valid picture ID to NASA Security before access to NASA Kennedy Space Center. To attend the meeting in person, attendees that are SUMMARY: PO 00000 Frm 00050 Fmt 4703 Sfmt 4703 55183 U.S. citizens and Permanent Residents (green card holders) are requested to provide full name and citizenship status no less than 3 working days prior to the meeting. Foreign nationals attending this meeting will be required to provide a copy of their passport and visa in addition to providing the following information no less than 15 days prior to the meeting: Full name; gender; date/ place of birth; citizenship; passport information (number, country, telephone); visa information (number, type, expiration date); employer/ affiliation information (name of institution, address, country, telephone); title/position of attendee. Information should be sent to Ms. Marcia Joseph via email at marcia.joseph@nasa.gov. It is imperative that the meeting be held on these dates to accommodate the scheduling priorities of the key participants. Patricia Rausch, Advisory Committee Management Officer, National Aeronautics and Space Administration. [FR Doc. 2019–22337 Filed 10–11–19; 8:45 am] BILLING CODE 7510–13–P NUCLEAR REGULATORY COMMISSION [Docket Nos. 52–025 and 52–026; NRC– 2008–0252] Southern Nuclear Operating Company Inc.; Vogtle Electric Generating Plant Units 3 and 4; Inspections, Tests, Analyses, and Acceptance Criteria Nuclear Regulatory Commission. ACTION: Determination of the successful completion of inspections, tests, and analyses. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) staff has determined that specified inspections, tests, and analyses have been successfully completed, and that specified acceptance criteria are met for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4. DATES: Determinations of the successful completion of inspections, tests, and analyses for VEGP Units 3 and 4 takes effect on the dates indicated in the NRC staff’s verification evaluation forms for the inspections, tests, analyses, and acceptance criteria (ITAAC). ADDRESSES: Please refer to Docket ID NRC–2008–0252 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available SUMMARY: E:\FR\FM\15OCN1.SGM 15OCN1 55184 Federal Register / Vol. 84, No. 199 / Tuesday, October 15, 2019 / Notices information related to this document using any of the following methods: • Federal Rulemaking Website: Go to https://www.regulations.gov/ and search for Docket ID NRC–2008–0252. Address questions about NRC docket IDs to Anne Frost; telephone: 301–287–9232; email: Anne.Frost@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, 301– 415–4737, or by email to pdr.resource@ nrc.gov. The ADAMS accession number for each document referenced in this document (if that document is available in ADAMS) is provided the first time that a document is referenced. • NRC’s PDR: You may examine and purchase copies of public documents at the NRC’s PDR, Room O1–F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. FOR FURTHER INFORMATION CONTACT: Chandu Patel, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001; telephone: 301–415–3025; email: Chandu.Patel@ nrc.gov. SUPPLEMENTARY INFORMATION: khammond on DSKJM1Z7X2PROD with NOTICES I. Licensee Notification of Completion of ITAAC Southern Nuclear Operating Company, Inc. (SNC), Georgia Power Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC., MEAG Power SPVJ, LLC., MEAG Power SPVP, LLC., and the City of Dalton, Georgia, (hereafter called the licensee) has submitted ITAAC closure notifications (ICNs) under § 52.99(c)(1) of title 10 of the Code of Federal Regulations (10 CFR), informing the NRC that the licensee has successfully performed the required inspections, tests, and analyses, and that the acceptance criteria are met for: VEGP Unit 3 ITAAC 2.1.02.08d.v (36), 2.2.03.08c.iii (182), 2.2.03.08c.iv.02 (184), 2.3.03.02 (319), 2.3.05.03a.ii (344), 2.3.05.03c.i (349), 2.3.05.03d.i (351), 2.3.07.07b.i (402), 2.3.10.02a (431), 3.3.00.06b (788), 2.2.05.07e (880), and 2.3.07.07b.vii (881). VEGP Unit 4 ITAAC VerDate Sep<11>2014 16:25 Oct 11, 2019 Jkt 250001 2.2.03.08c.v.01 (187), 2.2.03.08d (200), 2.3.09.03.iii (425), C.2.6.12.01 (671), C.2.6.12.02 (672), C.2.6.12.03 (673), C.2.6.12.04 (674), C.2.6.12.05 (675), and C.2.6.12.06 (676). The ITAAC for VEGP Unit 3 are in Appendix C of the VEGP Unit 3 combined license (ADAMS Accession No. ML14100A106). The ITAAC for VEGP Unit 4 are in Appendix C of VEGP Unit 4 combined license (ADAMS Accession No. ML14100A135). II. Licensee ITAAC Post-Closure Notifications Since the last Federal Register notice of the NRC staff’s determinations of successful completion of inspections, tests, and analyses for VEGP Units 3 and 4, the NRC staff has not made additional determinations of the successful completion of inspections, tests, and analyses based on licensee ITAAC postclosure notifications (IPCNs) submitted under 10 CFR 52.99(c)(2). III. NRC Staff Determination of Completion of ITAAC The NRC staff has determined that the specified inspections, tests, and analyses have been successfully completed, and that the specified acceptance criteria are met. The documentation of the NRC staff’s determination is in the ITAAC Closure Verification Evaluation Form (VEF) for each ITAAC. The VEF is a form that represents the NRC staff’s structured process for reviewing ICNs and IPCNs. Each ICN presents a narrative description of how the ITAAC was completed. The NRC’s ICN review process involves a determination on whether, among other things: (1) Each ICN provides sufficient information, including a summary of the methodology used to perform the ITAAC, to demonstrate that the inspections, tests, and analyses have been successfully completed; (2) each ICN provides sufficient information to demonstrate that the acceptance criteria of the ITAAC are met; and (3) any NRC inspections for the ITAAC have been completed and any ITAAC findings associated with that ITAAC have been closed. The NRC’s review process for IPCNs is similar to that for ICNs but focuses on how the licensee addressed the new material information giving rise to the IPCN. The NRC staff’s determination of the successful completion of these ITAAC is based on information available at this time and is subject to the licensee’s ability to maintain the condition that the acceptance criteria are met. If the NRC staff receives new information that PO 00000 Frm 00051 Fmt 4703 Sfmt 4703 suggests the NRC staff’s determination on any of these ITAAC is incorrect, then the NRC staff will determine whether to reopen that ITAAC (including withdrawing the NRC staff’s determination on that ITAAC). The NRC staff’s determination will be used to support a subsequent finding, pursuant to 10 CFR 52.103(g), at the end of construction that all acceptance criteria in the combined license are met. The ITAAC closure process is not finalized for these ITAAC until the NRC makes an affirmative finding under 10 CFR 52.103(g). Any future updates to the status of these ITAAC will be reflected on the NRC’s website at https:// www.nrc.gov/reactors/new-reactors/ oversight/itaac.html. This notice fulfills the NRC staff’s obligations under 10 CFR 52.99(e)(1) to publish a notice in the Federal Register of the NRC staff’s determination of the successful completion of inspections, tests, and analyses. Vogtle Electric Generating Plant Unit 3, Docket No. 5200025 A complete list of the review status for VEGP Unit 3 ITAAC, including the submission date and ADAMS accession number for each ICN received, the ADAMS accession number for each VEF, and the ADAMS accession numbers for the inspection reports associated with these specific ITAAC, can be found on the NRC’s website at https://www.nrc.gov/reactors/newreactors/new-licensing-files/vog3icnsr.pdf. Vogtle Electric Generating Plant Unit 4, Docket No. 5200026 A complete list of the review status for VEGP Unit 4 ITAAC, including the submission date and ADAMS accession number for each ICN and IPCN received, the ADAMS accession number for each VEF, and the ADAMS accession numbers for the inspection reports associated with these specific ITAAC, can be found on the NRC’s website at https://www.nrc.gov/reactors/newreactors/new-licensing-files/vog4icnsr.pdf. Dated at Rockville, Maryland, this 8th day of October, 2019. For the Nuclear Regulatory Commission. Victor E. Hall, Chief, Construction Inspection Program Branch, Division of Licensing, Siting, and Environmental Analysis, Office of New Reactors. [FR Doc. 2019–22383 Filed 10–11–19; 8:45 am] BILLING CODE 7590–01–P E:\FR\FM\15OCN1.SGM 15OCN1

Agencies

[Federal Register Volume 84, Number 199 (Tuesday, October 15, 2019)]
[Notices]
[Pages 55183-55184]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-22383]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 52-025 and 52-026; NRC-2008-0252]


Southern Nuclear Operating Company Inc.; Vogtle Electric 
Generating Plant Units 3 and 4; Inspections, Tests, Analyses, and 
Acceptance Criteria

AGENCY: Nuclear Regulatory Commission.

ACTION: Determination of the successful completion of inspections, 
tests, and analyses.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) staff has 
determined that specified inspections, tests, and analyses have been 
successfully completed, and that specified acceptance criteria are met 
for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4.

DATES: Determinations of the successful completion of inspections, 
tests, and analyses for VEGP Units 3 and 4 takes effect on the dates 
indicated in the NRC staff's verification evaluation forms for the 
inspections, tests, analyses, and acceptance criteria (ITAAC).

ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available

[[Page 55184]]

information related to this document using any of the following 
methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov/ and search for Docket ID NRC-2008-0252. Address 
questions about NRC docket IDs to Anne Frost; telephone: 301-287-9232; 
email: [email protected]. For technical questions, contact the 
individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected]. The ADAMS accession number for each 
document referenced in this document (if that document is available in 
ADAMS) is provided the first time that a document is referenced.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Chandu Patel, Office of New Reactors, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; 
telephone: 301-415-3025; email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Licensee Notification of Completion of ITAAC

    Southern Nuclear Operating Company, Inc. (SNC), Georgia Power 
Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC., MEAG 
Power SPVJ, LLC., MEAG Power SPVP, LLC., and the City of Dalton, 
Georgia, (hereafter called the licensee) has submitted ITAAC closure 
notifications (ICNs) under Sec.  52.99(c)(1) of title 10 of the Code of 
Federal Regulations (10 CFR), informing the NRC that the licensee has 
successfully performed the required inspections, tests, and analyses, 
and that the acceptance criteria are met for:

VEGP Unit 3 ITAAC
    2.1.02.08d.v (36), 2.2.03.08c.iii (182), 2.2.03.08c.iv.02 (184), 
2.3.03.02 (319), 2.3.05.03a.ii (344), 2.3.05.03c.i (349), 2.3.05.03d.i 
(351), 2.3.07.07b.i (402), 2.3.10.02a (431), 3.3.00.06b (788), 
2.2.05.07e (880), and 2.3.07.07b.vii (881).
VEGP Unit 4 ITAAC
    2.2.03.08c.v.01 (187), 2.2.03.08d (200), 2.3.09.03.iii (425), 
C.2.6.12.01 (671), C.2.6.12.02 (672), C.2.6.12.03 (673), C.2.6.12.04 
(674), C.2.6.12.05 (675), and C.2.6.12.06 (676).

    The ITAAC for VEGP Unit 3 are in Appendix C of the VEGP Unit 3 
combined license (ADAMS Accession No. ML14100A106). The ITAAC for VEGP 
Unit 4 are in Appendix C of VEGP Unit 4 combined license (ADAMS 
Accession No. ML14100A135).

II. Licensee ITAAC Post-Closure Notifications

    Since the last Federal Register notice of the NRC staff's 
determinations of successful completion of inspections, tests, and 
analyses for VEGP Units 3 and 4, the NRC staff has not made additional 
determinations of the successful completion of inspections, tests, and 
analyses based on licensee ITAAC post-closure notifications (IPCNs) 
submitted under 10 CFR 52.99(c)(2).

III. NRC Staff Determination of Completion of ITAAC

    The NRC staff has determined that the specified inspections, tests, 
and analyses have been successfully completed, and that the specified 
acceptance criteria are met. The documentation of the NRC staff's 
determination is in the ITAAC Closure Verification Evaluation Form 
(VEF) for each ITAAC. The VEF is a form that represents the NRC staff's 
structured process for reviewing ICNs and IPCNs.
    Each ICN presents a narrative description of how the ITAAC was 
completed. The NRC's ICN review process involves a determination on 
whether, among other things: (1) Each ICN provides sufficient 
information, including a summary of the methodology used to perform the 
ITAAC, to demonstrate that the inspections, tests, and analyses have 
been successfully completed; (2) each ICN provides sufficient 
information to demonstrate that the acceptance criteria of the ITAAC 
are met; and (3) any NRC inspections for the ITAAC have been completed 
and any ITAAC findings associated with that ITAAC have been closed. The 
NRC's review process for IPCNs is similar to that for ICNs but focuses 
on how the licensee addressed the new material information giving rise 
to the IPCN.
    The NRC staff's determination of the successful completion of these 
ITAAC is based on information available at this time and is subject to 
the licensee's ability to maintain the condition that the acceptance 
criteria are met. If the NRC staff receives new information that 
suggests the NRC staff's determination on any of these ITAAC is 
incorrect, then the NRC staff will determine whether to reopen that 
ITAAC (including withdrawing the NRC staff's determination on that 
ITAAC). The NRC staff's determination will be used to support a 
subsequent finding, pursuant to 10 CFR 52.103(g), at the end of 
construction that all acceptance criteria in the combined license are 
met. The ITAAC closure process is not finalized for these ITAAC until 
the NRC makes an affirmative finding under 10 CFR 52.103(g). Any future 
updates to the status of these ITAAC will be reflected on the NRC's 
website at https://www.nrc.gov/reactors/new-reactors/oversight/itaac.html.
    This notice fulfills the NRC staff's obligations under 10 CFR 
52.99(e)(1) to publish a notice in the Federal Register of the NRC 
staff's determination of the successful completion of inspections, 
tests, and analyses.

Vogtle Electric Generating Plant Unit 3, Docket No. 5200025

    A complete list of the review status for VEGP Unit 3 ITAAC, 
including the submission date and ADAMS accession number for each ICN 
received, the ADAMS accession number for each VEF, and the ADAMS 
accession numbers for the inspection reports associated with these 
specific ITAAC, can be found on the NRC's website at https://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog3-icnsr.pdf.

Vogtle Electric Generating Plant Unit 4, Docket No. 5200026

    A complete list of the review status for VEGP Unit 4 ITAAC, 
including the submission date and ADAMS accession number for each ICN 
and IPCN received, the ADAMS accession number for each VEF, and the 
ADAMS accession numbers for the inspection reports associated with 
these specific ITAAC, can be found on the NRC's website at https://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog4-icnsr.pdf.

    Dated at Rockville, Maryland, this 8th day of October, 2019.

    For the Nuclear Regulatory Commission.
Victor E. Hall,
Chief, Construction Inspection Program Branch, Division of Licensing, 
Siting, and Environmental Analysis, Office of New Reactors.
[FR Doc. 2019-22383 Filed 10-11-19; 8:45 am]