Combined Notice of Filings #1, 43801-43802 [2019-18122]
Download as PDF
Federal Register / Vol. 84, No. 163 / Thursday, August 22, 2019 / Notices
F. Bowe, Jr., King & Spalding, LLP, 1700
Pennsylvania Avenue NW, Suite 200,
Washington, DC 20006, by telephone at
(202) 626–9601, by fax at (202) 626–
3737, or by email at jbowe@kslaw.com.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the EA
for this proposal. The filing of the EA
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list and will be
notified of any meetings associated with
the Commission’s environmental review
process. Environmental commenters
will not be required to serve copies of
filed documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission and will not have the right
to seek court review of the
Commission’s final order.
VerDate Sep<11>2014
16:37 Aug 21, 2019
Jkt 247001
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 3 copies
of the protest or intervention to the
Federal Energy regulatory Commission,
888 First Street NE, Washington, DC
20426.
Dated: August 16, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–18124 Filed 8–21–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG19–166–000.
Applicants: Rosewater Wind Farm
LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Rosewater Wind
Farm LLC.
Filed Date: 8/16/19.
Accession Number: 20190816–5019.
Comments Due: 5 p.m. ET 9/6/19.
Docket Numbers: EG19–167–000.
Applicants: Kaheawa Wind Power,
LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Kaheawa Wind
Power, LLC.
Filed Date: 8/16/19.
Accession Number: 20190816–5065.
Comments Due: 5 p.m. ET 9/6/19.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER15–1883–006;
ER10–1836–016; ER10–1841–015;
ER10–1845–015; ER10–1846–011;
ER10–1849–017; ER10–1851–009;
ER10–1852–029; ER10–1855–011;
ER10–1857–010; ER10–1887–017;
ER10–1890–012; ER10–1897–015;
ER10–1899–011; ER10–1905–015;
ER10–1907–014; ER10–1918–015;
ER10–1920–019; ER10–1925–015;
ER10–1927–015; ER10–1928–019;
ER10–1930–009; ER10–1931–010;
ER10–1932–010; ER10–1935–010;
ER10–1950–015; ER10–1952–017;
ER10–1961–017; ER10–1962–012;
ER10–1964–015; ER10–2005–015;
ER10–2006–016; ER10–2551–012;
ER11–2160–012; ER11–26–015; ER11–
PO 00000
Frm 00015
Fmt 4703
Sfmt 4703
43801
2642–012; ER11–3635–012; ER12–1228–
019; ER12–2226–009; ER12–2227–017;
ER12–569–018; ER13–1991–011; ER13–
1992–011; ER13–2112–008; ER13–712–
019; ER13–752–010; ER15–1418–006;
ER15–1925–011; ER15–2101–006;
ER15–2477–006; ER15–2582–004;
ER15–2601–004; ER15–2676–010;
ER16–1672–008; ER16–2190–007;
ER16–2191–007; ER16–2275–007;
ER16–2276–007; ER16–2453–008;
ER16–632–004; ER16–90–006; ER16–
91–006; ER17–2152–004; ER17–2340–
003; ER18–1534–003; ER18–1771–005;
ER18–1863–002; ER18–1952–005;
ER18–1978–003; ER18–2118–003;
ER18–2246–004; ER18–882–003; ER19–
1003–002; ER19–1392–003; ER19–1393–
002; ER19–1394–002; ER19–987–002/
Applicants: Adelanto Solar, LLC,
Adelanto Solar II, LLC, Armadillo Flats
Wind Project, LLC, Ashtabula Wind,
LLC, Ashtabula Wind II, LLC, Ashtabula
Wind III, LLC, Baldwin Wind, LLC,
Blackwell Wind, LLC, Blythe Solar 110,
LLC, Blythe Solar II, LLC, Breckinridge
Wind Project, LLC, Brady
Interconnection, LLC, Brady Wind, LLC,
Brady Wind II, LLC, Butler Ridge Wind
Energy Center, LLC, Carousel Wind
Farm, LLC, Casa Mesa Wind, LLC, Cedar
Bluff Wind, LLC, Chaves County Solar,
LLC, Cimarron Wind Energy, LLC,
Coolidge Solar I, LLC, Cottonwood
Wind Project, LLC, Crystal Lake Wind
Energy I, LLC, Crystal Lake Wind
Energy I, LLC, Crystal Lake Wind III,
LLC, Day County Wind, LLC, Desert
Sunlight 250, LLC, Desert Sunlight 300,
LLC, East Hampton Energy Storage
Center, LLC, Elk City Renewables II,
LLC, Elk City Wind, LLC, Endeavor
Wind I, LLC, Endeavor Wind II, LLC,
Energy Storage Holdings, LLC, Ensign
Wind, LLC, ESI Vansycle Partners, L.P.,
Florida Power & Light Company, FPL
Energy Burleigh County Wind, LLC, FPL
Energy Cape, LLC, FPL Energy Cowboy
Wind, LLC, FPL Energy Green Power
Wind, LLC, FPL Energy Hancock
County Wind, LLC, FPL Energy Illinois
Wind, LLC, FPL Energy Montezuma
Wind, LLC, FPL Energy Mower County,
LLC, FPL Energy North Dakota Wind,
LLC, FPL Energy North Dakota Wind II,
LLC, FPL Energy Oklahoma Wind, LLC,
FPL Energy Oliver Wind I, LLC, FPL
Energy Oliver Wind II, LLC, FPL Energy
Sooner Wind, LLC, FPL Energy South
Dakota Wind, LLC, FPL Energy Stateline
II, Inc., FPL Energy Vansycle, L.L.C, FPL
Energy Wyman, LLC, FPL Energy
Wyman IV, LLC, Garden Wind, LLC,
Genesis Solar, LLC, Golden Hills
Interconnection, LLC, Golden Hills
North Wind, LLC, Golden Hills Wind,
LLC, Golden West Power Partners, LLC,
Gray County Wind Energy, LLC, Green
E:\FR\FM\22AUN1.SGM
22AUN1
43802
Federal Register / Vol. 84, No. 163 / Thursday, August 22, 2019 / Notices
Mountain Storage, LLC, Gulf Power
Company, LLC, Hatch Solar Energy
Center I, LLC, Hawkeye Power Partners,
LLC, Heartland Divide Wind Project,
LLC, High Lonesome Mesa Wind, LLC,
High Majestic Wind Energy Center, LLC,
High Majestic Wind II, LLC, High
Winds, LLC, Kingman Wind Energy I,
LLC, Kingman Wind Energy II, LLC,
Lake Benton Power Partners II, LLC,
Langdon Renewables, LLC, Limon
Wind, LLC
Description: Notice of Change in
Status of the NextEra MBR Sellers (Part
1).
Filed Date: 8/15/19.
Accession Number: 20190815–5219.
Comments Due: 5 p.m. ET 9/5/19.
Docket Numbers: ER19–2619–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2019–08–15_Revisions to Fast
Automatic Generation Control Signals to
be effective 10/15/2019.
Filed Date: 8/15/19.
Accession Number: 20190815–5182.
Comments Due: 5 p.m. ET 9/5/19.
Docket Numbers: ER19–2620–000.
Applicants: Idaho Power Company.
Description: Idaho Power Company
submits Average System Cost Filing for
Sales of Electric Power to the Bonneville
Power Administration, FY 2020–2021.
Filed Date: 8/15/19.
Accession Number: 20190815–5209.
Comments Due: 5 p.m. ET 9/5/19.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
85.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: August 16, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–18122 Filed 8–21–19; 8:45 am]
BILLING CODE 6717–01–P
VerDate Sep<11>2014
16:37 Aug 21, 2019
Jkt 247001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 516–503]
Dominion Energy South Carolina, Inc.;
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-project use
of project lands and waters.
b. Project No: 516–503.
c. Date Filed: May 24, 2019.
d. Applicant: Dominion Energy South
Carolina, Inc.
e. Name of Project: Saluda
Hydroelectric Project.
f. Location: The project is located on
the Lake Murray in Lexington County,
South Carolina.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Billy Chastain,
Manager, Lake Management Program,
Dominion Energy South Carolina, 6248
Bush River Road, Columbia, SC 29212,
(803) 217–7149.
i. FERC Contact: Mary Karwoski,
(678) 245–3027, mary.karwoski@
ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests:
August 19, 2019.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–516–503.
Comments emailed to Commission staff
are not considered part of the
Commission record.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
PO 00000
Frm 00016
Fmt 4703
Sfmt 4703
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Request: The
licensee seeks authorization to permit
the construction of non-project docks
for the temporary mooring of twenty
watercraft for lake access to a proposed
restaurant. The location of the
restaurant is 3348 U.S. Highway 378,
Leesville, South Carolina, 29070. The
proposed docks would consist of (2) ten
slip, 75-foot long by 100-foot wide
commercial docks, spaced 200 feet apart
along the shoreline. The permittee has
obtained necessary permits from the
U.S. Army Corps of Engineers and the
South Carolina Department of Health
and Environmental Control.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE, Room 2A,
Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s website at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above. Agencies may obtain copies of
the application directly from the
applicant.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
E:\FR\FM\22AUN1.SGM
22AUN1
Agencies
[Federal Register Volume 84, Number 163 (Thursday, August 22, 2019)]
[Notices]
[Pages 43801-43802]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-18122]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following exempt
wholesale generator filings:
Docket Numbers: EG19-166-000.
Applicants: Rosewater Wind Farm LLC.
Description: Notice of Self-Certification of Exempt Wholesale
Generator Status of Rosewater Wind Farm LLC.
Filed Date: 8/16/19.
Accession Number: 20190816-5019.
Comments Due: 5 p.m. ET 9/6/19.
Docket Numbers: EG19-167-000.
Applicants: Kaheawa Wind Power, LLC.
Description: Notice of Self-Certification of Exempt Wholesale
Generator Status of Kaheawa Wind Power, LLC.
Filed Date: 8/16/19.
Accession Number: 20190816-5065.
Comments Due: 5 p.m. ET 9/6/19.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER15-1883-006; ER10-1836-016; ER10-1841-015; ER10-
1845-015; ER10-1846-011; ER10-1849-017; ER10-1851-009; ER10-1852-029;
ER10-1855-011; ER10-1857-010; ER10-1887-017; ER10-1890-012; ER10-1897-
015; ER10-1899-011; ER10-1905-015; ER10-1907-014; ER10-1918-015; ER10-
1920-019; ER10-1925-015; ER10-1927-015; ER10-1928-019; ER10-1930-009;
ER10-1931-010; ER10-1932-010; ER10-1935-010; ER10-1950-015; ER10-1952-
017; ER10-1961-017; ER10-1962-012; ER10-1964-015; ER10-2005-015; ER10-
2006-016; ER10-2551-012; ER11-2160-012; ER11-26-015; ER11-2642-012;
ER11-3635-012; ER12-1228-019; ER12-2226-009; ER12-2227-017; ER12-569-
018; ER13-1991-011; ER13-1992-011; ER13-2112-008; ER13-712-019; ER13-
752-010; ER15-1418-006; ER15-1925-011; ER15-2101-006; ER15-2477-006;
ER15-2582-004; ER15-2601-004; ER15-2676-010; ER16-1672-008; ER16-2190-
007; ER16-2191-007; ER16-2275-007; ER16-2276-007; ER16-2453-008; ER16-
632-004; ER16-90-006; ER16-91-006; ER17-2152-004; ER17-2340-003; ER18-
1534-003; ER18-1771-005; ER18-1863-002; ER18-1952-005; ER18-1978-003;
ER18-2118-003; ER18-2246-004; ER18-882-003; ER19-1003-002; ER19-1392-
003; ER19-1393-002; ER19-1394-002; ER19-987-002/
Applicants: Adelanto Solar, LLC, Adelanto Solar II, LLC, Armadillo
Flats Wind Project, LLC, Ashtabula Wind, LLC, Ashtabula Wind II, LLC,
Ashtabula Wind III, LLC, Baldwin Wind, LLC, Blackwell Wind, LLC, Blythe
Solar 110, LLC, Blythe Solar II, LLC, Breckinridge Wind Project, LLC,
Brady Interconnection, LLC, Brady Wind, LLC, Brady Wind II, LLC, Butler
Ridge Wind Energy Center, LLC, Carousel Wind Farm, LLC, Casa Mesa Wind,
LLC, Cedar Bluff Wind, LLC, Chaves County Solar, LLC, Cimarron Wind
Energy, LLC, Coolidge Solar I, LLC, Cottonwood Wind Project, LLC,
Crystal Lake Wind Energy I, LLC, Crystal Lake Wind Energy I, LLC,
Crystal Lake Wind III, LLC, Day County Wind, LLC, Desert Sunlight 250,
LLC, Desert Sunlight 300, LLC, East Hampton Energy Storage Center, LLC,
Elk City Renewables II, LLC, Elk City Wind, LLC, Endeavor Wind I, LLC,
Endeavor Wind II, LLC, Energy Storage Holdings, LLC, Ensign Wind, LLC,
ESI Vansycle Partners, L.P., Florida Power & Light Company, FPL Energy
Burleigh County Wind, LLC, FPL Energy Cape, LLC, FPL Energy Cowboy
Wind, LLC, FPL Energy Green Power Wind, LLC, FPL Energy Hancock County
Wind, LLC, FPL Energy Illinois Wind, LLC, FPL Energy Montezuma Wind,
LLC, FPL Energy Mower County, LLC, FPL Energy North Dakota Wind, LLC,
FPL Energy North Dakota Wind II, LLC, FPL Energy Oklahoma Wind, LLC,
FPL Energy Oliver Wind I, LLC, FPL Energy Oliver Wind II, LLC, FPL
Energy Sooner Wind, LLC, FPL Energy South Dakota Wind, LLC, FPL Energy
Stateline II, Inc., FPL Energy Vansycle, L.L.C, FPL Energy Wyman, LLC,
FPL Energy Wyman IV, LLC, Garden Wind, LLC, Genesis Solar, LLC, Golden
Hills Interconnection, LLC, Golden Hills North Wind, LLC, Golden Hills
Wind, LLC, Golden West Power Partners, LLC, Gray County Wind Energy,
LLC, Green
[[Page 43802]]
Mountain Storage, LLC, Gulf Power Company, LLC, Hatch Solar Energy
Center I, LLC, Hawkeye Power Partners, LLC, Heartland Divide Wind
Project, LLC, High Lonesome Mesa Wind, LLC, High Majestic Wind Energy
Center, LLC, High Majestic Wind II, LLC, High Winds, LLC, Kingman Wind
Energy I, LLC, Kingman Wind Energy II, LLC, Lake Benton Power Partners
II, LLC, Langdon Renewables, LLC, Limon Wind, LLC
Description: Notice of Change in Status of the NextEra MBR Sellers
(Part 1).
Filed Date: 8/15/19.
Accession Number: 20190815-5219.
Comments Due: 5 p.m. ET 9/5/19.
Docket Numbers: ER19-2619-000.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Sec. 205(d) Rate Filing: 2019-08-15_Revisions to Fast
Automatic Generation Control Signals to be effective 10/15/2019.
Filed Date: 8/15/19.
Accession Number: 20190815-5182.
Comments Due: 5 p.m. ET 9/5/19.
Docket Numbers: ER19-2620-000.
Applicants: Idaho Power Company.
Description: Idaho Power Company submits Average System Cost Filing
for Sales of Electric Power to the Bonneville Power Administration, FY
2020-2021.
Filed Date: 8/15/19.
Accession Number: 20190815-5209.
Comments Due: 5 p.m. ET 9/5/19.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 85.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: August 16, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-18122 Filed 8-21-19; 8:45 am]
BILLING CODE 6717-01-P