Florida Gas Transmission Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Putnam Expansion Project and Request for Comments on Environmental Issues, 35113-35115 [2019-15487]

Download as PDF Federal Register / Vol. 84, No. 140 / Monday, July 22, 2019 / Notices comments on the EA before making recommendations to the Commission. With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the EA.2 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultation Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic Preservation Office, and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.3 The EA for this project will document findings on the impacts on historic properties and summarize the status of consultations under section 106. jbell on DSK3GLQ082PROD with NOTICES Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If the Commission issues the EA for an allotted public comment period, a Notice of Availability of the EA will 2 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 3 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. VerDate Sep<11>2014 19:11 Jul 19, 2019 Jkt 247001 be sent to the environmental mailing list and will provide instructions to access the electronic document on the FERC’s website (www.ferc.gov). Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on General Search and enter the docket number in the Docket Number field, excluding the last three digits (i.e., CP19–479–000. Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. Dated: July 16, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–15483 Filed 7–19–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP19–474–000] Florida Gas Transmission Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Putnam Expansion Project and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Putnam Expansion Project involving construction and operation of facilities by Florida Gas Transmission Company, LLC (FGT) in Columbia, Union, Putnam, Clay, and Orange Counties, Florida. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies about issues regarding the project. The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from its action whenever it PO 00000 Frm 00046 Fmt 4703 Sfmt 4703 35113 considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires the Commission to discover concerns the public may have about proposals. This process is referred to as scoping. The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC on or before 5:00 p.m. Eastern Time on August 15, 2019. You can make a difference by submitting your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Commission staff will consider all filed comments during the preparation of the EA. If you sent comments on this project to the Commission before the opening of this docket on June 14, 2019, you will need to file those comments in Docket No. CP19–474–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable easement agreement. You are not required to enter into an agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if you and the company do not reach an easement agreement, the pipeline company could initiate condemnation proceedings in court. In such instances, compensation would be determined by a judge in accordance with state law. FGT provided landowners with a fact sheet prepared by the FERC entitled An Interstate Natural Gas Facility On My Land? What Do I Need To Know? This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s E:\FR\FM\22JYN1.SGM 22JYN1 35114 Federal Register / Vol. 84, No. 140 / Monday, July 22, 2019 / Notices proceedings. It is also available for viewing on the FERC website (www.ferc.gov) at https://www.ferc.gov/ resources/guides/gas/gas.pdf. Public Participation The Commission offers a free service called eSubscription which makes it easy to stay informed of all issuances and submittals regarding the dockets/ projects to which you subscribe. These instant email notifications are the fastest way to receive notification and provide a link to the document files which can reduce the amount of time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/ esubscription.asp. For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208–3676 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. Using eComment is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on eRegister. You will be asked to select the type of filing you are making; a comment on a particular project is considered a Comment on a Filing; or (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (CP19–474– 000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. jbell on DSK3GLQ082PROD with NOTICES Summary of the Proposed Project The Putnam Expansion Project would consist of the following facilities in Florida: • West Loop—install 13.7 miles of 30inch-diameter pipeline loop 1 in Columbia and Union Counties; 1 A pipeline loop is a segment of pipe constructed parallel to an existing pipeline to increase capacity. VerDate Sep<11>2014 19:11 Jul 19, 2019 Jkt 247001 • East Loop—install 7.0 miles of 30inch-diameter pipeline loop in Clay and Putnam Counties; • Columbia/Union Receiver Station Relocation—remove and relocate the existing 30-inch-diameter loop pig receiver located at the beginning of the West Loop in Columbia County to a new pig receiver station to be installed at the terminus of the West Loop in Union County; • Clay/Putnam Receiver Station Relocation—remove and relocate the existing 30-inch-diateter loop pig receiver located at the beginning of the East Loop in Clay County to a new pig receiver station to be installed at the terminus of the East Loop in Putnam County; • Compressor Station (CS) 18—install new automated valves, over pressure protection device, and station piping at FGT’s existing CS 18 in Orange County, Florida. The general location of the project facilities is shown in appendix 1.2 Land Requirements for Construction Construction of the Project would disturb about 357.8 acres of land for the aboveground facilities and the pipeline loop. Following construction, FGT would maintain about 16.4 acres for permanent operation of the project’s facilities, and the remaining acreage would be restored and revert to former uses. The pipeline loops would be 100 percent collocated with the FGT mainline right-of-way. About 45 percent of the proposed pipeline loops would be located within FGT’s existing right-ofway. All modifications at CS 18 would occur within the existing station boundaries. The EA Process The EA will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geological resources; • water resources and wetlands; • vegetation and wildlife; • threatened and endangered species; • cultural resources; • land use; A ‘‘pig’’ is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting internal inspections, or other purposes. 2 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called eLibrary or from the Commission’s Public Reference Room, 888 First Street NE, Washington, DC 20426, or call (202) 502– 8371. For instructions on connecting to eLibrary, refer to the last page of this notice. PO 00000 Frm 00047 Fmt 4703 Sfmt 4703 • air quality and noise; • public safety; and • cumulative impacts. Commission staff will also evaluate reasonable alternatives to the proposed project, and make recommendations on how to lessen or avoid impacts on the various resource areas as applicable. The EA will present Commission staffs’ independent analysis of the issues. The EA will be available in electronic format in the public record through eLibrary 3 and the Commission’s website (https:// www.ferc.gov/industries/gas/enviro/ eis.asp). If eSubscribed, you will receive instant email notification when the EA is issued. The EA may be issued for an allotted public comment period. Commission staff will consider all comments on the EA before making recommendations to the Commission. To ensure Commission staff have the opportunity to address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2. With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the EA.4 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultation Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic Preservation Office (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.5 The EA for this project will document findings on the impacts on historic properties and summarize the status of consultations under section 106. 3 For instructions on connecting to eLibrary, refer to the last page of this notice. 4 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 5 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. E:\FR\FM\22JYN1.SGM 22JYN1 Federal Register / Vol. 84, No. 140 / Monday, July 22, 2019 / Notices jbell on DSK3GLQ082PROD with NOTICES Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If the Commission issues the EA for an allotted public comment period, a Notice of Availability of the EA will be sent to the environmental mailing list and will provide instructions to access the electronic document on the FERC’s website (www.ferc.gov). If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please return the attached Mailing List Update Form (appendix 2). Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on General Search and enter the docket number in the Docket Number field, excluding the last three digits (i.e., CP19–474). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. Public sessions or site visits will be posted on the Commission’s calendar located at www.ferc.gov/EventCalendar/ EventsList.aspx along with other related information. Dated: July 16, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–15487 Filed 7–19–19; 8:45 am] BILLING CODE 6717–01–P VerDate Sep<11>2014 19:11 Jul 19, 2019 Jkt 247001 FEDERAL COMMUNICATIONS COMMISSION [OMB 3060–0568] Information Collection Requirement Being Reviewed by the Federal Communications Commission Federal Communications Commission. ACTION: Notice and request for comments. AGENCY: As part of its continuing effort to reduce paperwork burdens, and as required by the Paperwork Reduction Act (PRA) of 1995, the Federal Communications Commission (FCC or the Commission) invites the general public and other Federal agencies to take this opportunity to comment on the following information collection. Comments are requested concerning: Whether the proposed collection of information is necessary for the proper performance of the functions of the Commission, including whether the information shall have practical utility; the accuracy of the Commission’s burden estimate; ways to enhance the quality, utility, and clarity of the information collected; ways to minimize the burden of the collection of information on the respondents, including the use of automated collection techniques or other forms of information technology; and ways to further reduce the information collection burden on small business concerns with fewer than 25 employees. The FCC may not conduct or sponsor a collection of information unless it displays a currently valid control number. No person shall be subject to any penalty for failing to comply with a collection of information subject to the PRA that does not display a valid Office of Management and Budget (OMB) control number. DATES: Written PRA comments should be submitted on or before September 20, 2019. If you anticipate that you will be submitting comments but find it difficult to do so within the period of time allowed by this notice, you should advise the contact listed below as soon as possible. ADDRESSES: Direct all PRA comments to Cathy Williams, FCC, via email PRA@ fcc.gov and to Cathy.Williams@fcc.gov. Include in the comments the Title as shown in the SUPPLEMENTARY INFORMATION section below. FOR FURTHER INFORMATION CONTACT: For additional information about the information collection, contact Cathy Williams at (202) 418–2918. SUMMARY: PO 00000 Frm 00048 Fmt 4703 Sfmt 4703 35115 OMB Control Number: 3060–0568. Title: Sections 76.970, 76.971, and 76.975, Commercial Leased Access Rates, Terms and Conditions, and Dispute Resolution. Form Number: N/A. Type of Review: Revision of a currently approved collection. Respondents: Businesses or other forprofit entities; Not-for-profit institutions. Number of Respondents and Responses: 2,677 respondents; 6,879 responses. Estimated Time per Response: 0.5 hours to 40 hours. Frequency of Response: Recordkeeping requirement; On occasion reporting requirement; Thirdparty disclosure requirement. Obligation to Respond: Mandatory; Required to obtain or retain benefits. The statutory authority for this information collection is contained in sections 4(i), 303, and 612 of the Communications Act of 1934, as amended, 47 U.S.C. 154(i), 303, and 532. Total Annual Burden: 17,131 hours. Total Annual Cost: $118,000. Privacy Act Impact Assessment: No impact(s). Nature and Extent of Confidentiality: There is no need for confidentiality with this collection of information. Needs and Uses: On June 7, 2019, in document FCC 19–52, the Commission released a Report and Order and Second Further Notice of Proposed Rulemaking updating its leased access rules as part of its Modernization of Media Regulation Initiative. The information collection requirements for this collection, some of which were revised (Sections 76.970(h) and 76.975(e)) by FCC 19–52, are contained in the following rule sections: 47 CFR 76.970(h) requires cable operators to provide prospective leased access programmers with the following information within 30 calendar days of the date on which a bona fide request for leased access information is made, provided that the programmer has remitted any application fee that the cable system operator requires up to a maximum of $100 per system-specific bona fide request (for systems subject to small system relief, cable operators are required to provide the following information within 45 calendar days of a bona fide request): (a) How much of the cable operator’s leased access set-aside capacity is available; (b) a complete schedule of the operator’s full-time leased access rates; (c) rates associated with technical and studio costs; and SUPPLEMENTARY INFORMATION: E:\FR\FM\22JYN1.SGM 22JYN1

Agencies

[Federal Register Volume 84, Number 140 (Monday, July 22, 2019)]
[Notices]
[Pages 35113-35115]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-15487]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-474-000]


Florida Gas Transmission Company, LLC; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed Putnam Expansion 
Project and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Putnam Expansion Project 
involving construction and operation of facilities by Florida Gas 
Transmission Company, LLC (FGT) in Columbia, Union, Putnam, Clay, and 
Orange Counties, Florida. The Commission will use this EA in its 
decision-making process to determine whether the project is in the 
public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies about issues regarding the project. The National Environmental 
Policy Act (NEPA) requires the Commission to take into account the 
environmental impacts that could result from its action whenever it 
considers the issuance of a Certificate of Public Convenience and 
Necessity. NEPA also requires the Commission to discover concerns the 
public may have about proposals. This process is referred to as 
scoping. The main goal of the scoping process is to focus the analysis 
in the EA on the important environmental issues. By this notice, the 
Commission requests public comments on the scope of the issues to 
address in the EA. To ensure that your comments are timely and properly 
recorded, please submit your comments so that the Commission receives 
them in Washington, DC on or before 5:00 p.m. Eastern Time on August 
15, 2019.
    You can make a difference by submitting your specific comments or 
concerns about the project. Your comments should focus on the potential 
environmental effects, reasonable alternatives, and measures to avoid 
or lessen environmental impacts. Your input will help the Commission 
staff determine what issues they need to evaluate in the EA. Commission 
staff will consider all filed comments during the preparation of the 
EA.
    If you sent comments on this project to the Commission before the 
opening of this docket on June 14, 2019, you will need to file those 
comments in Docket No. CP19-474-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable easement agreement. You 
are not required to enter into an agreement. However, if the Commission 
approves the project, that approval conveys with it the right of 
eminent domain. Therefore, if you and the company do not reach an 
easement agreement, the pipeline company could initiate condemnation 
proceedings in court. In such instances, compensation would be 
determined by a judge in accordance with state law.
    FGT provided landowners with a fact sheet prepared by the FERC 
entitled An Interstate Natural Gas Facility On My Land? What Do I Need 
To Know? This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's

[[Page 35114]]

proceedings. It is also available for viewing on the FERC website 
(www.ferc.gov) at https://www.ferc.gov/resources/guides/gas/gas.pdf.

Public Participation

    The Commission offers a free service called eSubscription which 
makes it easy to stay informed of all issuances and submittals 
regarding the dockets/projects to which you subscribe. These instant 
email notifications are the fastest way to receive notification and 
provide a link to the document files which can reduce the amount of 
time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/esubscription.asp.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected]. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. Using eComment is an easy 
method for submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. With eFiling, you can provide 
comments in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on eRegister. You will be asked to select the type of filing you are 
making; a comment on a particular project is considered a Comment on a 
Filing; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP19-474-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    The Putnam Expansion Project would consist of the following 
facilities in Florida:
     West Loop--install 13.7 miles of 30-inch-diameter pipeline 
loop \1\ in Columbia and Union Counties;
---------------------------------------------------------------------------

    \1\ A pipeline loop is a segment of pipe constructed parallel to 
an existing pipeline to increase capacity. A ``pig'' is a tool that 
the pipeline company inserts into and pushes through the pipeline 
for cleaning the pipeline, conducting internal inspections, or other 
purposes.
---------------------------------------------------------------------------

     East Loop--install 7.0 miles of 30-inch-diameter pipeline 
loop in Clay and Putnam Counties;
     Columbia/Union Receiver Station Relocation--remove and 
relocate the existing 30-inch-diameter loop pig receiver located at the 
beginning of the West Loop in Columbia County to a new pig receiver 
station to be installed at the terminus of the West Loop in Union 
County;
     Clay/Putnam Receiver Station Relocation--remove and 
relocate the existing 30-inch-diateter loop pig receiver located at the 
beginning of the East Loop in Clay County to a new pig receiver station 
to be installed at the terminus of the East Loop in Putnam County;
     Compressor Station (CS) 18--install new automated valves, 
over pressure protection device, and station piping at FGT's existing 
CS 18 in Orange County, Florida.
    The general location of the project facilities is shown in appendix 
1.\2\
---------------------------------------------------------------------------

    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called eLibrary or from the Commission's Public 
Reference Room, 888 First Street NE, Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the Project would disturb about 357.8 acres of land 
for the aboveground facilities and the pipeline loop. Following 
construction, FGT would maintain about 16.4 acres for permanent 
operation of the project's facilities, and the remaining acreage would 
be restored and revert to former uses. The pipeline loops would be 100 
percent collocated with the FGT mainline right-of-way. About 45 percent 
of the proposed pipeline loops would be located within FGT's existing 
right-of-way. All modifications at CS 18 would occur within the 
existing station boundaries.

The EA Process

    The EA will discuss impacts that could occur as a result of the 
construction and operation of the proposed project under these general 
headings:
     Geological resources;
     water resources and wetlands;
     vegetation and wildlife;
     threatened and endangered species;
     cultural resources;
     land use;
     air quality and noise;
     public safety; and
     cumulative impacts.
    Commission staff will also evaluate reasonable alternatives to the 
proposed project, and make recommendations on how to lessen or avoid 
impacts on the various resource areas as applicable.
    The EA will present Commission staffs' independent analysis of the 
issues. The EA will be available in electronic format in the public 
record through eLibrary \3\ and the Commission's website (https://www.ferc.gov/industries/gas/enviro/eis.asp). If eSubscribed, you will 
receive instant email notification when the EA is issued. The EA may be 
issued for an allotted public comment period. Commission staff will 
consider all comments on the EA before making recommendations to the 
Commission. To ensure Commission staff have the opportunity to address 
your comments, please carefully follow the instructions in the Public 
Participation section, beginning on page 2.
---------------------------------------------------------------------------

    \3\ For instructions on connecting to eLibrary, refer to the 
last page of this notice.
---------------------------------------------------------------------------

    With this notice, the Commission is asking agencies with 
jurisdiction by law and/or special expertise with respect to the 
environmental issues of this project to formally cooperate in the 
preparation of the EA.\4\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultation Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, the Commission is using this notice to initiate 
consultation with the applicable State Historic Preservation Office 
(SHPO), and to solicit their views and those of other government 
agencies, interested Indian tribes, and the public on the project's 
potential effects on historic properties.\5\ The EA for this project 
will document findings on the impacts on historic properties and 
summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.

---------------------------------------------------------------------------

[[Page 35115]]

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. Commission staff will update the environmental 
mailing list as the analysis proceeds to ensure that Commission notices 
related to this environmental review are sent to all individuals, 
organizations, and government entities interested in and/or potentially 
affected by the proposed project.
    If the Commission issues the EA for an allotted public comment 
period, a Notice of Availability of the EA will be sent to the 
environmental mailing list and will provide instructions to access the 
electronic document on the FERC's website (www.ferc.gov). If you need 
to make changes to your name/address, or if you would like to remove 
your name from the mailing list, please return the attached Mailing 
List Update Form (appendix 2).

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website at www.ferc.gov using the eLibrary link. Click on the 
eLibrary link, click on General Search and enter the docket number in 
the Docket Number field, excluding the last three digits (i.e., CP19-
474). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or (866) 208-3676, or for TTY, contact (202) 
502-8659. The eLibrary link also provides access to the texts of all 
formal documents issued by the Commission, such as orders, notices, and 
rulemakings.
    Public sessions or site visits will be posted on the Commission's 
calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along 
with other related information.

    Dated: July 16, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-15487 Filed 7-19-19; 8:45 am]
 BILLING CODE 6717-01-P