Notice of Intent To Prepare an Environmental Assessment Statement for the Sempra PALNG Holdings, LLC Planned Port Arthur LNG Expansion Project, and Request for Comments on Environmental Issues, 53432-53434 [2019-21793]

Download as PDF 53432 Federal Register / Vol. 84, No. 194 / Monday, October 7, 2019 / Notices Filed Date: 10/1/19. Accession Number: 20191001–5158. Comments Due: 5 p.m. ET 10/22/19. Docket Numbers: ER20–13–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2019–10–01_TO Attachment O’s and ADIT Proration Filing to be effective 1/ 1/2019. Filed Date: 10/1/19. Accession Number: 20191001–5173. Comments Due: 5 p.m. ET 10/22/19. Docket Numbers: ER20–14–000. Applicants: Alabama Power Company. Description: § 205(d) Rate Filing: Sunflower Solar (Lucedale Solar Project) LGIA Filing to be effective 9/17/2019. Filed Date: 10/1/19. Accession Number: 20191001–5233. Comments Due: 5 p.m. ET 10/22/19. Docket Numbers: ER20–15–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Amended ISA SA No. 5227; Queue No. AB2–158 to be effective 10/8/2018. Filed Date: 10/1/19. Accession Number: 20191001–5263. Comments Due: 5 p.m. ET 10/22/19. Take notice that the Commission received the following electric securities filings: Docket Numbers: ES19–70–000. Applicants: West Penn Power Company. Description: Application under Section 204 of the Federal Power Act for Authorization to Issue Securities of West Penn Power Company. Filed Date: 9/27/19. Accession Number: 20190927–5194. Comments Due: 5 p.m. ET 10/18/19. Docket Numbers: ES19–71–000. Applicants: Basin Electric Power Cooperative, Inc. Description: Application under Section 204 of the Federal Power Act for Authorization to Issue Securities, et al. of Basin Electric Power Cooperative. Filed Date: 9/30/19. Accession Number: 20190930–5200. Comments Due: 5 p.m. ET 10/21/19. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. VerDate Sep<11>2014 18:29 Oct 04, 2019 Jkt 250001 eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: October 1, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–21795 Filed 10–4–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. PF19–5–000] Notice of Intent To Prepare an Environmental Assessment Statement for the Sempra PALNG Holdings, LLC Planned Port Arthur LNG Expansion Project, and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Port Arthur LNG Expansion Project (Project) involving construction and operation of facilities by Sempra PALNG Holdings, LLC (Sempra) in Jefferson County, Texas. The Commission will use this EA in its decision-making process to determine whether the project is in the public interest. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies about issues regarding the project. The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from its action whenever it considers the issuance of an authorization. NEPA also requires the Commission to discover concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of issues to address in the EA. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC on or before 5:00 p.m. Eastern Time on November 12, 2019. PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 You can make a difference by submitting your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Commission staff will consider all filed comments during the preparation of the EA. If you sent comments on this project to the Commission before the opening of this docket on June 14, 2019, you will need to file those comments in Docket No. PF19–5–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this planned project and encourage them to comment on their areas of concern. A fact sheet prepared by the FERC entitled An Interstate Natural Gas Facility On My Land? What Do I Need To Know? is available for viewing on the FERC website (www.ferc.gov) at https://www.ferc.gov/resources/guides/ gas/gas.pdf. This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. Public Participation The Commission offers a free service called eSubscription which makes it easy to stay informed of all issuances and submittals regarding the dockets/ projects to which you subscribe. These instant email notifications are the fastest way to receive notification and provide a link to the document files which can reduce the amount of time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/ esubscription.asp. For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208–3676 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature, which is on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. Using eComment is an easy method for submitting brief, text-only comments on a project; E:\FR\FM\07OCN1.SGM 07OCN1 Federal Register / Vol. 84, No. 194 / Monday, October 7, 2019 / Notices (2) You can file your comments electronically by using the eFiling feature, which is also on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on eRegister. You will be asked to select the type of filing you are making; a comment on a particular project is considered a Comment on a Filing; or (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (PF19–5–000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426 Summary of the Planned Project Sempra plans to construct and operate additional liquefaction capacity at the site of the recently approved Port Arthur Liquefaction Project near Port Arthur, Texas. The planned expansion would add two liquefaction trains, increasing liquefied natural gas production capacity from 13.5 million metric tons per annum (MTPA) to approximately 27.0 MTPA. The general location of the project facilities is shown in appendix 1.1 Land Requirements for Construction Construction and operation of the planned project would be wholly within property already certificated for the Port Arthur Liquefaction Project. No additional land would be required. The Project facilities, once constructed, would occupy approximately 60 acres. The EA Process The EA will discuss impacts that could occur as a result of the construction and operation of the planned project under these general headings: • Geology and soils; • water resources and wetlands; • vegetation and wildlife; • threatened and endangered species; • cultural resources; • socioeconomics; • land use; • air quality and noise; 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of the appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called eLibrary or from the Commission’s Public Reference Room, 888 First Street NE, Washington, DC 20426, or call (202) 502– 8371. For instructions on connecting to eLibrary, refer to the last page of this notice. VerDate Sep<11>2014 18:29 Oct 04, 2019 Jkt 250001 • public safety; and • cumulative impacts Commission staff will also evaluate possible alternatives to the planned project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. Although no formal application has been filed, Commission staff have already initiated a NEPA review under the Commission’s pre-filing process. The purpose of the pre-filing process is to encourage early involvement of interested stakeholders and to identify and resolve issues before the Commission receives an application. As part of the pre-filing review, Commission staff will contact federal and state agencies to discuss their involvement in the scoping process and the preparation of the EA. The EA will present Commission staffs’ independent analysis of the issues. The EA will be available in electronic format in the public record through eLibrary 2 and the Commission’s website (https:// www.ferc.gov/industries/gas/enviro/ eis.asp). If eSubscribed, you will receive instant email notification when the EA is issued. The EA may be issued for an allotted public comment period. Commission staff will consider all comments on the EA before making recommendations to the Commission. To ensure Commission staff have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2. With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues related to this project to formally cooperate in the preparation of the EA.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultation Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic 2 For instructions on connecting to eLibrary, refer to the last page of this notice. 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 53433 Preservation Office, and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.4 The EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Environmental Mailing List The environmental mailing list includes: Federal, state, and local government representatives and agencies; elected officials; and other interested parties. This list also includes all affected landowners (as defined in the Commission’s regulations) who own homes within certain distances of aboveground facilities as well as anyone who submits comments on the project. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the planned project. If the Commission issues the EA for an allotted public comment period, a Notice of Availability of the EA will be sent to the environmental mailing list and will provide instructions to access the electronic document on the FERC’s website (www.ferc.gov). If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please return the attached ‘‘Mailing List Update Form’’ (appendix 2). Becoming an Intervenor Once Sempra files its application with the Commission, you may want to become an intervenor which is an official party to the Commission’s proceeding. Only intervenors have the right to seek rehearing of the Commission’s decision and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene pursuant to Rule 214 of the Commission’s Rules of Practice and Procedures (18 CFR 385.214). Motions to intervene are more fully described at https://www.ferc.gov/resources/guides/ how-to/intervene.asp. Please note that the Commission will not accept requests 4 The Advisory Council on Historic Preservation regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. E:\FR\FM\07OCN1.SGM 07OCN1 53434 Federal Register / Vol. 84, No. 194 / Monday, October 7, 2019 / Notices for intervenor status at this time. You must wait until the Commission receives a formal application for the project, after which the Commission will issue a public notice that establishes an intervention deadline. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on General Search and enter the docket number in the Docket Number field, excluding the last three digits (i.e., PF19–5). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. Public sessions or site visits will be posted on the Commission’s calendar located at www.ferc.gov/EventCalendar/ EventsList.aspx along with other related information. Dated: October 1, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–21793 Filed 10–4–19; 8:45 am] BILLING CODE 6717–01–P ENVIRONMENTAL PROTECTION AGENCY [EPA–HQ–OECA–2012–0676; FRL–10000– 55–OMS] Information Collection Request Submitted to OMB for Review and Approval; Comment Request; NESHAP for Phosphoric Acid Manufacturing and Phosphate Fertilizers Production (Renewal) Environmental Protection Agency (EPA). ACTION: Notice. AGENCY: The Environmental Protection Agency (EPA) has submitted an information collection request (ICR), NESHAP for Phosphoric Acid Manufacturing and Phosphate Fertilizers Production (EPA ICR Number 1790.09, OMB Control Number 2060– 0361), to the Office of Management and Budget (OMB) for review and approval in accordance with the Paperwork Reduction Act. This is a proposed extension of the ICR, which is currently approved through January 31, 2020. SUMMARY: VerDate Sep<11>2014 18:29 Oct 04, 2019 Jkt 250001 Public comments were previously requested, via the Federal Register, on May 6, 2019, during a 60-day comment period. This notice allows for an additional 30 days for public comments. A fuller description of the ICR is given below, including its estimated burden and cost to the public. An agency may neither conduct nor sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number. DATES: Additional comments may be submitted on or before November 6, 2019. ADDRESSES: Submit your comments, referencing Docket ID Number EPA– HQ–OECA–2012–0676, to: (1) EPA online using www.regulations.gov (our preferred method), or by email to docket.oeca@epa.gov, or by mail to: EPA Docket Center, Environmental Protection Agency, Mail Code 28221T, 1200 Pennsylvania Ave. NW, Washington, DC 20460; and (2) OMB via email to oira_submission@omb.eop.gov. Address comments to OMB Desk Officer for EPA. EPA’s policy is that all comments received will be included in the public docket without change, including any personal information provided, unless the comment includes profanity, threats, information claimed to be Confidential Business Information (CBI), or other information whose disclosure is restricted by statute. FOR FURTHER INFORMATION CONTACT: Patrick Yellin, Monitoring, Assistance, and Media Programs Division, Office of Compliance, Mail Code 2227A, Environmental Protection Agency, 1200 Pennsylvania Ave. NW, Washington, DC 20460; telephone number: (202) 564– 2970; fax number: (202) 564–0050; email address: yellin.patrick@epa.gov. SUPPLEMENTARY INFORMATION: Supporting documents, which explain in detail the information that the EPA will be collecting, are available in the public docket for this ICR. The docket can be viewed online at www.regulations.gov, or in person at the EPA Docket Center, WJC West, Room 3334, 1301 Constitution Ave. NW, Washington, DC. The telephone number for the Docket Center is 202–566–1744. For additional information about EPA’s public docket, visit: https:// www.epa.gov/dockets. Abstract: The National Emission Standards for Hazardous Air Pollutants (NESHAP) for Phosphoric Acid Manufacturing and Phosphate Fertilizers Production (40 CFR part 63, subparts AA and BB) were proposed on December 27, 1996, promulgated on PO 00000 Frm 00037 Fmt 4703 Sfmt 4703 June 10, 1999, and amended on: June 12, 2002; April 20, 2006, August 19, 2015, and September 28, 2017. Owners and operators of affected facilities are required to comply with reporting and record-keeping requirements for the General Provisions (40 CFR part 63, subpart A), as well as for the specific requirements at 40 CFR part 63 subparts AA and BB. This includes submitting initial notifications, performance tests and periodic reports and results, and maintaining records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of an affected facility, or any period during which the monitoring system is inoperative. These reports are used by EPA to determine compliance with these standards. Form Numbers: None. Respondents/affected entities: Phosphoric acid and phosphate fertilizer production facilities. Respondent’s obligation to respond: Mandatory (40 CFR part 63). Estimated number of respondents: 13 (total). Frequency of response: Quarterly and semiannually. Total estimated burden: 2,200 hours (per year). Burden is defined at 5 CFR 1320.3(b). Total estimated cost: $441,000 (per year), which includes $186,000 in annualized capital/startup and/or operation & maintenance costs. Changes in the Estimates: There is no change in the labor hours in this ICR compared to the previous ICR. This is due to a zero-growth rate for the industry. Courtney Kerwin, Director, Regulatory Support Division. [FR Doc. 2019–21809 Filed 10–4–19; 8:45 am] BILLING CODE 6560–50–P ENVIRONMENTAL PROTECTION AGENCY [EPA–HQ–OPP–2018–0651; FRL–9999–71] Product Cancellation Order for Certain Pesticide Registrations Environmental Protection Agency (EPA). ACTION: Notice. AGENCY: This notice announces EPA’s order for the cancellations, voluntarily requested by the registrants and accepted by the Agency, of the products listed in Table 1 and Table 1A of Unit II., pursuant to the Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA). This cancellation order follows a March 5, 2019 Federal Register Notice SUMMARY: E:\FR\FM\07OCN1.SGM 07OCN1

Agencies

[Federal Register Volume 84, Number 194 (Monday, October 7, 2019)]
[Notices]
[Pages 53432-53434]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-21793]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. PF19-5-000]


Notice of Intent To Prepare an Environmental Assessment Statement 
for the Sempra PALNG Holdings, LLC Planned Port Arthur LNG Expansion 
Project, and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Port Arthur LNG Expansion 
Project (Project) involving construction and operation of facilities by 
Sempra PALNG Holdings, LLC (Sempra) in Jefferson County, Texas. The 
Commission will use this EA in its decision-making process to determine 
whether the project is in the public interest.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies about issues regarding the project. The National Environmental 
Policy Act (NEPA) requires the Commission to take into account the 
environmental impacts that could result from its action whenever it 
considers the issuance of an authorization. NEPA also requires the 
Commission to discover concerns the public may have about proposals. 
This process is referred to as ``scoping.'' The main goal of the 
scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of issues to address in the EA. To ensure that 
your comments are timely and properly recorded, please submit your 
comments so that the Commission receives them in Washington, DC on or 
before 5:00 p.m. Eastern Time on November 12, 2019.
    You can make a difference by submitting your specific comments or 
concerns about the project. Your comments should focus on the potential 
environmental effects, reasonable alternatives, and measures to avoid 
or lessen environmental impacts. Your input will help the Commission 
staff determine what issues they need to evaluate in the EA. Commission 
staff will consider all filed comments during the preparation of the 
EA.
    If you sent comments on this project to the Commission before the 
opening of this docket on June 14, 2019, you will need to file those 
comments in Docket No. PF19-5-000 to ensure they are considered as part 
of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this planned 
project and encourage them to comment on their areas of concern.
    A fact sheet prepared by the FERC entitled An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know? is available for 
viewing on the FERC website (www.ferc.gov) at https://www.ferc.gov/resources/guides/gas/gas.pdf. This fact sheet addresses a number of 
typically asked questions, including the use of eminent domain and how 
to participate in the Commission's proceedings.

Public Participation

    The Commission offers a free service called eSubscription which 
makes it easy to stay informed of all issuances and submittals 
regarding the dockets/projects to which you subscribe. These instant 
email notifications are the fastest way to receive notification and 
provide a link to the document files which can reduce the amount of 
time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/esubscription.asp.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature, which is on the Commission's website (www.ferc.gov) under the 
link to Documents and Filings. Using eComment is an easy method for 
submitting brief, text-only comments on a project;

[[Page 53433]]

    (2) You can file your comments electronically by using the eFiling 
feature, which is also on the Commission's website (www.ferc.gov) under 
the link to Documents and Filings. With eFiling, you can provide 
comments in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on eRegister. You will be asked to select the type of filing you are 
making; a comment on a particular project is considered a Comment on a 
Filing; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(PF19-5-000) with your submission: Kimberly D. Bose, Secretary, Federal 
Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, 
DC 20426

Summary of the Planned Project

    Sempra plans to construct and operate additional liquefaction 
capacity at the site of the recently approved Port Arthur Liquefaction 
Project near Port Arthur, Texas. The planned expansion would add two 
liquefaction trains, increasing liquefied natural gas production 
capacity from 13.5 million metric tons per annum (MTPA) to 
approximately 27.0 MTPA.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called eLibrary or from the Commission's 
Public Reference Room, 888 First Street NE, Washington, DC 20426, or 
call (202) 502-8371. For instructions on connecting to eLibrary, 
refer to the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction and operation of the planned project would be wholly 
within property already certificated for the Port Arthur Liquefaction 
Project. No additional land would be required. The Project facilities, 
once constructed, would occupy approximately 60 acres.

The EA Process

    The EA will discuss impacts that could occur as a result of the 
construction and operation of the planned project under these general 
headings:

     Geology and soils;
     water resources and wetlands;
     vegetation and wildlife;
     threatened and endangered species;
     cultural resources;
     socioeconomics;
     land use;
     air quality and noise;
     public safety; and
     cumulative impacts

    Commission staff will also evaluate possible alternatives to the 
planned project or portions of the project, and make recommendations on 
how to lessen or avoid impacts on the various resource areas.
    Although no formal application has been filed, Commission staff 
have already initiated a NEPA review under the Commission's pre-filing 
process. The purpose of the pre-filing process is to encourage early 
involvement of interested stakeholders and to identify and resolve 
issues before the Commission receives an application. As part of the 
pre-filing review, Commission staff will contact federal and state 
agencies to discuss their involvement in the scoping process and the 
preparation of the EA.
    The EA will present Commission staffs' independent analysis of the 
issues. The EA will be available in electronic format in the public 
record through eLibrary \2\ and the Commission's website (https://www.ferc.gov/industries/gas/enviro/eis.asp). If eSubscribed, you will 
receive instant email notification when the EA is issued. The EA may be 
issued for an allotted public comment period. Commission staff will 
consider all comments on the EA before making recommendations to the 
Commission. To ensure Commission staff have the opportunity to consider 
and address your comments, please carefully follow the instructions in 
the Public Participation section, beginning on page 2.
---------------------------------------------------------------------------

    \2\ For instructions on connecting to eLibrary, refer to the 
last page of this notice.
---------------------------------------------------------------------------

    With this notice, the Commission is asking agencies with 
jurisdiction by law and/or special expertise with respect to the 
environmental issues related to this project to formally cooperate in 
the preparation of the EA.\3\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultation Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, the Commission is using this notice to initiate 
consultation with the applicable State Historic Preservation Office, 
and to solicit their views and those of other government agencies, 
interested Indian tribes, and the public on the project's potential 
effects on historic properties.\4\ The EA for this project will 
document our findings on the impacts on historic properties and 
summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes: Federal, state, and local 
government representatives and agencies; elected officials; and other 
interested parties. This list also includes all affected landowners (as 
defined in the Commission's regulations) who own homes within certain 
distances of aboveground facilities as well as anyone who submits 
comments on the project. Commission staff will update the environmental 
mailing list as the analysis proceeds to ensure that Commission notices 
related to this environmental review are sent to all individuals, 
organizations, and government entities interested in and/or potentially 
affected by the planned project.
    If the Commission issues the EA for an allotted public comment 
period, a Notice of Availability of the EA will be sent to the 
environmental mailing list and will provide instructions to access the 
electronic document on the FERC's website (www.ferc.gov). If you need 
to make changes to your name/address, or if you would like to remove 
your name from the mailing list, please return the attached ``Mailing 
List Update Form'' (appendix 2).

Becoming an Intervenor

    Once Sempra files its application with the Commission, you may want 
to become an intervenor which is an official party to the Commission's 
proceeding. Only intervenors have the right to seek rehearing of the 
Commission's decision and be heard by the courts if they choose to 
appeal the Commission's final ruling. An intervenor formally 
participates in the proceeding by filing a request to intervene 
pursuant to Rule 214 of the Commission's Rules of Practice and 
Procedures (18 CFR 385.214). Motions to intervene are more fully 
described at https://www.ferc.gov/resources/guides/how-to/intervene.asp. 
Please note that the Commission will not accept requests

[[Page 53434]]

for intervenor status at this time. You must wait until the Commission 
receives a formal application for the project, after which the 
Commission will issue a public notice that establishes an intervention 
deadline.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on General Search and enter the docket number in 
the Docket Number field, excluding the last three digits (i.e., PF19-
5). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of all formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    Public sessions or site visits will be posted on the Commission's 
calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along 
with other related information.

    Dated: October 1, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-21793 Filed 10-4-19; 8:45 am]
BILLING CODE 6717-01-P