Combined Notice of Filings #1, 46511-46512 [2019-19036]

Download as PDF Federal Register / Vol. 84, No. 171 / Wednesday, September 4, 2019 / Notices Size Number of entities Average hours per entity Total burden hours 7 (1) (2) (1) * (2) Large .......................................................................................................................... Medium ...................................................................................................................... Small .......................................................................................................................... The total estimated annual cost burden to respondents is $212,482,720, which includes $127,433,401 for nonlabor record storage costs and $85,049,319 for employee costs. The average cost per respondent is $417,451, which includes $250,360 for non-labor record storage costs and $167,091 for employee costs. All of these cost figures are based on staff analysis of the data we received in 2019. Comments: Comments are invited on: (1) Whether the collection of information is necessary for the proper performance of the functions of the Commission, including whether the information will have practical utility; (2) the accuracy of the agency’s estimate of the burden and cost of the collection of information, including the validity of the methodology and assumptions used; (3) ways to enhance the quality, utility and clarity of the information collection; and (4) ways to minimize the burden of the collection of information on those who are to respond, including the use of automated collection techniques or other forms of information technology. Dated: August 28, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–19043 Filed 9–3–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission jbell on DSK3GLQ082PROD with NOTICES Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC19–113–000. Applicants: Golden State Water Company. Description: Supplement to July 12, 2019 Application for Authorization Under Section 203 of the Federal Power Act [Revised Exhibit N] of Golden State Water Company. Filed Date: 8/28/19. Accession Number: 20190828–5072. 7 Due to rounding during the analysis and calculations, the total in this column does not sum to the exact figure reported shown in the summary burden table. VerDate Sep<11>2014 19:08 Sep 03, 2019 Jkt 247001 174 166 169 Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: EC19–129–000. Applicants: Ambit Northeast, LLC. Description: Application for Authorization Under Section 203 of the Federal Power Act, et al. of Ambit Northeast, LLC. Filed Date: 8/28/19. Accession Number: 20190828–5139. Comments Due: 5 p.m. ET 9/18/19. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER19–1762–001. Applicants: Electric Energy, Inc. Description: Compliance filing: Compliance to 2019 Att M and Att N to be effective 4/30/2019. Filed Date: 8/28/19. Accession Number: 20190828–5063. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2150–001. Applicants: Shawville Power, LLC. Description: Compliance filing: Shawville Power LLC Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5032. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2151–001. Applicants: New Castle Power, LLC. Description: Compliance filing: New Castle Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5033. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2152–001. Applicants: Brunot Island Power, LLC. Description: Compliance filing: Brunot Island Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5035. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2153–001. Applicants: Gilbert Power, LLC. Description: Compliance filing: Gilbert Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5036. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2154–001. Applicants: Sayreville Power, LLC. Description: Compliance filing: Sayreville Power Compliance Filing to be effective 9/1/2019. PO 00000 Frm 00010 Fmt 4703 Sfmt 4703 46511 11,475 2,371 1,571 1,996,658 393,619 265,572 Filed Date: 8/28/19. Accession Number: 20190828–5037. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2155–001. Applicants: Portland Power, LLC. Description: Compliance filing: Portland Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5038. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2156–001. Applicants: Warren Generation, LLC. Description: Compliance filing: Warren Generation Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5039. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2157–001. Applicants: Mountain Power, LLC. Description: Compliance filing: Mountain Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5040. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2158–001. Applicants: Orrtanna Power, LLC. Description: Compliance filing: Orrtanna Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5041. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2159–001. Applicants: Shawnee Power, LLC. Description: Compliance filing: Shawnee Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5042. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2160–001. Applicants: Titus Power, LLC. Description: Compliance filing: Titus Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5043. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2161–001. Applicants: Hamilton Power, LLC. Description: Compliance filing: Hamilton Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5047. E:\FR\FM\04SEN1.SGM 04SEN1 jbell on DSK3GLQ082PROD with NOTICES 46512 Federal Register / Vol. 84, No. 171 / Wednesday, September 4, 2019 / Notices Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2162–001. Applicants: Blossburg Power, LLC. Description: Compliance filing: Blossburg Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5052. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2163–001. Applicants: Hunterstown Power, LLC. Description: Compliance filing: Hunterstown Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5053. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2164–001. Applicants: Tolna Power, LLC. Description: Compliance filing: Tolna Power Compliance Filing to be effective 9/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5057. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2505–001. Applicants: Southern California Edison Company. Description: Tariff Amendment: Refile WDAT Energy Storage to be effective 10/30/2019. Filed Date: 8/28/19. Accession Number: 20190828–5130. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2687–000. Applicants: California Independent System Operator Corporation. Description: § 205(d) Rate Filing: 2019–08–27 Transferred Frequency Response Agreement with Tacoma Power to be effective 12/1/2019. Filed Date: 8/27/19. Accession Number: 20190827–5101. Comments Due: 5 p.m. ET 9/17/19. Docket Numbers: ER19–2688–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original WMPA SA No. 5459; Queue No. AE1–041 to be effective 7/29/2019. Filed Date: 8/27/19. Accession Number: 20190827–5106. Comments Due: 5 p.m. ET 9/17/19. Docket Numbers: ER19–2689–000. Applicants: California Independent System Operator Corporation. Description: § 205(d) Rate Filing: 2019–08–27 Transferred Frequency Response Agreement with PUD No. 2 Grant Co. to be effective 12/1/2019. Filed Date: 8/27/19. Accession Number: 20190827–5117. Comments Due: 5 p.m. ET 9/17/19. Docket Numbers: ER19–2690–000. Applicants: California Independent System Operator Corporation. Description: § 205(d) Rate Filing: 2019–08–27 Transferred Frequency VerDate Sep<11>2014 19:08 Sep 03, 2019 Jkt 247001 Response Agreement with PUD No. 1 Chelan Co. to be effective 12/1/2019. Filed Date: 8/27/19. Accession Number: 20190827–5119. Comments Due: 5 p.m. ET 9/17/19. Docket Numbers: ER19–2691–000. Applicants: Southern California Edison Company. Description: § 205(d) Rate Filing: GIA and Distribution Service Agmt SCEBESS–021 Project to be effective 8/ 29/2019. Filed Date: 8/28/19. Accession Number: 20190828–5001. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2692–000. Applicants: California Independent System Operator Corporation. Description: § 205(d) Rate Filing: 2019–08–28 Transferred Frequency Response Agreement with Bonneville Power Admin to be effective 12/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5098. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2693–000. Applicants: California Independent System Operator Corporation. Description: § 205(d) Rate Filing: 2019–08–28 Transferred Frequency Response Agreement with City of Seattle to be effective 12/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5103. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2694–000. Applicants: California Independent System Operator Corporation. Description: § 205(d) Rate Filing: 2019–08–28 Transferred Frequency Response Agreement with Powerex to be effective 12/1/2019. Filed Date: 8/28/19. Accession Number: 20190828–5105. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2695–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: Revisions to Clarify Trading Hub Modification Process Language to be effective 10/28/2019. Filed Date: 8/28/19. Accession Number: 20190828–5108. Comments Due: 5 p.m. ET 9/18/19. Docket Numbers: ER19–2696–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Amendment to ISA, SA No. 5159 and ICSA, SA No. 5189; Queue No. AB2–040 (amend) to be effective 8/8/2018. Filed Date: 8/28/19. Accession Number: 20190828–5116. Comments Due: 5 p.m. ET 9/18/19. The filings are accessible in the Commission’s eLibrary system by PO 00000 Frm 00011 Fmt 4703 Sfmt 4703 clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: August 28, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–19036 Filed 9–3–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Docket No. CP19–488–000] Columbia Gulf Transmission, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Louisiana Xpress Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Session The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Louisiana Xpress Project involving construction and operation of facilities by Columbia Gulf Transmission, LLC (Columbia Gulf) in Evangeline, East Carroll, Catahoula, and Rapides Parishes, Louisiana. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies about issues regarding the project. The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from its action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires the Commission to E:\FR\FM\04SEN1.SGM 04SEN1

Agencies

[Federal Register Volume 84, Number 171 (Wednesday, September 4, 2019)]
[Notices]
[Pages 46511-46512]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-19036]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Combined Notice of Filings #1

    Take notice that the Commission received the following electric 
corporate filings:

    Docket Numbers: EC19-113-000.
    Applicants: Golden State Water Company.
    Description: Supplement to July 12, 2019 Application for 
Authorization Under Section 203 of the Federal Power Act [Revised 
Exhibit N] of Golden State Water Company.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5072.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: EC19-129-000.
    Applicants: Ambit Northeast, LLC.
    Description: Application for Authorization Under Section 203 of the 
Federal Power Act, et al. of Ambit Northeast, LLC.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5139.
    Comments Due: 5 p.m. ET 9/18/19.

    Take notice that the Commission received the following electric 
rate filings:

    Docket Numbers: ER19-1762-001.
    Applicants: Electric Energy, Inc.
    Description: Compliance filing: Compliance to 2019 Att M and Att N 
to be effective 4/30/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5063.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2150-001.
    Applicants: Shawville Power, LLC.
    Description: Compliance filing: Shawville Power LLC Compliance 
Filing to be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5032.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2151-001.
    Applicants: New Castle Power, LLC.
    Description: Compliance filing: New Castle Power Compliance Filing 
to be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5033.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2152-001.
    Applicants: Brunot Island Power, LLC.
    Description: Compliance filing: Brunot Island Power Compliance 
Filing to be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5035.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2153-001.
    Applicants: Gilbert Power, LLC.
    Description: Compliance filing: Gilbert Power Compliance Filing to 
be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5036.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2154-001.
    Applicants: Sayreville Power, LLC.
    Description: Compliance filing: Sayreville Power Compliance Filing 
to be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5037.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2155-001.
    Applicants: Portland Power, LLC.
    Description: Compliance filing: Portland Power Compliance Filing to 
be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5038.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2156-001.
    Applicants: Warren Generation, LLC.
    Description: Compliance filing: Warren Generation Compliance Filing 
to be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5039.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2157-001.
    Applicants: Mountain Power, LLC.
    Description: Compliance filing: Mountain Power Compliance Filing to 
be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5040.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2158-001.
    Applicants: Orrtanna Power, LLC.
    Description: Compliance filing: Orrtanna Power Compliance Filing to 
be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5041.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2159-001.
    Applicants: Shawnee Power, LLC.
    Description: Compliance filing: Shawnee Power Compliance Filing to 
be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5042.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2160-001.
    Applicants: Titus Power, LLC.
    Description: Compliance filing: Titus Power Compliance Filing to be 
effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5043.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2161-001.
    Applicants: Hamilton Power, LLC.
    Description: Compliance filing: Hamilton Power Compliance Filing to 
be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5047.

[[Page 46512]]

    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2162-001.
    Applicants: Blossburg Power, LLC.
    Description: Compliance filing: Blossburg Power Compliance Filing 
to be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5052.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2163-001.
    Applicants: Hunterstown Power, LLC.
    Description: Compliance filing: Hunterstown Power Compliance Filing 
to be effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5053.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2164-001.
    Applicants: Tolna Power, LLC.
    Description: Compliance filing: Tolna Power Compliance Filing to be 
effective 9/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5057.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2505-001.
    Applicants: Southern California Edison Company.
    Description: Tariff Amendment: Refile WDAT Energy Storage to be 
effective 10/30/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5130.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2687-000.
    Applicants: California Independent System Operator Corporation.
    Description: Sec.  205(d) Rate Filing: 2019-08-27 Transferred 
Frequency Response Agreement with Tacoma Power to be effective 12/1/
2019.
    Filed Date: 8/27/19.
    Accession Number: 20190827-5101.
    Comments Due: 5 p.m. ET 9/17/19.

    Docket Numbers: ER19-2688-000.
    Applicants: PJM Interconnection, L.L.C.
    Description: Sec.  205(d) Rate Filing: Original WMPA SA No. 5459; 
Queue No. AE1-041 to be effective 7/29/2019.
    Filed Date: 8/27/19.
    Accession Number: 20190827-5106.
    Comments Due: 5 p.m. ET 9/17/19.

    Docket Numbers: ER19-2689-000.
    Applicants: California Independent System Operator Corporation.
    Description: Sec.  205(d) Rate Filing: 2019-08-27 Transferred 
Frequency Response Agreement with PUD No. 2 Grant Co. to be effective 
12/1/2019.
    Filed Date: 8/27/19.
    Accession Number: 20190827-5117.
    Comments Due: 5 p.m. ET 9/17/19.

    Docket Numbers: ER19-2690-000.
    Applicants: California Independent System Operator Corporation.
    Description: Sec.  205(d) Rate Filing: 2019-08-27 Transferred 
Frequency Response Agreement with PUD No. 1 Chelan Co. to be effective 
12/1/2019.
    Filed Date: 8/27/19.
    Accession Number: 20190827-5119.
    Comments Due: 5 p.m. ET 9/17/19.

    Docket Numbers: ER19-2691-000.
    Applicants: Southern California Edison Company.
    Description: Sec.  205(d) Rate Filing: GIA and Distribution Service 
Agmt SCEBESS-021 Project to be effective 8/29/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5001.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2692-000.
    Applicants: California Independent System Operator Corporation.
    Description: Sec.  205(d) Rate Filing: 2019-08-28 Transferred 
Frequency Response Agreement with Bonneville Power Admin to be 
effective 12/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5098.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2693-000.
    Applicants: California Independent System Operator Corporation.
    Description: Sec.  205(d) Rate Filing: 2019-08-28 Transferred 
Frequency Response Agreement with City of Seattle to be effective 12/1/
2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5103.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2694-000.
    Applicants: California Independent System Operator Corporation.
    Description: Sec.  205(d) Rate Filing: 2019-08-28 Transferred 
Frequency Response Agreement with Powerex to be effective 12/1/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5105.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2695-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: Revisions to Clarify Trading 
Hub Modification Process Language to be effective 10/28/2019.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5108.
    Comments Due: 5 p.m. ET 9/18/19.

    Docket Numbers: ER19-2696-000.
    Applicants: PJM Interconnection, L.L.C.
    Description: Sec.  205(d) Rate Filing: Amendment to ISA, SA No. 
5159 and ICSA, SA No. 5189; Queue No. AB2-040 (amend) to be effective 
8/8/2018.
    Filed Date: 8/28/19.
    Accession Number: 20190828-5116.
    Comments Due: 5 p.m. ET 9/18/19.

    The filings are accessible in the Commission's eLibrary system by 
clicking on the links or querying the docket number.
    Any person desiring to intervene or protest in any of the above 
proceedings must file in accordance with Rules 211 and 214 of the 
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00 
p.m. Eastern time on the specified comment date. Protests may be 
considered, but intervention is necessary to become a party to the 
proceeding.
    eFiling is encouraged. More detailed information relating to filing 
requirements, interventions, protests, service, and qualifying 
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676 
(toll free). For TTY, call (202) 502-8659.

    Dated: August 28, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-19036 Filed 9-3-19; 8:45 am]
 BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.