Download as PDF jbell on DSK3GLQ082PROD with NOTICES 45142 Federal Register / Vol. 84, No. 167 / Wednesday, August 28, 2019 / Notices Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–10674–017. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application is not ready for environmental analysis at this time. l. Project Description: The Kimberly Project consists of: (1) A 161-foot-long, 43-foot-wide, 61-foot-high reinforced concrete and brick masonry powerhouse located at the south abutment of Cedars Dam and containing three turbinegenerator units each rated at 723 kilowatts for a total installed capacity of 2.170 megawatts; (2) a 2.4 kilovolts (kV) to 34.5 kV step-up transformer; and (3) appurtenant facilities. The project is directly connected to a 34.5 kV local distribution line which is not part of the project. The average annual generation was 12,324,827 kilowatt-hours for the period 2011 to 2017. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s website at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to address the document. For assistance, contact FERC Online Support. A copy is available for inspection and reproduction at the address in Item H above. n. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. o. Scoping Process. The Commission staff intends to prepare a single Environmental Assessment (EA) for the project in accordance with the National Environmental Policy Act. The EA will consider both site-specific and cumulative environmental impacts and reasonable alternatives to the proposed action. At this time, we do not anticipate holding on-site public or agency scoping meetings. Instead, we are soliciting your comments and suggestions on the preliminary list of issues and alternatives to be addressed in the EA, VerDate Sep<11>2014 20:14 Aug 27, 2019 Jkt 247001 as described in scoping document 1 (SD1), issued August 22, 2019. Copies of the SD1 outlining the subject areas to be addressed in the EA were distributed to the parties on the Commission’s mailing list and the applicant’s distribution list. Copies of SD1 may be viewed on the web at https://www.ferc.gov using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call 1–866–208–3676 or for TTY, (202) 502–8659. Dated: August 22, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–18532 Filed 8–27–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 10674–017] Kaukauna Utilities; Notice Soliciting Scoping Comments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New License. b. Project No.: P–10674–017. c. Date filed: February 14, 2019. d. Applicant: Kaukauna Utilities. e. Name of Project: Kimberly Hydroelectric Project (Kimberly Project). f. Location: The existing project is located at the U.S. Army Corps of Engineers’ (Corps) Cedars Dam on the Lower Fox River in the Village of Kimberly, Outagamie County, Wisconsin. The project does not occupy federal lands. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mike Pedersen, Manager of Generation and Operations, Kaukauna Utilities, 777 Island Street, P.O. Box 1777, Kaukauna, WI 54130– 7077, (902) 766–5721. i. FERC Contact: Colleen Corballis at (202) 502–8598; or Colleen.corballis@ ferc.gov. j. Deadline for filing scoping comments: September 21, 2019. The Commission strongly encourages electronic filing. Please file scoping comments using the Commission’s eFiling system at https://www.ferc.gov/ docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–10674–017. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application is not ready for environmental analysis at this time. l. Project Description: The Kimberly Project consists of: (1) A 161-foot-long, 43-foot-wide, 61-foot-high reinforced concrete and brick masonry powerhouse located at the south abutment of Cedars Dam and containing three turbinegenerator units each rated at 723 kilowatts for a total installed capacity of 2.170 megawatts; (2) a 2.4 kilovolts (kV) to 34.5 kV step-up transformer; and (3) appurtenant facilities. The project is directly connected to a 34.5 kV local distribution line which is not part of the project. The average annual generation was 12,324,827 kilowatt-hours for the period 2011 to 2017. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s website at https://www.ferc.gov using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to address the document. For assistance, contact FERC Online Support. A copy is available for inspection and reproduction at the address in Item H above. n. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. o. Scoping Process The Commission staff intends to prepare a single Environmental Assessment (EA) for the project in accordance with the National Environmental Policy Act. The EA will consider both site-specific and cumulative environmental impacts and E:\FR\FM\28AUN1.SGM 28AUN1 Federal Register / Vol. 84, No. 167 / Wednesday, August 28, 2019 / Notices reasonable alternatives to the proposed action. At this time, we do not anticipate holding on-site public or agency scoping meetings. Instead, we are soliciting your comments and suggestions on the preliminary list of issues and alternatives to be addressed in the EA, as described in scoping document 1 (SD1), issued August 22, 2019. Copies of the SD1 outlining the subject areas to be addressed in the EA were distributed to the parties on the Commission’s mailing list and the applicant’s distribution list. Copies of SD1 may be viewed on the web at https://www.ferc.gov using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call 1–866–208–3676 or for TTY, (202) 502–8659. Dated: August 22, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–18537 Filed 8–27–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission jbell on DSK3GLQ082PROD with NOTICES Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER19–2387–001. Applicants: New England Power Pool Participants Committee. Description: Tariff Amendment: Viridity Energy Termination Correction to be effective 9/10/2019. Filed Date: 7/12/19. Accession Number: 20190712–5148. Comments Due: 5 p.m. ET 8/29/19. Docket Numbers: ER19–2671–000. Applicants: SR Arlington II, LLC. Description: Baseline eTariff Filing: MBR Application to be effective 10/21/ 2019. Filed Date: 8/21/19. Accession Number: 20190821–5116. Comments Due: 5 p.m. ET 9/11/19. Docket Numbers: ER19–2672–000. Applicants: SR Arlington II MT, LLC. Description: Baseline eTariff Filing: MBR Application to be effective 10/21/ 2019. Filed Date: 8/21/19. Accession Number: 20190821–5127. Comments Due: 5 p.m. ET 9/11/19. Docket Numbers: ER19–2673–000. Applicants: NorthWestern Corporation. Description: Tariff Cancellation: Notice of Cancellation; SA 811, Fast VerDate Sep<11>2014 20:14 Aug 27, 2019 Jkt 247001 45143 Process Agreement with MDT (Russell St.) to be effective 8/22/2019. Filed Date: 8/21/19. Accession Number: 20190821–5130. Comments Due: 5 p.m. ET 9/11/19. DEPARTMENT OF ENERGY Docket Numbers: ER19–2674–000. Applicants: New Mexico PPA Corporation. Description: Baseline eTariff Filing: Application for Market-Based Rate Sales to be effective 10/22/2019. Filed Date: 8/22/19. Accession Number: 20190822–5078. Comments Due: 5 p.m. ET 9/12/19. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER19–1980–001. Applicants: Southwest Power Pool, Inc. Description: Tariff Amendment: 3555SO Haystack Wind Project GIAAmended Filing/Deficiency to be effective 5/10/2019. Filed Date: 8/21/19. Accession Number: 20190821–5061. Comments Due: 5 p.m. ET 9/11/19. Docket Numbers: ER19–2399–000. Applicants: Caden Energix Hickory LLC. Description: Supplement to July 15, 2019 Caden Energix Hickory LLC tariff filing. Filed Date: 8/21/19. Accession Number: 20190821–5092. Comments Due: 5 p.m. ET 9/11/19. Docket Numbers: ER19–2640–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 1910R15 Southwestern Public Service Company NITSA NOA Notice of Cancellation to be effective 6/1/2019. Filed Date: 8/20/19. Accession Number: 20190820–5172. Comments Due: 5 p.m. ET 9/10/19. Docket Numbers: ER19–2652–000. Applicants: Avista Corporation. Description: § 205(d) Rate Filing: Avista Corp Rate Schedule T1158 Northern Grid Funding Agreement to be effective 10/31/2019. Filed Date: 8/20/19. Accession Number: 20190820–5153. Comments Due: 5 p.m. ET 9/10/19. Docket Numbers: ER19–2653–000. Applicants: MATL LLP. Description: § 205(d) Rate Filing: NorthernGrid Funding Agreement Concurrence to be effective 10/31/2019. Filed Date: 8/20/19. Accession Number: 20190820–5156. Comments Due: 5 p.m. ET 9/10/19. Docket Numbers: ER19–2654–000. Applicants: Puget Sound Energy, Inc. Description: § 205(d) Rate Filing: Certificate of Concurrence to NorthernGrid Funding Agreement to be effective 10/31/2019. Filed Date: 8/20/19. Accession Number: 20190820–5163. Comments Due: 5 p.m. ET 9/10/19. Docket Numbers: ER19–2655–000. Applicants: Portland General Electric Company. Docket Numbers: ER19–2675–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 3517R1 Plum Creek Wind, LLC GIA to be effective 7/25/2019. Filed Date: 8/22/19. Accession Number: 20190822–5086. Comments Due: 5 p.m. ET 9/12/19. Docket Numbers: ER19–2676–000. Applicants: Southern California Edison Company. Description: § 205(d) Rate Filing: Correction to Appendix 2 Under WDAT Recollation Filing 1 to be effective 5/1/ 2019. Filed Date: 8/22/19. Accession Number: 20190822–5094. Comments Due: 5 p.m. ET 9/12/19. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: August 22, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–18510 Filed 8–27–19; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 Federal Energy Regulatory Commission Combined Notice of Filings #1 E:\FR\FM\28AUN1.SGM 28AUN1

Agencies

[Federal Register Volume 84, Number 167 (Wednesday, August 28, 2019)]
[Notices]
[Pages 45142-45143]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-18537]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 10674-017]


Kaukauna Utilities; Notice Soliciting Scoping Comments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.

    a. Type of Application: New License.
    b. Project No.: P-10674-017.
    c. Date filed: February 14, 2019.
    d. Applicant: Kaukauna Utilities.
    e. Name of Project: Kimberly Hydroelectric Project (Kimberly 
Project).
    f. Location: The existing project is located at the U.S. Army Corps 
of Engineers' (Corps) Cedars Dam on the Lower Fox River in the Village 
of Kimberly, Outagamie County, Wisconsin. The project does not occupy 
federal lands.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Mike Pedersen, Manager of Generation and 
Operations, Kaukauna Utilities, 777 Island Street, P.O. Box 1777, 
Kaukauna, WI 54130-7077, (902) 766-5721.
    i. FERC Contact: Colleen Corballis at (202) 502-8598; or 
[email protected].
    j. Deadline for filing scoping comments: September 21, 2019.
    The Commission strongly encourages electronic filing. Please file 
scoping comments using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-10674-017.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application is not ready for environmental analysis at this 
time.
    l. Project Description: The Kimberly Project consists of: (1) A 
161-foot-long, 43-foot-wide, 61-foot-high reinforced concrete and brick 
masonry powerhouse located at the south abutment of Cedars Dam and 
containing three turbine-generator units each rated at 723 kilowatts 
for a total installed capacity of 2.170 megawatts; (2) a 2.4 kilovolts 
(kV) to 34.5 kV step-up transformer; and (3) appurtenant facilities. 
The project is directly connected to a 34.5 kV local distribution line 
which is not part of the project. The average annual generation was 
12,324,827 kilowatt-hours for the period 2011 to 2017.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's website at https://www.ferc.gov using the eLibrary link. 
Enter the docket number excluding the last three digits in the docket 
number field to address the document. For assistance, contact FERC 
Online Support. A copy is available for inspection and reproduction at 
the address in Item H above.
    n. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    o. Scoping Process
    The Commission staff intends to prepare a single Environmental 
Assessment (EA) for the project in accordance with the National 
Environmental Policy Act. The EA will consider both site-specific and 
cumulative environmental impacts and

[[Page 45143]]

reasonable alternatives to the proposed action.
    At this time, we do not anticipate holding on-site public or agency 
scoping meetings. Instead, we are soliciting your comments and 
suggestions on the preliminary list of issues and alternatives to be 
addressed in the EA, as described in scoping document 1 (SD1), issued 
August 22, 2019.
    Copies of the SD1 outlining the subject areas to be addressed in 
the EA were distributed to the parties on the Commission's mailing list 
and the applicant's distribution list. Copies of SD1 may be viewed on 
the web at https://www.ferc.gov using the eLibrary link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document. For assistance, call 1-866-208-3676 or 
for TTY, (202) 502-8659.

    Dated: August 22, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-18537 Filed 8-27-19; 8:45 am]
BILLING CODE 6717-01-P