Verdant Power, LLC; Notice of Request To Waive Requirement To File Draft License Application, 48607 [2019-19968]
Download as PDF
Federal Register / Vol. 84, No. 179 / Monday, September 16, 2019 / Notices
access the document. For assistance,
contact FERC Online Support.
Dated: September 10, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–19970 Filed 9–13–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12611–009]
jspears on DSK3GMQ082PROD with NOTICES
Verdant Power, LLC; Notice of Request
To Waive Requirement To File Draft
License Application
a. Type of Filing: Request to Waive
Pre-Filing Requirements.
b. Project No.: 12611–009.
c. Date Filed: August 30, 2019.
d. Applicant: Verdant Power, LLC.
e. Name of Project: Roosevelt Island
Tidal Energy Project.
f. Location: On the East River in New
York County, New York.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Mr. Ronald F.
Smith, President and Chief Operating
Officer, Verdant Power, LLC, P.O. Box
282, Roosevelt Island, New York, New
York 10044. Phone: (703) 328–6841.
i. FERC Contact: Andy Bernick, (202)
502–8660, andrew.bernick@ferc.gov.
j. Verdant requests a waiver of the
Commission’s pre-filing regulations
under section 16.8(c) with respect to the
requirement to submit a draft license
application for the Roosevelt Island
Tidal Energy Project. Verdant states that
the project has a long history of
consultation and that it proposes no
substantive changes to the currently
licensed pilot project. Further, Verdant
indicates that it held two joint agency
meetings (on January 8, 2019 and May
16, 2019), the second of which was held
for federal agencies that were unable to
attend the January meeting due to the
funding lapse at certain federal agencies
between December 22, 2018, and
January 25, 2019. Verdant explains that
the second joint agency meeting and the
additional time needed to respond to
study requests has reduced the amount
of time available for submitting and
effectively reviewing responses to a
draft license application, prior to the
filing of the final license application by
December 31, 2019. Therefore,
Commission staff is soliciting comments
on Verdant’s request to waive the
requirement to file a draft license
application for the Roosevelt Island
Tidal Energy Project, pursuant to
VerDate Sep<11>2014
18:14 Sep 13, 2019
Jkt 247001
sections 16.8(c)(4) and 16.8(c)(6) of the
Commission’s regulations.
k. The deadline for filing comments is
15 days from the issuance date of this
notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and protests, comments, and
final terms and conditions,
recommendations, and prescriptions
using the Commission’s eFiling system
at https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–12611–009.
l. A copy of the request is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
three digits in the docket number field
to access the document. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676, or for TTY,
contact (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Dated: September 10, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–19968 Filed 9–13–19; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
48607
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14979–000]
Lock+TM Hydro Friends Fund XXVII,
LLC; Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On March 6, 2019, Lock+TM Hydro
Friends Fund XXVII, LLC, filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act, proposing to study the
feasibility of the Cowanesque Dam
Hydropower Project to be located at the
U.S. Army Corps of Engineers’
Cowanesque Dam on the Cowanesque
River in Tioga County, Pennsylvania.
The sole purpose of a preliminary
permit, if issued, is to grant the permit
holder priority to file a license
application during the permit term. A
preliminary permit does not authorize
the permit holder to perform any landdisturbing activities or otherwise enter
upon lands or waters owned by others
without the owners’ express permission.
The proposed project would consist of
the following: (1) A new 30-foot-long,
30-foot-wide, 160-foot-high Large Frame
Module; (2) two turbine-generator units
with a total rated capacity of 0.85
megawatt; (3) a new 4-foot-long, 4-footwide, 3-foot-high pad-mounted
transformer; (4) a new 200-foot-long, 13kilovolt transmission line connecting
the new transformer to an existing
distribution line; and (5) appurtenant
facilities. The proposed project would
have an annual generation of 3,700
megawatt-hours.
Applicant Contact: Wayne Krouse,
Lock+TM Hydro Friends Fund XXVII,
LLC, P.O. Box 43796, Birmingham, AL
35243; phone: 877–556–6566 ext. 709.
FERC Contact: Woohee Choi; phone:
(202) 502–6336.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
E:\FR\FM\16SEN1.SGM
16SEN1
Agencies
[Federal Register Volume 84, Number 179 (Monday, September 16, 2019)]
[Notices]
[Page 48607]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-19968]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12611-009]
Verdant Power, LLC; Notice of Request To Waive Requirement To
File Draft License Application
a. Type of Filing: Request to Waive Pre-Filing Requirements.
b. Project No.: 12611-009.
c. Date Filed: August 30, 2019.
d. Applicant: Verdant Power, LLC.
e. Name of Project: Roosevelt Island Tidal Energy Project.
f. Location: On the East River in New York County, New York.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Mr. Ronald F. Smith, President and Chief
Operating Officer, Verdant Power, LLC, P.O. Box 282, Roosevelt Island,
New York, New York 10044. Phone: (703) 328-6841.
i. FERC Contact: Andy Bernick, (202) 502-8660,
[email protected].
j. Verdant requests a waiver of the Commission's pre-filing
regulations under section 16.8(c) with respect to the requirement to
submit a draft license application for the Roosevelt Island Tidal
Energy Project. Verdant states that the project has a long history of
consultation and that it proposes no substantive changes to the
currently licensed pilot project. Further, Verdant indicates that it
held two joint agency meetings (on January 8, 2019 and May 16, 2019),
the second of which was held for federal agencies that were unable to
attend the January meeting due to the funding lapse at certain federal
agencies between December 22, 2018, and January 25, 2019. Verdant
explains that the second joint agency meeting and the additional time
needed to respond to study requests has reduced the amount of time
available for submitting and effectively reviewing responses to a draft
license application, prior to the filing of the final license
application by December 31, 2019. Therefore, Commission staff is
soliciting comments on Verdant's request to waive the requirement to
file a draft license application for the Roosevelt Island Tidal Energy
Project, pursuant to sections 16.8(c)(4) and 16.8(c)(6) of the
Commission's regulations.
k. The deadline for filing comments is 15 days from the issuance
date of this notice.
The Commission strongly encourages electronic filing. Please file
motions to intervene and protests, comments, and final terms and
conditions, recommendations, and prescriptions using the Commission's
eFiling system at https://www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments up to 6,000 characters, without
prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact
information at the end of your comments. For assistance, please contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC 20426. The first page of any filing
should include docket number P-12611-009.
l. A copy of the request is available for review at the Commission
in the Public Reference Room or may be viewed on the Commission's
website at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the three digits in the docket number field to
access the document. For assistance, please contact FERC Online Support
at [email protected] or toll free at (866) 208-3676, or for
TTY, contact (202) 502-8659. A copy is also available for inspection
and reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
Dated: September 10, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-19968 Filed 9-13-19; 8:45 am]
BILLING CODE 6717-01-P