Eagle Creek Sartell Hydro, LLC; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests, 33930-33931 [2019-15062]
Download as PDF
jspears on DSK30JT082PROD with NOTICES
33930
Federal Register / Vol. 84, No. 136 / Tuesday, July 16, 2019 / Notices
of intervention and pursuant to section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the EA
for this proposal. The filing of the EA
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list and will be
notified of any meetings associated with
the Commission’s environmental review
process. Environmental commenters
will not be required to serve copies of
filed documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 3 copies of the protest or
intervention to the Federal Energy
regulatory Commission, 888 First Street
NE, Washington, DC 20426.
VerDate Sep<11>2014
17:33 Jul 15, 2019
Jkt 247001
Dated: July 10, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–15068 Filed 7–15–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 8315–014]
Eagle Creek Sartell Hydro, LLC; Notice
of Application Accepted for Filing,
Soliciting Comments, Motions To
Intervene, and Protests
July 10, 2019.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Request for
temporary variance of Article 34.
b. Project No.: 8315–014.
c. Date Filed: July 9, 2019.
d. Applicant: Eagle Creek Sartell
Hydro, LLC.
e. Name of Project: Sartell Dam Hydro
Project.
f. Location: Mississippi River in
Stearns and Benton counties,
Minnesota.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Ms. Melissa
Rondou, Eagle Creek Sartell Hydro, LLC,
116 N State Street, P.O. Box 167,
Neshkoro, WI 54960, (920) 293–4628
ext. 347, melissa.rondou@
eaglecreekre.com.
i. FERC Contact: Mr. Jeremy Jessup,
(202) 502–6779, Jeremy.Jessup@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests, is 15
days from the issuance date of this
notice by the Commission. The
Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, and protests using
the Commission’s eFiling system at
https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/doc-sfiling/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
The first page of any filing should
include docket numbers P–8315–014.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Request: The
applicant requests a temporary variance
from the run-of-river and reservoir
elevation requirements of Article 34 of
the license. The variance will allow the
licensee to drawdown the reservoir
approximately three feet beginning
August 1, 2019, for a six-week period
(from August 1 through approximately
September 15, 2019). The drawdown is
to assist the Minnesota Department of
Natural Resources, the Little Rock Lake
Association, and the Benton Soil and
Water Conservation District to facilitate
water quality, fish habitat, and
restoration improvements in the reach
of the Mississippi River upstream of the
project, and at Little Rock Lake, located
approximately six miles upstream of the
project.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE, Room 2A,
Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s website at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208- 3676 or
email FERCOnlineSupport@ferc.gov, for
TTY, call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Motions to Intervene, or
Protests: Anyone may submit
comments, a motion to intervene, or a
protest in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
E:\FR\FM\16JYN1.SGM
16JYN1
Federal Register / Vol. 84, No. 136 / Tuesday, July 16, 2019 / Notices
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
motions to intervene, or protests must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘MOTION TO
INTERVENE’’, or ‘‘PROTEST’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number(s) of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person intervening or
protesting; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene, or
protests must set forth their evidentiary
basis. A copy of all other filings in
reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with
385.2010.
Dated: July 10, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on July 24, 2019.
[FR Doc. 2019–15062 Filed 7–15–19; 8:45 am]
Dated: July 10, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
BILLING CODE 6717–01–P
[FR Doc. 2019–15064 Filed 7–15–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Federal Energy Regulatory
Commission
[Docket No. EF19–4–000]
jspears on DSK30JT082PROD with NOTICES
Western Area Power Administration;
Notice of Filing
Take notice that on June 24, 2019,
Western Area Power Administration
submitted tariff filing per: Extension of
Formula Rates for the Central Valley
Project, California-Oregon Transmission
Project, Pacific Alternating Current
Intertie, and Third-Party Transmission
Service—Rate Order No. WAPA–185 to
be effective October 1, 2019.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
VerDate Sep<11>2014
17:33 Jul 15, 2019
Jkt 247001
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER18–734–001.
Applicants: Frenchtown III Solar,
LLC.
Description: Report Filing:
Frenchtown III Refund Report to be
effective N/A.
Filed Date: 7/10/19.
Accession Number: 20190710–5050.
Comments Due: 5 p.m. ET 7/31/19.
Docket Numbers: ER18–1226–001.
Applicants: PA Solar Park, LLC.
Description: Report Filing: PA Solar
Park Refund Report to be effective N/A.
Filed Date: 7/10/19.
Accession Number: 20190710–5049.
Comments Due: 5 p.m. ET 7/31/19.
Docket Numbers: ER18–2063–001.
Applicants: Flemington Solar, LLC.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
33931
Description: Report Filing:
Flemington Solar Refund Report to be
effective N/A.
Filed Date: 7/10/19.
Accession Number: 20190710–5052.
Comments Due: 5 p.m. ET 7/31/19.
Docket Numbers: ER19–1916–001.
Applicants: Louisville Gas and
Electric Company.
Description: Compliance filing: Order
No. 845 Additional Information
Compliance Filing to be effective 5/22/
2019.
Filed Date: 7/10/19.
Accession Number: 20190710–5087.
Comments Due: 5 p.m. ET 7/31/19.
Docket Numbers: ER19–2165–001.
Applicants: Western Interconnect
LLC.
Description: Compliance filing:
Amendment to Order 845 Compliance
Filing to be effective 5/22/2019.
Filed Date: 7/10/19.
Accession Number: 20190710–5063.
Comments Due: 5 p.m. ET 7/31/19.
Docket Numbers: ER19–2231–001.
Applicants: Chief Conemaugh Power
II, LLC.
Description: Tariff Amendment:
Supplement to Petition for MarketBased Rate Authorization to be effective
8/21/2019.
Filed Date: 7/10/19.
Accession Number: 20190710–5089.
Comments Due: 5 p.m. ET 7/31/19.
Docket Numbers: ER19–2232–001.
Applicants: Chief Keystone Power II,
LLC.
Description: Tariff Amendment:
Supplement to Petition for MarketBased Rate Authorization to be effective
8/21/2019.
Filed Date: 7/10/19.
Accession Number: 20190710–5092.
Comments Due: 5 p.m. ET 7/31/19.
Docket Numbers: ER19–2369–000.
Applicants: Indigo Generation LLC.
Description: § 205(d) Rate Filing:
Revised Market Based Rate Tariff to be
effective 7/11/2019.
Filed Date: 7/10/19.
Accession Number: 20190710–5028.
Comments Due: 5 p.m. ET 7/31/19.
Docket Numbers: ER19–2370–000.
Applicants: Larkspur Energy LLC.
Description: § 205(d) Rate Filing:
Revised Market Based Rate Tariff to be
effective 7/11/2019.
Filed Date: 7/10/19.
Accession Number: 20190710–5029.
Comments Due: 5 p.m. ET 7/31/19.
Docket Numbers: ER19–2371–000.
Applicants: Mariposa Energy, LLC.
Description: § 205(d) Rate Filing:
Revised Market Based Rate Tariff to be
effective 7/11/2019.
Filed Date: 7/10/19.
E:\FR\FM\16JYN1.SGM
16JYN1
Agencies
[Federal Register Volume 84, Number 136 (Tuesday, July 16, 2019)]
[Notices]
[Pages 33930-33931]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-15062]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 8315-014]
Eagle Creek Sartell Hydro, LLC; Notice of Application Accepted
for Filing, Soliciting Comments, Motions To Intervene, and Protests
July 10, 2019.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Request for temporary variance of Article
34.
b. Project No.: 8315-014.
c. Date Filed: July 9, 2019.
d. Applicant: Eagle Creek Sartell Hydro, LLC.
e. Name of Project: Sartell Dam Hydro Project.
f. Location: Mississippi River in Stearns and Benton counties,
Minnesota.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Ms. Melissa Rondou, Eagle Creek Sartell
Hydro, LLC, 116 N State Street, P.O. Box 167, Neshkoro, WI 54960, (920)
293-4628 ext. 347, [email protected].
i. FERC Contact: Mr. Jeremy Jessup, (202) 502-6779,
[email protected].
j. Deadline for filing comments, motions to intervene, and
protests, is 15 days from the issuance date of this notice by the
Commission. The Commission strongly encourages electronic filing.
Please file comments, motions to intervene, and protests using the
Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://www.ferc.gov/doc-sfiling/ecomment.asp. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE,
Washington, DC 20426. The first page of any filing should include
docket numbers P-8315-014.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. Description of Request: The applicant requests a temporary
variance from the run-of-river and reservoir elevation requirements of
Article 34 of the license. The variance will allow the licensee to
drawdown the reservoir approximately three feet beginning August 1,
2019, for a six-week period (from August 1 through approximately
September 15, 2019). The drawdown is to assist the Minnesota Department
of Natural Resources, the Little Rock Lake Association, and the Benton
Soil and Water Conservation District to facilitate water quality, fish
habitat, and restoration improvements in the reach of the Mississippi
River upstream of the project, and at Little Rock Lake, located
approximately six miles upstream of the project.
l. Locations of the Application: A copy of the application is
available for inspection and reproduction at the Commission's Public
Reference Room, located at 888 First Street NE, Room 2A, Washington, DC
20426, or by calling (202) 502-8371. This filing may also be viewed on
the Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number excluding the last three digits
in the docket number field to access the document. You may also
register online at https://www.ferc.gov/docs-filing/esubscription.asp to
be notified via email of new filings and issuances related to this or
other pending projects. For assistance, call 1-866-208- 3676 or email
[email protected], for TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
(h) above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Motions to Intervene, or Protests: Anyone may submit
comments, a motion to intervene, or a protest in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all
[[Page 33931]]
protests or other comments filed, but only those who file a motion to
intervene in accordance with the Commission's Rules may become a party
to the proceeding. Any comments, motions to intervene, or protests must
be received on or before the specified comment date for the particular
application.
o. Filing and Service of Responsive Documents: Any filing must (1)
bear in all capital letters the title ``COMMENTS'', ``MOTION TO
INTERVENE'', or ``PROTEST'' as applicable; (2) set forth in the heading
the name of the applicant and the project number(s) of the application
to which the filing responds; (3) furnish the name, address, and
telephone number of the person intervening or protesting; and (4)
otherwise comply with the requirements of 18 CFR 385.2001 through
385.2005. All comments, motions to intervene, or protests must set
forth their evidentiary basis. A copy of all other filings in reference
to this application must be accompanied by proof of service on all
persons listed in the service list prepared by the Commission in this
proceeding, in accordance with 385.2010.
Dated: July 10, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-15062 Filed 7-15-19; 8:45 am]