Double E Pipeline, LLC; Notice of Schedule for Environmental Review of the Double E Project, 53140 [2019-21634]
Download as PDF
53140
Federal Register / Vol. 84, No. 193 / Friday, October 4, 2019 / Notices
Dated: September 30, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–21674 Filed 10–3–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–495–000]
Double E Pipeline, LLC; Notice of
Schedule for Environmental Review of
the Double E Project
khammond on DSKJM1Z7X2PROD with NOTICES
On July 31, 2019, Double E Pipeline,
LLC (Double E) filed an application in
Docket No. CP19–495–000 requesting a
Certificate of Public Convenience and
Necessity pursuant to section 7(c) of the
Natural Gas Act to construct and operate
certain natural gas pipeline facilities.
The proposed project, known as the
Double E Pipeline Project (Project),
involves the construction and operation
of approximately 132.9 combined miles
of varying diameter natural gas pipeline
connecting the Delaware Basin
production areas in New Mexico and
Texas to the Waha Hub. The Project
would provide up to 1,350,000
dekatherms per day of firm capacity to
delivery points near the Waha Hub in
Reeves and Pecos Counties, Texas.
On August 14, 2019, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
Issuance of EA—March 24, 2020
90-day Federal Authorization Decision
Deadline—June 22, 2020
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
As part of the Project, Double E would
construct and operate:
• 33.3 miles of new 30-inch-diameter
trunkline T100 from Summit
Midstream’s existing Lane Processing
Plant located in Eddy County, New
VerDate Sep<11>2014
16:49 Oct 03, 2019
Jkt 250001
Mexico, to a new Double E Poker Lake
Meter Station in Eddy County, New
Mexico.
• 81.9 miles of new 42-inch-diameter
trunkline T200 from the proposed Poker
Lake Meter Station through Loving,
Ward, and Reeves Counties, Texas to a
terminus point at Double E’s proposed
Waha Receiver and Separation Site at
the Waha Hub in Reeves County.
• Approximately 1.4 miles of new 42inch-diameter pipeline T300 from the
proposed Waha Receiver site to the final
delivery location in Pecos County,
Texas.
• Approximately 16.3 miles of new
30-inch-diameter pipeline L100 from
three existing Gas Processing Plants in
Loving, New Mexico to the proposed
T100 trunkline in Eddy County, New
Mexico.
Background
On December 11, 2018, the
Commission issued a Notice of Intent to
Prepare an Environmental Assessment
for the Proposed Double E Pipeline
Project and Request for Comments on
Environmental Issues (NOI). The NOI
was issued during the pre-filing review
of the Project in Docket No. PF18–6–000
and sent to affected landowners; federal,
state, and local government agencies;
elected officials; Native American tribes;
other interested parties; and local
libraries and newspapers. Comments
were received from the New Mexico
Department of Game and Fish, the Hopi
Tribe, Choctaw Nation of Oklahoma,
Alabama-Coushatta Tribe of Texas, and
the New Mexico Department of
Transportation. All substantive
comments received will be addressed in
the EA.
The Bureau of Land Management will
be a cooperating agency in the
preparation of the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
Number’’ excluding the last three digits
(i.e., CP19–495), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: September 30, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–21634 Filed 10–3–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14998–000]
Premium Energy Holdings, LLC; Notice
of Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On June 18, 2019, Premium Energy
Holdings, LLC, filed an application for
a preliminary permit, pursuant to
section 4(f) of the Federal Power Act,
proposing to study the feasibility of the
Pyramid Lake Pumped Storage Project
(Pyramid Lake Project or project) to be
located on Pyramid Lake and Truckee
River, near the community of Nixon,
Washoe County, Nevada. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would be a
closed-loop pumped storage
hydropower facility. The applicant
proposes three alternative upper
reservoirs: San Emidio Reservoir,
Tohakum Peak Reservoir, or Lake Range
Reservoir. The existing Pyramid Lake
would be the lower reservoir for each
alternative.
Upper Reservoir Alternative 1: San
Emidio Reservoir
The San Emidio alternative consists
of: (1) A 180-acre upper reservoir having
a total storage capacity of 21,550 acrefeet at a normal maximum operating
elevation of 6,700 feet mean sea level
(msl); (2) a 315-foot-high, 2,385-footlong roller compacted concrete upper
E:\FR\FM\04OCN1.SGM
04OCN1
Agencies
[Federal Register Volume 84, Number 193 (Friday, October 4, 2019)]
[Notices]
[Page 53140]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-21634]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP19-495-000]
Double E Pipeline, LLC; Notice of Schedule for Environmental
Review of the Double E Project
On July 31, 2019, Double E Pipeline, LLC (Double E) filed an
application in Docket No. CP19-495-000 requesting a Certificate of
Public Convenience and Necessity pursuant to section 7(c) of the
Natural Gas Act to construct and operate certain natural gas pipeline
facilities. The proposed project, known as the Double E Pipeline
Project (Project), involves the construction and operation of
approximately 132.9 combined miles of varying diameter natural gas
pipeline connecting the Delaware Basin production areas in New Mexico
and Texas to the Waha Hub. The Project would provide up to 1,350,000
dekatherms per day of firm capacity to delivery points near the Waha
Hub in Reeves and Pecos Counties, Texas.
On August 14, 2019, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
Environmental Assessment (EA) for the Project. This instant notice
identifies the FERC staff's planned schedule for the completion of the
EA for the Project.
Schedule for Environmental Review
Issuance of EA--March 24, 2020
90-day Federal Authorization Decision Deadline--June 22, 2020
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
As part of the Project, Double E would construct and operate:
33.3 miles of new 30-inch-diameter trunkline T100 from
Summit Midstream's existing Lane Processing Plant located in Eddy
County, New Mexico, to a new Double E Poker Lake Meter Station in Eddy
County, New Mexico.
81.9 miles of new 42-inch-diameter trunkline T200 from the
proposed Poker Lake Meter Station through Loving, Ward, and Reeves
Counties, Texas to a terminus point at Double E's proposed Waha
Receiver and Separation Site at the Waha Hub in Reeves County.
Approximately 1.4 miles of new 42-inch-diameter pipeline
T300 from the proposed Waha Receiver site to the final delivery
location in Pecos County, Texas.
Approximately 16.3 miles of new 30-inch-diameter pipeline
L100 from three existing Gas Processing Plants in Loving, New Mexico to
the proposed T100 trunkline in Eddy County, New Mexico.
Background
On December 11, 2018, the Commission issued a Notice of Intent to
Prepare an Environmental Assessment for the Proposed Double E Pipeline
Project and Request for Comments on Environmental Issues (NOI). The NOI
was issued during the pre-filing review of the Project in Docket No.
PF18-6-000 and sent to affected landowners; federal, state, and local
government agencies; elected officials; Native American tribes; other
interested parties; and local libraries and newspapers. Comments were
received from the New Mexico Department of Game and Fish, the Hopi
Tribe, Choctaw Nation of Oklahoma, Alabama-Coushatta Tribe of Texas,
and the New Mexico Department of Transportation. All substantive
comments received will be addressed in the EA.
The Bureau of Land Management will be a cooperating agency in the
preparation of the EA.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP19-495), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC
website also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rule makings.
Dated: September 30, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-21634 Filed 10-3-19; 8:45 am]
BILLING CODE 6717-01-P