Sam Rayburn Dam Rate Schedule, 51551-51553 [2019-21041]
Download as PDF
Federal Register / Vol. 84, No. 189 / Monday, September 30, 2019 / Notices
1.2. Transmission and Related Ancillary
Services
Rate Schedule SRD–15, Wholesale Rates
for Hydro Power and Energy
Transmission service for the delivery
of Excess Energy shall be the sole
responsibility of such customer
purchasing Excess Energy.
The Sam Rayburn Dam rate schedule
(SRD–15) was placed into effect on an
interim basis by the Deputy Secretary
and was confirmed and approved on a
final basis by the Federal Energy
Regulatory Commission (FERC) on June
30, 2016, in Docket No. EF16–2–000
(155 FERC ¶ 62,254) for the period
January 1, 2016 through September 30,
2019. The 2019 Sam Rayburn Dam
power repayment studies (PRSs)
indicated the need for a 1.7 percent
revenue increase to continue to satisfy
cost recovery criteria. It is
Southwestern’s established practice for
the Administrator to defer, on a case by
case basis, revenue adjustments for an
isolated project if such adjustments are
within plus or minus five percent of the
revenue estimated from the current rate
schedule. The Administrator
determined it to be prudent to defer the
increase and allow the current rate
schedule, which is set to expire
September 30, 2019, to remain in effect.
The deferral of a revenue adjustment
provides for rate stability and savings on
the administrative cost of
implementation, and recognizes that the
revenue sufficiency will be re-examined
in the following year’s PRSs. Therefore,
the Administrator proposes the two-year
extension of the Sam Rayburn Dam rate
schedule for the period October 1, 2019
through September 30, 2021.
The Administrator has followed part
903, subpart A of Title 10 of the Code
of Federal Regulations, ‘‘Procedures for
Public Participation in Power and
Transmission Rate Adjustments and
Extensions’’ for the proposed extension
to the rate schedule. The public was
advised by notice published in the
Federal Register (84 FR 29200 (June 21,
2019)) of the proposed extension of the
rate schedules and of the opportunity to
provide written comments for a period
of 30 days ending July 22, 2019. No
comments were received.
Information regarding the extension of
this rate schedule, including the rate
schedule and other supporting material,
is available for public review in the
offices of Southwestern Power
Administration, Williams Tower I, One
West Third Street, Tulsa, Oklahoma
74103. I have reviewed the
Southwestern proposal and I approve
Rate Order No. SWPA–75.
1.3. Excess Energy Charge
$0.0094 per kilowatthour of Excess
Energy delivered.
[FR Doc. 2019–21040 Filed 9–27–19; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Southwestern Power Administration
Sam Rayburn Dam Rate Schedule
Southwestern Power
Administration, DOE.
ACTION: Notice of extension of Sam
Rayburn Dam rate schedule.
AGENCY:
The Assistant Secretary for
Electricity has approved and placed into
effect on an interim basis Rate Order No.
SWPA–75, which extends the following
existing Sam Rayburn Dam rate
schedule for the Southwestern Power
Administration: Rate Schedule SRD–15,
Wholesale Rates for Hydro Power and
Energy. This is an interim rate action
effective October 1, 2019, extending for
a period of two years through September
30, 2021.
DATES: The effective period for the rate
schedule specified in Rate Order No.
SWPA–75 is October 1, 2019 through
September 30, 2021.
FOR FURTHER INFORMATION CONTACT: Ms.
Fritha Ohlson, Director, Division of
Resources and Rates, Office of Corporate
Operations, Southwestern Power
Administration, U.S. Department of
Energy, One West Third Street, Tulsa,
Oklahoma 74103, (918) 595–6684,
fritha.ohlson@swpa.gov, or facsimile
transmission (918) 595–6684.
SUPPLEMENTARY INFORMATION: Pursuant
to Delegation Order Nos. 00–037.00B,
effective November 19, 2016, and 00–
002.00Q, effective November 1, 2018,
and Redelegation Order No. 00–
002.10D, effective June 4, 2019, and
pursuant to the implementation
authorities in 10 CFR 903.22(h), 10 CFR
903.23(a)(3), and 10 CFR 903.23(b), as
amended (84 FR 5347 (Feb. 21, 2019)),
Rate Order No. SWPA–75 is approved
and placed into effect on an interim
basis for the period October 1, 2019
through September 30, 2021, for the
following Southwestern Power
Administration (Southwestern) Sam
Rayburn Dam rate schedule:
khammond on DSKJM1Z7X2PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
19:16 Sep 27, 2019
Jkt 247001
PO 00000
51551
Dated: September 22, 2019.
Bruce J. Walker,
Assistant Secretary for Electricity.
UNITED STATES OF AMERICA
DEPARTMENT OF ENERGY
ASSISTANT SECRETARY
In the matter of: Southwestern Power
Administration, Sam Rayburn Dam Rate
Schedule
Rate Order
No. SWPA–75
ORDER APPROVING EXTENSION OF
RATE SCHEDULE ON AN INTERIM
BASIS
( September 22, 2019 )
Pursuant to Sections 302(a) and
301(b) of the Department of Energy
Organization Act, Public Law 95–91, the
functions of the Secretary of the Interior
and the Federal Power Commission
under Section 5 of the Flood Control
Act of 1944, 16 U.S.C. 825s, relating to
the Southwestern Power Administration
(Southwestern), were transferred to and
vested in the Secretary of Energy. By
Delegation Order No. 00-037.00B, the
Secretary of Energy delegated to the
Administrator of Southwestern
(Administrator) the authority to develop
power and transmission rates, and
delegated to the Federal Energy
Regulatory Commission (FERC) the
authority to confirm and approve on a
final basis or to disapprove rates
developed by the Administrator under
the delegation. By Delegation Order No.
00-002.00Q, the Secretary of Energy
delegated to the Under Secretary (of
Energy) the authority to confirm,
approve, and place into effect on an
interim basis rates developed by the
Administrator under delegation. By
Redelegation Order No. 00-002.10D, the
Under Secretary (of Energy) redelegated
to the Assistant Secretary for Electricity
(Assistant Secretary) the authority to
confirm, approve, and place into effect
such rates on an interim basis. Pursuant
to that delegated authority, the Assistant
Secretary has issued this interim rate
order.
BACKGROUND
The following rate schedule for Sam
Rayburn Dam was confirmed and
approved on a final basis by FERC on
June 30, 2016 in Docket No. EF16–2-000
(155 FERC ¶ 62,254) for the period
January 1, 2016 through September 30,
2019.
Rate Schedule SRD-15, Wholesale Rates
for Hydro Power and Energy
DISCUSSION
The existing Sam Rayburn Dam rate
schedule is based on the 2015 power
Frm 00044
Fmt 4703
Sfmt 4703
E:\FR\FM\30SEN1.SGM
30SEN1
51552
Federal Register / Vol. 84, No. 189 / Monday, September 30, 2019 / Notices
repayment studies (PRSs). PRSs have
been completed on the Sam Rayburn
Dam isolated project each year since
approval of the existing rate schedule.
The estimated revised annual revenue
identified by the subsequent PRSs since
the 2015 PRSs has indicated the need
for minimal rate increases. Since the
revenue changes reflected by the
subsequent PRSs were all within the
plus or minus five percent isolated
project rate adjustment threshold
practice established by the
Administrator on September 8, 2003,
these rate adjustments were deferred in
the best interest of the government.
However, the existing rate schedule is
set to expire on September 30, 2019.
Consequently, Southwestern proposed
to extend the existing rate schedule for
a two-year period ending September 30,
2021, on an interim basis under the
implementation authorities noted in 10
CFR 903.22(h) and 10 CFR 903.23(a)(3).
Southwestern followed Part 903 of
Title 10 of the Code of Federal
Regulations, ‘‘Procedures for Public
Participation in Power and
Transmission Rate Adjustments and
Extensions’’ for the proposed extension
of the rate schedule. An opportunity for
customers and other interested members
of the public to review and comment on
the proposed extension of the rate
schedule was announced by notice
published in the Federal Register on
June 21, 2019 (84 FR 29200), with
written comments due by July 22, 2019.
COMMENTS AND RESPONSES
Southwestern received no comments
regarding the extension of the rate
schedule.
AVAILABILITY OF INFORMATION
Information regarding the extension of
the rate schedule is available for public
review in the offices of Southwestern
Power Administration, Williams Tower
I, One West Third Street, Tulsa,
Oklahoma 74103.
khammond on DSKJM1Z7X2PROD with NOTICES
ADMINISTRATION’S
CERTIFICATION
The 2015 Sam Rayburn Dam PRSs
indicated that the current rate schedule
will repay all costs, including
amortization of the power investment
consistent with the provisions of
Department of Energy Order No. RA
6120.2. The 2019 Sam Rayburn Dam
PRSs indicated the need for an annual
revenue increase of 1.7 percent.
However, the 2019 rate adjustment falls
within Southwestern’s established plus
or minus five percent isolated project
rate adjustment threshold practice and
was deferred.
VerDate Sep<11>2014
19:16 Sep 27, 2019
Jkt 247001
Southwestern’s 2020 PRSs will
determine the appropriate level of
revenues needed for the next rate
period. In accordance with Delegation
Order No. 00–037.00B, effective
November 19, 2016, and Section 5 of the
Flood Control Act of 1944, the
Administrator has determined that the
existing rate schedule is the lowest
possible rate consistent with sound
business principles, and the extension is
consistent with applicable law.
ENVIRONMENT
The Southwestern NEPA Compliance
Officer determined that this class of
actions is categorically excluded from
the requirements of preparing either an
Environmental Impact Statement or an
Environmental Assessment. No
additional evaluation of the
environmental impact of the extension
of the existing rate schedule was
conducted, since no change in
anticipated revenues has been made to
the currently-approved rate schedule.
ADMINISTRATIVE PROCEDURES
Under the Administrative Procedure
Act (5 U.S.C. 553(d)), publication or
service of a substantive rule must be
made not less than 30 days before its
effective date, except (1) a substantive
rule that grants or recognizes an
exemption or relieves a restriction; (2)
interpretative rules and statements of
policy; or (3) as otherwise provided by
the agency for good cause found and
published with the rule. The Assistant
Secretary finds good cause to waive the
30-day delay in the effective date of this
action as unnecessary for the following
reasons: 1) this is an extension of rates
previously approved by FERC, pursuant
to 10 CFR 903.23(a); 2) there are no
substantive changes, as the existing rate
schedule and anticipated revenues
remain the same; and 3) the
Administrator provided notice and
opportunity for public comment more
than 30 days prior to the effective date
of the rate extension and received no
comments.
ORDER
In view of the foregoing, and pursuant
to the authority redelegated to me by the
Under Secretary (of Energy), I hereby
extend on an interim basis, for the
period of two years, effective October 1,
2019 through September 30, 2021, the
current Sam Rayburn Dam rate
schedule:
Rate Schedule SRD-15, Wholesale Rates
for Hydro Power and Energy
Dated: September 22, 2019
Bruce J. Walker
Assistant Secretary for Electricity
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
UNITED STATES DEPARTMENT OF
ENERGY
SOUTHWESTERN POWER
ADMINISTRATION
RATE SCHEDULE SRD–151 **
WHOLESALE RATES FOR HYDRO
POWER AND ENERGY
SOLD TO SAM RAYBURN DAM
ELECTRIC COOPERATIVE, INC.
(CONTRACT NO. DE–PM75–
92SW00215)
Effective:
During the period January 1, 2016,
through September 30, 2021 **, in
accordance with Federal Energy
Regulatory Commission (FERC) order
issued in Docket No. EF16–2–000 (June
30, 2016) and extension approved by the
Assistant Secretary in Rate Order No.
75.
Applicable:
To the power and energy purchased
by Sam Rayburn Dam Electric
Cooperative, Inc. (SRDEC) from the
Southwestern Power Administration
(Southwestern) under the terms and
conditions of the Power Sales Contract
dated October 7, 1992, as amended, for
the sale of all Hydro Power and Energy
generated at the Sam Rayburn Dam and
Reservoir.
Character and Conditions of Service:
Three-phase, alternating current,
delivered at approximately 60 Hertz, at
the nominal voltage, at the point of
delivery, and in such quantities as are
specified by contract.
1. Wholesale Rates, Terms, and
Conditions for Hydro Power and Energy
1.1. This rate shall be applicable
regardless of the quantity of Hydro
Power and Energy available or
delivered to SRDEC; provided,
however, that if an Uncontrollable
Force prevents utilization of both of
the project’s power generating units
for an entire billing period, and if
during such billing period water
releases were being made which
otherwise would have been used to
generate Hydro Power and Energy,
then Southwestern shall, upon
request by SRDEC, suspend billing
for subsequent billing periods, until
such time as at least one of the
project’s generating units is again
available.
1.2. The term ‘‘Uncontrollable Force,’’
as used herein, shall mean any force
which is not within the control of
1 Supersedes Rate Schedule SRD–13
** Extended through September 30, 2021, by
approval of Rate Order No. SWPA-75 by the
Assistant Secretary for Electricity.
E:\FR\FM\30SEN1.SGM
30SEN1
Federal Register / Vol. 84, No. 189 / Monday, September 30, 2019 / Notices
the party affected, including, but
not limited to, failure of water
supply, failure of facilities, flood,
earthquake, storm, lightning, fire,
epidemic, riot, civil disturbance,
labor disturbance, sabotage, war,
acts of war, terrorist acts, or
restraint by court of general
jurisdiction, which by exercise of
due diligence and foresight such
party could not reasonably have
been expected to avoid.
1.3. Hydro Power Rates, Terms, and
Conditions
1.3.1. Monthly Charge for the Period of
January 1, 2016 through September
30, 2021
$380,316 per month ($4,563,792 per
year) for Sam Rayburn Dam Hydro
Power and Energy purchased by SRDEC
from January 1, 2016, through
September 30, 2021.
[FR Doc. 2019–21041 Filed 9–27–19; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Southwestern Power Administration
Robert D. Willis Hydropower Project
Rate Schedule
Southwestern Power
Administration, DOE.
ACTION: Notice of extension of Robert D.
Willis Hydropower Project rate
schedule.
AGENCY:
The Assistant Secretary for
Electricity has approved and placed into
effect on an interim basis Rate Order No.
SWPA–76, which extends the following
existing Robert D. Willis Hydropower
Project rate schedule for the
Southwestern Power Administration:
Rate Schedule RDW–15, Wholesale
Rates for Hydro Power and Energy. This
is an interim rate action effective
October 1, 2019, extending for a period
of two years through September 30,
2021.
SUMMARY:
The effective period for the rate
schedule specified in Rate Order No.
SWPA–76 is October 1, 2019, through
September 30, 2021.
FOR FURTHER INFORMATION CONTACT: Ms.
Fritha Ohlson, Director, Division of
Resources and Rates, Office of Corporate
Operations, Southwestern Power
Administration, U.S. Department of
Energy, One West Third Street, Tulsa,
Oklahoma 74103, (918) 595–6684,
fritha.ohlson@swpa.gov, or facsimile
transmission (918) 595–6684.
SUPPLEMENTARY INFORMATION: Pursuant
to Delegation Order Nos. 00–037.00B,
effective November 19, 2016, and 00–
khammond on DSKJM1Z7X2PROD with NOTICES
DATES:
VerDate Sep<11>2014
19:16 Sep 27, 2019
Jkt 247001
002.00Q, effective November 1, 2018,
and Redelegation Order No. 00–
002.10D, effective June 4, 2019, and
pursuant to the implementation
authorities in 10 CFR 903.22(h), 10 CFR
903.23(a)(3), and 10 CFR 903.23(b), as
amended (84 FR 5347 (Feb. 21, 2019)),
Rate Order No. SWPA–76 is approved
and placed into effect on an interim
basis for the period October 1, 2019
through September 30, 2021, for the
following Southwestern Power
Administration (Southwestern) Robert
D. Willis Hydropower Project (Robert D.
Willis) rate schedule:
Rate Schedule RDW–15, Wholesale
Rates for Hydro Power and Energy
The Robert D. Willis rate schedule
(RDW–15) was placed into effect on an
interim basis by the Deputy Secretary
and was confirmed and approved on a
final basis by the Federal Energy
Regulatory Commission (FERC) on June
15, 2016, in Docket No. EF16–1–000
(155 FERC ¶ 62,213) for the period
January 1, 2016 through September 30,
2019. The 2019 Robert D. Willis power
repayment studies (PRSs) indicated the
need for a 3.7 percent revenue increase
to continue to satisfy cost recovery
criteria. It is Southwestern’s established
practice for the Administrator to defer,
on a case by case basis, revenue
adjustments for an isolated project if
such adjustments are within plus or
minus five percent of the revenue
estimated from the current rate
schedule. The Administrator
determined it to be prudent to defer the
increase and allow the current rate
schedule, which is set to expire
September 30, 2019, to remain in effect.
The deferral of a revenue adjustment
provides for rate stability and savings on
the administrative cost of
implementation, and recognizes that the
revenue sufficiency will be re-examined
in the following year’s PRSs. Therefore,
the Administrator proposes the two-year
extension of the Robert D. Willis rate
schedule for the period October 1, 2019
through September 30, 2021.
The Administrator has followed part
903, subpart A of Title 10 of the Code
of Federal Regulations, ‘‘Procedures for
Public Participation in Power and
Transmission Rate Adjustments and
Extensions’’ for the proposed extension
to the rate schedule. The public was
advised by notice published in the
Federal Register (84 FR 29200 (June 21,
2019)) of the proposed extension of the
rate schedules and of the opportunity to
provide written comments for a period
of 30 days ending July 22, 2019. No
comments were received.
Information regarding the extension of
this rate schedule, including the rate
PO 00000
Frm 00046
Fmt 4703
Sfmt 4703
51553
schedule and other supporting material,
is available for public review in the
offices of Southwestern Power
Administration, Williams Tower I, One
West Third Street, Tulsa, Oklahoma
74103. I have reviewed the
Southwestern proposal and I approve
Rate Order No. SWPA–76.
Dated: September 22, 2019.
Bruce J. Walker,
Assistant Secretary for Electricity.
UNITED STATES OF AMERICA
DEPARTMENT OF ENERGY
ASSISTANT SECRETARY
In the matter of: Southwestern Power
Administration, Robert D. Willis Hydropower
Project Rate Schedule
Rate Order
No. SWPA–76
ORDER APPROVING EXTENSION OF
RATE SCHEDULE ON AN INTERIM
BASIS
(September 22, 2019)
Pursuant to Sections 302(a) and
301(b) of the Department of Energy
Organization Act, Public Law 95–91, the
functions of the Secretary of the Interior
and the Federal Power Commission
under Section 5 of the Flood Control
Act of 1944, 16 U.S.C. 825s, relating to
the Southwestern Power Administration
(Southwestern), were transferred to and
vested in the Secretary of Energy. By
Delegation Order No. 00–037.00B, the
Secretary of Energy delegated to the
Administrator of Southwestern
(Administrator) the authority to develop
power and transmission rates, and
delegated to the Federal Energy
Regulatory Commission (FERC) the
authority to confirm and approve on a
final basis or to disapprove rates
developed by the Administrator under
the delegation. By Delegation Order No.
00-002.00Q, the Secretary of Energy
delegated to the Under Secretary (of
Energy) the authority to confirm,
approve, and place into effect on an
interim basis rates developed by the
Administrator under delegation. By
Redelegation Order No. 00-002.10D, the
Under Secretary (of Energy) redelegated
to the Assistant Secretary for Electricity
(Assistant Secretary) the authority to
confirm, approve, and place into effect
such rates on an interim basis. Pursuant
to that delegated authority, the Assistant
Secretary has issued this interim rate
order.
BACKGROUND
The following rate schedule for the
Robert D. Willis Hydropower Project
(Robert D. Willis) was confirmed and
approved on a final basis by FERC on
June 15, 2016, in Docket No. EF16–1–
E:\FR\FM\30SEN1.SGM
30SEN1
Agencies
[Federal Register Volume 84, Number 189 (Monday, September 30, 2019)]
[Notices]
[Pages 51551-51553]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-21041]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Southwestern Power Administration
Sam Rayburn Dam Rate Schedule
AGENCY: Southwestern Power Administration, DOE.
ACTION: Notice of extension of Sam Rayburn Dam rate schedule.
-----------------------------------------------------------------------
SUMMARY: The Assistant Secretary for Electricity has approved and
placed into effect on an interim basis Rate Order No. SWPA-75, which
extends the following existing Sam Rayburn Dam rate schedule for the
Southwestern Power Administration: Rate Schedule SRD-15, Wholesale
Rates for Hydro Power and Energy. This is an interim rate action
effective October 1, 2019, extending for a period of two years through
September 30, 2021.
DATES: The effective period for the rate schedule specified in Rate
Order No. SWPA-75 is October 1, 2019 through September 30, 2021.
FOR FURTHER INFORMATION CONTACT: Ms. Fritha Ohlson, Director, Division
of Resources and Rates, Office of Corporate Operations, Southwestern
Power Administration, U.S. Department of Energy, One West Third Street,
Tulsa, Oklahoma 74103, (918) 595-6684, [email protected], or
facsimile transmission (918) 595-6684.
SUPPLEMENTARY INFORMATION: Pursuant to Delegation Order Nos. 00-
037.00B, effective November 19, 2016, and 00-002.00Q, effective
November 1, 2018, and Redelegation Order No. 00-002.10D, effective June
4, 2019, and pursuant to the implementation authorities in 10 CFR
903.22(h), 10 CFR 903.23(a)(3), and 10 CFR 903.23(b), as amended (84 FR
5347 (Feb. 21, 2019)), Rate Order No. SWPA-75 is approved and placed
into effect on an interim basis for the period October 1, 2019 through
September 30, 2021, for the following Southwestern Power Administration
(Southwestern) Sam Rayburn Dam rate schedule:
Rate Schedule SRD-15, Wholesale Rates for Hydro Power and Energy
The Sam Rayburn Dam rate schedule (SRD-15) was placed into effect
on an interim basis by the Deputy Secretary and was confirmed and
approved on a final basis by the Federal Energy Regulatory Commission
(FERC) on June 30, 2016, in Docket No. EF16-2-000 (155 FERC ] 62,254)
for the period January 1, 2016 through September 30, 2019. The 2019 Sam
Rayburn Dam power repayment studies (PRSs) indicated the need for a 1.7
percent revenue increase to continue to satisfy cost recovery criteria.
It is Southwestern's established practice for the Administrator to
defer, on a case by case basis, revenue adjustments for an isolated
project if such adjustments are within plus or minus five percent of
the revenue estimated from the current rate schedule. The Administrator
determined it to be prudent to defer the increase and allow the current
rate schedule, which is set to expire September 30, 2019, to remain in
effect.
The deferral of a revenue adjustment provides for rate stability
and savings on the administrative cost of implementation, and
recognizes that the revenue sufficiency will be re-examined in the
following year's PRSs. Therefore, the Administrator proposes the two-
year extension of the Sam Rayburn Dam rate schedule for the period
October 1, 2019 through September 30, 2021.
The Administrator has followed part 903, subpart A of Title 10 of
the Code of Federal Regulations, ``Procedures for Public Participation
in Power and Transmission Rate Adjustments and Extensions'' for the
proposed extension to the rate schedule. The public was advised by
notice published in the Federal Register (84 FR 29200 (June 21, 2019))
of the proposed extension of the rate schedules and of the opportunity
to provide written comments for a period of 30 days ending July 22,
2019. No comments were received.
Information regarding the extension of this rate schedule,
including the rate schedule and other supporting material, is available
for public review in the offices of Southwestern Power Administration,
Williams Tower I, One West Third Street, Tulsa, Oklahoma 74103. I have
reviewed the Southwestern proposal and I approve Rate Order No. SWPA-
75.
Dated: September 22, 2019.
Bruce J. Walker,
Assistant Secretary for Electricity.
UNITED STATES OF AMERICA DEPARTMENT OF ENERGY ASSISTANT SECRETARY
In the matter of: Southwestern Power Administration, Sam Rayburn
Dam Rate Schedule
Rate Order
No. SWPA-75
ORDER APPROVING EXTENSION OF RATE SCHEDULE ON AN INTERIM BASIS
( September 22, 2019 )
Pursuant to Sections 302(a) and 301(b) of the Department of Energy
Organization Act, Public Law 95-91, the functions of the Secretary of
the Interior and the Federal Power Commission under Section 5 of the
Flood Control Act of 1944, 16 U.S.C. 825s, relating to the Southwestern
Power Administration (Southwestern), were transferred to and vested in
the Secretary of Energy. By Delegation Order No. 00-037.00B, the
Secretary of Energy delegated to the Administrator of Southwestern
(Administrator) the authority to develop power and transmission rates,
and delegated to the Federal Energy Regulatory Commission (FERC) the
authority to confirm and approve on a final basis or to disapprove
rates developed by the Administrator under the delegation. By
Delegation Order No. 00-002.00Q, the Secretary of Energy delegated to
the Under Secretary (of Energy) the authority to confirm, approve, and
place into effect on an interim basis rates developed by the
Administrator under delegation. By Redelegation Order No. 00-002.10D,
the Under Secretary (of Energy) redelegated to the Assistant Secretary
for Electricity (Assistant Secretary) the authority to confirm,
approve, and place into effect such rates on an interim basis. Pursuant
to that delegated authority, the Assistant Secretary has issued this
interim rate order.
BACKGROUND
The following rate schedule for Sam Rayburn Dam was confirmed and
approved on a final basis by FERC on June 30, 2016 in Docket No. EF16-
2-000 (155 FERC ] 62,254) for the period January 1, 2016 through
September 30, 2019.
Rate Schedule SRD-15, Wholesale Rates for Hydro Power and Energy
DISCUSSION
The existing Sam Rayburn Dam rate schedule is based on the 2015
power
[[Page 51552]]
repayment studies (PRSs). PRSs have been completed on the Sam Rayburn
Dam isolated project each year since approval of the existing rate
schedule. The estimated revised annual revenue identified by the
subsequent PRSs since the 2015 PRSs has indicated the need for minimal
rate increases. Since the revenue changes reflected by the subsequent
PRSs were all within the plus or minus five percent isolated project
rate adjustment threshold practice established by the Administrator on
September 8, 2003, these rate adjustments were deferred in the best
interest of the government.
However, the existing rate schedule is set to expire on September
30, 2019. Consequently, Southwestern proposed to extend the existing
rate schedule for a two-year period ending September 30, 2021, on an
interim basis under the implementation authorities noted in 10 CFR
903.22(h) and 10 CFR 903.23(a)(3).
Southwestern followed Part 903 of Title 10 of the Code of Federal
Regulations, ``Procedures for Public Participation in Power and
Transmission Rate Adjustments and Extensions'' for the proposed
extension of the rate schedule. An opportunity for customers and other
interested members of the public to review and comment on the proposed
extension of the rate schedule was announced by notice published in the
Federal Register on June 21, 2019 (84 FR 29200), with written comments
due by July 22, 2019.
COMMENTS AND RESPONSES
Southwestern received no comments regarding the extension of the
rate schedule.
AVAILABILITY OF INFORMATION
Information regarding the extension of the rate schedule is
available for public review in the offices of Southwestern Power
Administration, Williams Tower I, One West Third Street, Tulsa,
Oklahoma 74103.
ADMINISTRATION'S CERTIFICATION
The 2015 Sam Rayburn Dam PRSs indicated that the current rate
schedule will repay all costs, including amortization of the power
investment consistent with the provisions of Department of Energy Order
No. RA 6120.2. The 2019 Sam Rayburn Dam PRSs indicated the need for an
annual revenue increase of 1.7 percent. However, the 2019 rate
adjustment falls within Southwestern's established plus or minus five
percent isolated project rate adjustment threshold practice and was
deferred.
Southwestern's 2020 PRSs will determine the appropriate level of
revenues needed for the next rate period. In accordance with Delegation
Order No. 00-037.00B, effective November 19, 2016, and Section 5 of the
Flood Control Act of 1944, the Administrator has determined that the
existing rate schedule is the lowest possible rate consistent with
sound business principles, and the extension is consistent with
applicable law.
ENVIRONMENT
The Southwestern NEPA Compliance Officer determined that this class
of actions is categorically excluded from the requirements of preparing
either an Environmental Impact Statement or an Environmental
Assessment. No additional evaluation of the environmental impact of the
extension of the existing rate schedule was conducted, since no change
in anticipated revenues has been made to the currently-approved rate
schedule.
ADMINISTRATIVE PROCEDURES
Under the Administrative Procedure Act (5 U.S.C. 553(d)),
publication or service of a substantive rule must be made not less than
30 days before its effective date, except (1) a substantive rule that
grants or recognizes an exemption or relieves a restriction; (2)
interpretative rules and statements of policy; or (3) as otherwise
provided by the agency for good cause found and published with the
rule. The Assistant Secretary finds good cause to waive the 30-day
delay in the effective date of this action as unnecessary for the
following reasons: 1) this is an extension of rates previously approved
by FERC, pursuant to 10 CFR 903.23(a); 2) there are no substantive
changes, as the existing rate schedule and anticipated revenues remain
the same; and 3) the Administrator provided notice and opportunity for
public comment more than 30 days prior to the effective date of the
rate extension and received no comments.
ORDER
In view of the foregoing, and pursuant to the authority redelegated
to me by the Under Secretary (of Energy), I hereby extend on an interim
basis, for the period of two years, effective October 1, 2019 through
September 30, 2021, the current Sam Rayburn Dam rate schedule:
Rate Schedule SRD-15, Wholesale Rates for Hydro Power and Energy
Dated: September 22, 2019
Bruce J. Walker
Assistant Secretary for Electricity
UNITED STATES DEPARTMENT OF ENERGY
SOUTHWESTERN POWER ADMINISTRATION
RATE SCHEDULE SRD-15\1\ **
\1 \ Supersedes Rate Schedule SRD-13
** Extended through September 30, 2021, by approval of Rate
Order No. SWPA-75 by the Assistant Secretary for Electricity.
---------------------------------------------------------------------------
WHOLESALE RATES FOR HYDRO POWER AND ENERGY
SOLD TO SAM RAYBURN DAM ELECTRIC COOPERATIVE, INC.
(CONTRACT NO. DE-PM75-92SW00215)
Effective:
During the period January 1, 2016, through September 30, 2021 **,
in accordance with Federal Energy Regulatory Commission (FERC) order
issued in Docket No. EF16-2-000 (June 30, 2016) and extension approved
by the Assistant Secretary in Rate Order No. 75.
Applicable:
To the power and energy purchased by Sam Rayburn Dam Electric
Cooperative, Inc. (SRDEC) from the Southwestern Power Administration
(Southwestern) under the terms and conditions of the Power Sales
Contract dated October 7, 1992, as amended, for the sale of all Hydro
Power and Energy generated at the Sam Rayburn Dam and Reservoir.
Character and Conditions of Service:
Three-phase, alternating current, delivered at approximately 60
Hertz, at the nominal voltage, at the point of delivery, and in such
quantities as are specified by contract.
1. Wholesale Rates, Terms, and Conditions for Hydro Power and Energy
1.1. This rate shall be applicable regardless of the quantity of Hydro
Power and Energy available or delivered to SRDEC; provided, however,
that if an Uncontrollable Force prevents utilization of both of the
project's power generating units for an entire billing period, and if
during such billing period water releases were being made which
otherwise would have been used to generate Hydro Power and Energy, then
Southwestern shall, upon request by SRDEC, suspend billing for
subsequent billing periods, until such time as at least one of the
project's generating units is again available.
1.2. The term ``Uncontrollable Force,'' as used herein, shall mean any
force which is not within the control of
[[Page 51553]]
the party affected, including, but not limited to, failure of water
supply, failure of facilities, flood, earthquake, storm, lightning,
fire, epidemic, riot, civil disturbance, labor disturbance, sabotage,
war, acts of war, terrorist acts, or restraint by court of general
jurisdiction, which by exercise of due diligence and foresight such
party could not reasonably have been expected to avoid.
1.3. Hydro Power Rates, Terms, and Conditions
1.3.1. Monthly Charge for the Period of January 1, 2016 through
September 30, 2021
$380,316 per month ($4,563,792 per year) for Sam Rayburn Dam Hydro
Power and Energy purchased by SRDEC from January 1, 2016, through
September 30, 2021.
[FR Doc. 2019-21041 Filed 9-27-19; 8:45 am]