Denali Commission Fiscal Year 2020 Draft Work Plan, 38604-38606 [2019-16914]
Download as PDF
38604
Federal Register / Vol. 84, No. 152 / Wednesday, August 7, 2019 / Notices
the FACA, all submitted comments will
be treated as public documents and will
be made available for public inspection,
including, but not limited to, being
posted on the Board’s website.
Dated: August 2, 2019.
Aaron T. Siegel,
Alternate OSD Federal Register Liaison
Officer, Department of Defense.
[FR Doc. 2019–16875 Filed 8–6–19; 8:45 am]
BILLING CODE 5001–06–P
DEPARTMENT OF DEFENSE
Department of the Navy
Meeting of the Board of Visitors of
Marine Corps University
Department of the Navy, DoD.
Notice of open meeting.
AGENCY:
ACTION:
The Board of Visitors of the
Marine Corps University (BOV MCU)
will meet to review, develop and
provide recommendations on all aspects
of the academic and administrative
policies of the University; examine all
aspects of professional military
education operations; and provide such
oversight and advice, as is necessary, to
facilitate high educational standards
and cost effective operations. The Board
will be focusing primarily on the
internal procedures of Marine Corps
University. All sessions of the meeting
will be open to the public.
DATES: The meeting will be held on
Thursday, September 19, 2019, from
8:00 a.m. to 4:30 p.m. and Friday,
September 20, 2019, from 8:00 a.m. to
12:30 p.m. Eastern Time Zone.
ADDRESSES: The meeting will be held at
Marine Corps University in Quantico,
Virginia. The address is: 2076 South
Street, Quantico, VA 22134.
FOR FURTHER INFORMATION CONTACT: Dr.
Kim Florich, Director of Faculty
Development and Outreach, Marine
Corps University Board of Visitors, 2076
South Street, Quantico, Virginia 22134,
703–432–4837.
SUMMARY:
Dated: August 2, 2019.
M.S. Werner,
Commander, Judge Advocate General’s Corps,
U.S. Navy, Federal Register Liaison Officer.
[FR Doc. 2019–16869 Filed 8–6–19; 8:45 am]
jspears on DSK3GMQ082PROD with NOTICES
BILLING CODE 3810–FF–P
DENALI COMMISSION
Denali Commission Fiscal Year 2020
Draft Work Plan
Denali Commission.
Notice.
AGENCY:
ACTION:
VerDate Sep<11>2014
16:49 Aug 06, 2019
Jkt 247001
The Denali Commission
(Commission) is an independent Federal
agency based on an innovative federalstate partnership designed to provide
critical utilities, infrastructure and
support for economic development and
training in Alaska by delivering federal
services in the most cost-effective
manner possible. The Commission was
created in 1998 with passage of the
October 21, 1998 Denali Commission
Act (Act). The Act requires that the
Commission develop proposed work
plans for future spending and that the
annual work plan be published in the
Federal Register, providing an
opportunity for a 30-day period of
public review and written comment.
This Federal Register notice serves to
announce the 30-day opportunity for
public comment on the Denali
Commission Draft Work Plan for Federal
Fiscal Year 2020 (FY 2020).
DATES: Comments and related material
to be received by September 2, 2019.
ADDRESSES: Submit comments to the
Denali Commission, Attention: Elinda
Hetami, 510 L Street, Suite 410,
Anchorage, AK 99501.
FOR FURTHER INFORMATION CONTACT:
Elinda Hetami, Denali Commission, 510
L Street, Suite 410, Anchorage, AK
99501. Telephone: (907) 271–3415.
Email: ehetemi@denali.gov.
SUPPLEMENTARY INFORMATION:
Background: The Denali Commission’s
mission is to partner with tribal, federal,
state, and local governments and
collaborate with all Alaskans to improve
the effectiveness and efficiency of
government services, to build and
ensure the operation and maintenance
of Alaska’s basic infrastructure, and to
develop a well-trained labor force
employed in a diversified and
sustainable economy.
By creating the Commission, Congress
mandated that all parties involved
partner together to find new and
innovative solutions to the unique
infrastructure and economic
development challenges in America’s
most remote communities. Pursuant to
the Act, the Commission determines its
own basic operating principles and
funding criteria on an annual federal
fiscal year (October 1 to September 30)
basis. The Commission outlines these
priorities and funding recommendations
in an annual work plan. The FY 2020
Work Plan was developed in the
following manner.
• A workgroup comprised of Denali
Commissioners and Commission staff
developed a preliminary draft work
plan.
• The preliminary draft work plan
was published on Denali.gov for review
SUMMARY:
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
by the public in advance of public
testimony.
• A public hearing was held to record
public comments and recommendations
on the preliminary draft work plan.
• Written comments on the
preliminary draft work plan were
accepted for another ten days after the
public hearing.
• All public hearing comments and
written comments were provided to
Commissioners for their review and
consideration.
• Commissioners discussed the
preliminary draft work plan in a public
meeting and then voted on the work
plan during the meeting.
• The Commissioners forwarded their
recommended work plan to the Federal
Co-Chair, who then prepared the draft
work plan for publication in the Federal
Register providing a 30-day period for
public review and written comment.
During this time, the draft work plan
will also be disseminated to
Commission program partners
including, but not limited to, the Bureau
of Indian Affairs (BIA), the Economic
Development Administration (EDA),
Department of Agriculture—Rural
Utilities Service (USDA/RUS), and the
State of Alaska.
• At the conclusion of the Federal
Register Public comment period
Commission staff provides the Federal
Co-Chair with a summary of public
comments and recommendations, if any,
on the draft work plan.
• If no revisions are made to the draft,
the Federal Co-Chair provides notice of
approval of the work plan to the
Commissioners, and forwards the work
plan to the Secretary of Commerce for
approval; or, if there are revisions the
Federal Co-Chair provides notice of
modifications to the Commissioners for
their consideration and approval, and
upon receipt of approval from
Commissioners, forwards the work plan
to the Secretary of Commerce for
approval.
• The Secretary of Commerce
approves the work plan.
• The Federal Co-Chair then approves
grants and contracts based upon the
approved work plan.
FY 2020 Appropriations Summary
The Commission has historically
received federal funding from several
sources. The two primary sources at this
time include the Energy & Water
Appropriation Bill (‘‘base’’ or
‘‘discretionary’’ funds) and an annual
allocation from the Trans-Alaska
Pipeline Liability (TAPL) fund. The
proposed FY 2020 Work Plan assumes
the Commission will receive
$15,000,000 of base funds, which is the
E:\FR\FM\07AUN1.SGM
07AUN1
38605
Federal Register / Vol. 84, No. 152 / Wednesday, August 7, 2019 / Notices
amount referenced in the
reauthorization of the Commission
passed by Congress in 2016 (ref: Pub. L.
114–322), and a $2,917,000 TAPL
allocation based on discussions with the
Office of Management and Budget
(OMB). Approximately $2,500,000 of
the base funds will be used for
administrative expenses and non-project
program support, leaving $12,500,000
available for program activities. The
total base funding shown in the Work
Plan also includes an amount typically
available from project closeouts and
other de-obligations that occur in any
given year. Approximately $117,000 of
the TAPL funds will be utilized for
administrative expenses and non-project
program support, leaving $2,800,000
available for program activities. Absent
any new specific direction or limitations
provided by Congress in the current
Energy & Water Appropriations Bill,
these funding sources are governed by
the following general principles, either
by statute or by language in the Work
Plan itself:
• Funds from the Energy & Water
Appropriation are eligible for use in all
programs.
• TAPL funds can only be used for
bulk fuel related projects and activities.
• Appropriated funds may be reduced
due to Congressional action, rescissions
by OMB, and other federal agency
actions.
• All Energy & Water and TAPL
investment amounts identified in the
work plan, are ‘‘up to’’ amounts, and
may be reassigned to other programs
included in the current year work plan,
if they are not fully expended in a
program component area or a specific
project.
• Energy & Water and TAPL funds set
aside for administrative expenses that
subsequently become available, may be
used for program activities included in
the current year work plan.
Denali Commission FY2020 funding summary
Available for
program
activities
Source
Energy & Water Funds:
FY 2020 Energy & Water Appropriation 1 ....................................................................................................................................
Prior Year Funds ..........................................................................................................................................................................
$12,500,000
2,000,000
Subtotal .................................................................................................................................................................................
TAPL Funds:
FY 2020 Annual Allocation ...........................................................................................................................................................
14,500,000
Grand Total ...........................................................................................................................................................................
17,300,000
2,800,000
Notes:
1. If the final appropriation is less than $15 million the Federal Co-Chair shall reduce investments to balance the FY 2020 Work Plan.
Base
Energy Reliability and Security:
Diesel Power Plants and Interties ........................................................................................
Wind, Hydro, Biomass, Other Proven Renewables and Emerging Technologies ...............
Audits, TA, & Community Energy Efficiency Improvements ................................................
RPSU Maintenance and Improvement Projects ..................................................................
Total
$3,800,000
1,000,000
500,000
1,200,000
........................
........................
........................
........................
$3,800,000
1,000,000
500,000
1,200,000
6,500,000
........................
6,500,000
........................
........................
$1,500,000
700,000
1,500,000
700,000
0
2,200,000
2,200,000
150,000
150,000
150,000
150,000
400,000
........................
........................
........................
........................
........................
150,000
150,000
150,000
150,000
400,000
Subtotal .........................................................................................................................
Transportation ..............................................................................................................................
Sanitation:
Village Water, Wastewater and Solid Waste .......................................................................
1,000,000
1,000,000
........................
........................
1,000,000
1,000,000
2,000,000
........................
2,000,000
Subtotal .........................................................................................................................
Health Facilities ...........................................................................................................................
Housing ........................................................................................................................................
Broadband ...................................................................................................................................
Workforce Development:
Energy and Bulk Fuel ...........................................................................................................
Other .....................................................................................................................................
2,000,000
1,000,000
500,000
1,000,000
........................
........................
........................
........................
2,000,000
1,000,000
500,000
1,000,000
500,000
1,000,000
600,000
........................
1,100,000
1,000,000
Subtotal .........................................................................................................................
1,500,000
600,000
2,100,000
Totals ......................................................................................................................
14,500,000
2,800,000
17,300,000
Subtotal .........................................................................................................................
Bulk Fuel Safety and Security:
New/Refurbished Facilities ...................................................................................................
Maintenance and Improvement Projects ..............................................................................
Subtotal .........................................................................................................................
Village Infrastructure Protection:
Mertarvik ...............................................................................................................................
Shishmaref ............................................................................................................................
Shaktoolik .............................................................................................................................
Kivalina .................................................................................................................................
Program Support ..................................................................................................................
jspears on DSK3GMQ082PROD with NOTICES
TAPL
VerDate Sep<11>2014
16:49 Aug 06, 2019
Jkt 247001
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
E:\FR\FM\07AUN1.SGM
07AUN1
38606
Federal Register / Vol. 84, No. 152 / Wednesday, August 7, 2019 / Notices
Energy, Bulk Fuel, Transportation,
Sanitation, Health Facilities, Housing,
Broadband, Workforce Development
In FY 2020 the Commission is moving
in a new direction to work closely with
other Federal Agencies, the State of
Alaska and regional/local entities with
the goal of identifying projects with
funding gaps that will allow the
Commission to use its small amount of
funding to move forward a large number
of projects. The Commission has already
begun to have conversations with many
of our Federal partners and intends to
prioritize shovel-ready projects where
the Commission can leverage its funds.
If the Commission is unable to fully
utilize its funding by April of 2020 then
it will use any remaining funds to fund
Energy and Bulk Fuel projects
consistent with a needs-based list
established in partnership with the State
of Alaska.
Mertarvik, Shishmaref, Shaktoolik and
Kivalina
In FY 2020 the Commission will
continue to provide support to these
communities by funding the relocation
coordinator positions. These
coordinators will assist the communities
in applying for grants and coordinating
relocation efforts.
Program Development
The $400,000 referenced above for
this line item in the Workplan will be
used to fund the ETC Grant Writing
Center of Excellence at the Alaska
Native Tribal Health Consortium.
Chad Stovall,
Chief Operating Officer.
[FR Doc. 2019–16914 Filed 8–6–19; 8:45 am]
BILLING CODE 3300–01–P
DEPARTMENT OF EDUCATION
Applications for New Awards;
Technical Assistance and
Dissemination To Improve Services
and Results for Children With
Disabilities—Technical Assistance and
Dissemination Center for the
Development and Implementation of
High-Quality Instruction, Interventions,
and Services for Children With
Disabilities
Office of Special Education and
Rehabilitative Services, Department of
Education.
ACTION: Notice.
jspears on DSK3GMQ082PROD with NOTICES
AGENCY:
The mission of the Office of
Special Education and Rehabilitative
Services (OSERS) is to improve early
childhood, educational, and
SUMMARY:
VerDate Sep<11>2014
16:49 Aug 06, 2019
Jkt 247001
employment outcomes and raise
expectations for all people with
disabilities, their families, their
communities, and the Nation. As such,
the Department of Education
(Department) is issuing a notice inviting
applications for new awards for fiscal
year (FY) 2019 for a Technical
Assistance and Dissemination Center for
the Development and Implementation of
High-Quality Instruction, Interventions,
and Services for Children with
Disabilities, Catalog of Federal Domestic
Assistance (CFDA) number 84.326C.
This Center will develop knowledge,
curate resources, and disseminate
information related to (1) enabling
children with disabilities to make
progress toward meeting challenging
goals and objectives in light of each
child’s circumstances, and (2)
supporting local educational agencies
(LEAs), charter management
organizations (CMOs), private school
associations, and schools in developing
and implementing high-quality
individualized educational
programming. This notice relates to the
approved information collection under
OMB control number 1820–0028.
DATES:
Applications Available: August 7,
2019.
Deadline for Transmittal of
Applications: September 6, 2019.
Pre-Application Webinar Information:
No later than August 12, 2019, OSERS
will post pre-recorded informational
webinars designed to provide technical
assistance to interested applicants. The
webinars may be found at www2.ed.gov/
fund/grant/apply/osep/new-osepgrants.html.
Pre-Application Q & A Blog: No later
than August 12, 2019, OSERS will open
a blog where interested applicants may
post questions about the application
requirements for this competition and
where OSERS will post answers to the
questions received. OSERS will not
respond to questions unrelated to the
application requirements for this
competition. The blog may be found at
www2.ed.gov/fund/grant/apply/osep/
new-osep-grants.html and will remain
open until August 26, 2019. After the
blog closes, applicants should direct
questions to the person listed under FOR
FURTHER INFORMATION CONTACT.
ADDRESSES: For the addresses for
obtaining and submitting an
application, please refer to our Common
Instructions for Applicants to
Department of Education Discretionary
Grant Programs, published in the
Federal Register on February 13, 2019
(84 FR 3768), and available at
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
www.govinfo.gov/content/pkg/FR-201902-13/pdf/2019-02206.pdf.
FOR FURTHER INFORMATION CONTACT:
David E. Emenheiser, U.S. Department
of Education, 400 Maryland Avenue
SW, Room 5134, Potomac Center Plaza,
Washington, DC 20202–5076.
Telephone: (202) 245–7556. Email:
David.Emenheiser@ed.gov.
If you use a telecommunications
device for the deaf (TDD) or a text
telephone (TTY), call the Federal Relay
Service (FRS), toll free, at 1–800–877–
8339.
SUPPLEMENTARY INFORMATION:
Full Text of Announcement
I. Funding Opportunity Description
Purpose of Program: The purpose of
the Technical Assistance and
Dissemination to Improve Services and
Results for Children with Disabilities
program is to promote academic
achievement and to improve results for
children with disabilities by providing
TA, supporting model demonstration
projects, disseminating useful
information, and implementing
activities that are supported by
scientifically based research.
Priority: This competition includes
one absolute priority. In accordance
with 34 CFR 75.105(b)(2)(v), this
priority is from allowable activities
specified in the statute (see sections 663
and 681(d) of the Individuals with
Disabilities Education Act (IDEA); 20
U.S.C. 1463 and 1481(d)).
Absolute Priority: For FY 2019 and
any subsequent year in which we make
awards from the list of unfunded
applications from this competition, this
priority is an absolute priority. Under 34
CFR 75.105(c)(3), we consider only
applications that meet this priority.
This priority is:
Technical Assistance and
Dissemination Center for the
Development and Implementation of
High-Quality Instruction, Interventions,
and Services for Children with
Disabilities (Center).
Background:
The Individuals with Disabilities
Education Act (IDEA) entitles all
eligible children with disabilities to a
free appropriate public education
(FAPE) that emphasizes special
education and related services designed
to meet their unique needs and prepare
them for further education,
employment, and independent living.
(20 U.S.C. 1400(d)(1)(A)). The
individualized education program (IEP)
is the primary vehicle through which
FAPE is delivered to those eligible
children and is the foundation for each
E:\FR\FM\07AUN1.SGM
07AUN1
Agencies
[Federal Register Volume 84, Number 152 (Wednesday, August 7, 2019)]
[Notices]
[Pages 38604-38606]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-16914]
=======================================================================
-----------------------------------------------------------------------
DENALI COMMISSION
Denali Commission Fiscal Year 2020 Draft Work Plan
AGENCY: Denali Commission.
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: The Denali Commission (Commission) is an independent Federal
agency based on an innovative federal-state partnership designed to
provide critical utilities, infrastructure and support for economic
development and training in Alaska by delivering federal services in
the most cost-effective manner possible. The Commission was created in
1998 with passage of the October 21, 1998 Denali Commission Act (Act).
The Act requires that the Commission develop proposed work plans for
future spending and that the annual work plan be published in the
Federal Register, providing an opportunity for a 30-day period of
public review and written comment. This Federal Register notice serves
to announce the 30-day opportunity for public comment on the Denali
Commission Draft Work Plan for Federal Fiscal Year 2020 (FY 2020).
DATES: Comments and related material to be received by September 2,
2019.
ADDRESSES: Submit comments to the Denali Commission, Attention: Elinda
Hetami, 510 L Street, Suite 410, Anchorage, AK 99501.
FOR FURTHER INFORMATION CONTACT: Elinda Hetami, Denali Commission, 510
L Street, Suite 410, Anchorage, AK 99501. Telephone: (907) 271-3415.
Email: [email protected].
SUPPLEMENTARY INFORMATION: Background: The Denali Commission's mission
is to partner with tribal, federal, state, and local governments and
collaborate with all Alaskans to improve the effectiveness and
efficiency of government services, to build and ensure the operation
and maintenance of Alaska's basic infrastructure, and to develop a
well-trained labor force employed in a diversified and sustainable
economy.
By creating the Commission, Congress mandated that all parties
involved partner together to find new and innovative solutions to the
unique infrastructure and economic development challenges in America's
most remote communities. Pursuant to the Act, the Commission determines
its own basic operating principles and funding criteria on an annual
federal fiscal year (October 1 to September 30) basis. The Commission
outlines these priorities and funding recommendations in an annual work
plan. The FY 2020 Work Plan was developed in the following manner.
A workgroup comprised of Denali Commissioners and
Commission staff developed a preliminary draft work plan.
The preliminary draft work plan was published on
Denali.gov for review by the public in advance of public testimony.
A public hearing was held to record public comments and
recommendations on the preliminary draft work plan.
Written comments on the preliminary draft work plan were
accepted for another ten days after the public hearing.
All public hearing comments and written comments were
provided to Commissioners for their review and consideration.
Commissioners discussed the preliminary draft work plan in
a public meeting and then voted on the work plan during the meeting.
The Commissioners forwarded their recommended work plan to
the Federal Co-Chair, who then prepared the draft work plan for
publication in the Federal Register providing a 30-day period for
public review and written comment. During this time, the draft work
plan will also be disseminated to Commission program partners
including, but not limited to, the Bureau of Indian Affairs (BIA), the
Economic Development Administration (EDA), Department of Agriculture--
Rural Utilities Service (USDA/RUS), and the State of Alaska.
At the conclusion of the Federal Register Public comment
period Commission staff provides the Federal Co-Chair with a summary of
public comments and recommendations, if any, on the draft work plan.
If no revisions are made to the draft, the Federal Co-
Chair provides notice of approval of the work plan to the
Commissioners, and forwards the work plan to the Secretary of Commerce
for approval; or, if there are revisions the Federal Co-Chair provides
notice of modifications to the Commissioners for their consideration
and approval, and upon receipt of approval from Commissioners, forwards
the work plan to the Secretary of Commerce for approval.
The Secretary of Commerce approves the work plan.
The Federal Co-Chair then approves grants and contracts
based upon the approved work plan.
FY 2020 Appropriations Summary
The Commission has historically received federal funding from
several sources. The two primary sources at this time include the
Energy & Water Appropriation Bill (``base'' or ``discretionary'' funds)
and an annual allocation from the Trans-Alaska Pipeline Liability
(TAPL) fund. The proposed FY 2020 Work Plan assumes the Commission will
receive $15,000,000 of base funds, which is the
[[Page 38605]]
amount referenced in the reauthorization of the Commission passed by
Congress in 2016 (ref: Pub. L. 114-322), and a $2,917,000 TAPL
allocation based on discussions with the Office of Management and
Budget (OMB). Approximately $2,500,000 of the base funds will be used
for administrative expenses and non-project program support, leaving
$12,500,000 available for program activities. The total base funding
shown in the Work Plan also includes an amount typically available from
project closeouts and other de-obligations that occur in any given
year. Approximately $117,000 of the TAPL funds will be utilized for
administrative expenses and non-project program support, leaving
$2,800,000 available for program activities. Absent any new specific
direction or limitations provided by Congress in the current Energy &
Water Appropriations Bill, these funding sources are governed by the
following general principles, either by statute or by language in the
Work Plan itself:
Funds from the Energy & Water Appropriation are eligible
for use in all programs.
TAPL funds can only be used for bulk fuel related projects
and activities.
Appropriated funds may be reduced due to Congressional
action, rescissions by OMB, and other federal agency actions.
All Energy & Water and TAPL investment amounts identified
in the work plan, are ``up to'' amounts, and may be reassigned to other
programs included in the current year work plan, if they are not fully
expended in a program component area or a specific project.
Energy & Water and TAPL funds set aside for administrative
expenses that subsequently become available, may be used for program
activities included in the current year work plan.
------------------------------------------------------------------------
Denali Commission FY2020 funding summary
-------------------------------------------------------------------------
Available for
Source program
activities
------------------------------------------------------------------------
Energy & Water Funds:
FY 2020 Energy & Water Appropriation \1\............ $12,500,000
Prior Year Funds.................................... 2,000,000
---------------
Subtotal........................................ 14,500,000
TAPL Funds:
FY 2020 Annual Allocation........................... 2,800,000
---------------
Grand Total..................................... 17,300,000
------------------------------------------------------------------------
Notes:
\1.\ If the final appropriation is less than $15 million the Federal Co-
Chair shall reduce investments to balance the FY 2020 Work Plan.
----------------------------------------------------------------------------------------------------------------
Base TAPL Total
----------------------------------------------------------------------------------------------------------------
Energy Reliability and Security:
Diesel Power Plants and Interties........................... $3,800,000 .............. $3,800,000
Wind, Hydro, Biomass, Other Proven Renewables and Emerging 1,000,000 .............. 1,000,000
Technologies...............................................
Audits, TA, & Community Energy Efficiency Improvements...... 500,000 .............. 500,000
RPSU Maintenance and Improvement Projects................... 1,200,000 .............. 1,200,000
-----------------------------------------------
Subtotal................................................ 6,500,000 .............. 6,500,000
Bulk Fuel Safety and Security:
New/Refurbished Facilities.................................. .............. $1,500,000 1,500,000
Maintenance and Improvement Projects........................ .............. 700,000 700,000
-----------------------------------------------
Subtotal................................................ 0 2,200,000 2,200,000
Village Infrastructure Protection:
Mertarvik................................................... 150,000 .............. 150,000
Shishmaref.................................................. 150,000 .............. 150,000
Shaktoolik.................................................. 150,000 .............. 150,000
Kivalina.................................................... 150,000 .............. 150,000
Program Support............................................. 400,000 .............. 400,000
-----------------------------------------------
Subtotal................................................ 1,000,000 .............. 1,000,000
Transportation.................................................. 1,000,000 .............. 1,000,000
Sanitation:
Village Water, Wastewater and Solid Waste................... 2,000,000 .............. 2,000,000
-----------------------------------------------
Subtotal................................................ 2,000,000 .............. 2,000,000
Health Facilities............................................... 1,000,000 .............. 1,000,000
Housing......................................................... 500,000 .............. 500,000
Broadband....................................................... 1,000,000 .............. 1,000,000
Workforce Development:
Energy and Bulk Fuel........................................ 500,000 600,000 1,100,000
Other....................................................... 1,000,000 .............. 1,000,000
-----------------------------------------------
Subtotal................................................ 1,500,000 600,000 2,100,000
-----------------------------------------------
Totals.............................................. 14,500,000 2,800,000 17,300,000
----------------------------------------------------------------------------------------------------------------
[[Page 38606]]
Energy, Bulk Fuel, Transportation, Sanitation, Health Facilities,
Housing, Broadband, Workforce Development
In FY 2020 the Commission is moving in a new direction to work
closely with other Federal Agencies, the State of Alaska and regional/
local entities with the goal of identifying projects with funding gaps
that will allow the Commission to use its small amount of funding to
move forward a large number of projects. The Commission has already
begun to have conversations with many of our Federal partners and
intends to prioritize shovel-ready projects where the Commission can
leverage its funds. If the Commission is unable to fully utilize its
funding by April of 2020 then it will use any remaining funds to fund
Energy and Bulk Fuel projects consistent with a needs-based list
established in partnership with the State of Alaska.
Mertarvik, Shishmaref, Shaktoolik and Kivalina
In FY 2020 the Commission will continue to provide support to these
communities by funding the relocation coordinator positions. These
coordinators will assist the communities in applying for grants and
coordinating relocation efforts.
Program Development
The $400,000 referenced above for this line item in the Workplan
will be used to fund the ETC Grant Writing Center of Excellence at the
Alaska Native Tribal Health Consortium.
Chad Stovall,
Chief Operating Officer.
[FR Doc. 2019-16914 Filed 8-6-19; 8:45 am]