Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 33768-33769 [2019-14928]

Download as PDF khammond on DSKBBV9HB2PROD with NOTICES 33768 Federal Register / Vol. 84, No. 135 / Monday, July 15, 2019 / Notices County Line in Citrus County, Florida. This interconnect will provide Duke Energy Florida, Inc. (DEF), an existing shipper on the Sabal Trail system, with additional operational flexibility and reliability (FGT Citrus County Meter Station Project), all as more fully set forth in the application, which is open to the public for inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Specifically, Sabal Trail proposes to construct, own, and operate a new M&R Facility at milepost (MP) 18.42 on its Citrus County Line. The Project is designed to connect Sabal Trail’s Citrus County Line with FGT’s 30-inch and 36inch diameter pipelines located at FGT’s MP 81.6 to provide DEF with an additional source of natural gas. Any questions regarding this application should be directed to P. Martin Teague, Associate General Counsel, 2701 North Rocky Point Drive, Suite 1050, Tampa, FL 33607, or call (813) 282–6605, or by email: marty.teague@enbridge.com. Any person or the Commission’s staff may, within 60 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to Section 157.205 of the regulations under the NGA (18 CFR 157.205), a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the allowed time for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding, or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the VerDate Sep<11>2014 16:08 Jul 12, 2019 Jkt 247001 EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission’s environmental mailing list, and will be notified of any meetings associated with the Commission’s environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenter will not receive copies of all documents filed by other parties or issued by the Commission and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 3 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Dated: July 9, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–14926 Filed 7–12–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [ECOsponsible, LLC, Project No. 14987– 000] Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On April 18, 2019, ECOsponsible, LLC, filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of hydropower on the Oneida River in Onondaga and Oswego Counties, New York. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 application during the permit term. A preliminary permit does not authorize the permit holder to perform any landdisturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Caughdenoy Lock Hydro Project would consist of the following: (1) An existing 15-foot-high, 550-foot-long flood control dam (i.e., the Caughdenoy Dam) and an associated impoundment; (2) three turbines for a total installed capacity of 3,000 kilowatts to be installed on the Oneida Canal; (3) a new 50-foot-long transmission line from the powerhouse to an existing grid interconnection point; and (4) appurtenant facilities. The proposed project would have an average annual generation of 13,446 megawatthours. Applicant Contact: Dennis Ryan, ECOsponsible, LLC, PO Box 114, West Falls, NY 14170; phone: (716) 222–2188. FERC Contact: Monir Chowdhury; phone: (202) 502–6736. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. The Commission strongly encourages electronic filing. Please file comments, motions to intervene, notices of intent, and competing applications using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–14987–000. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s website at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–14987) in the docket number field to access the document. For assistance, contact FERC Online Support. E:\FR\FM\15JYN1.SGM 15JYN1 Federal Register / Vol. 84, No. 135 / Monday, July 15, 2019 / Notices Dated: July 9, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–14928 Filed 7–12–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: khammond on DSKBBV9HB2PROD with NOTICES Filings Instituting Proceedings Docket Numbers: RP19–419–003. Applicants: Tuscarora Gas Transmission Company. Description: Compliance filing Compliance to RP19–419 Phase II Rates to be effective 8/1/2019. Filed Date: 6/28/19. Accession Number: 20190628–5061. Comments Due: 5 p.m. ET 7/11/19. Docket Numbers: RP19–1045–001. Applicants: Cheniere Creole Trail Pipeline, L.P. Description: Request for Temporary Waiver and Extension of Time to Implement NAESB 3.1 Standards Per Order No. 587–Y of Cheniere Creole Trail Pipeline, L.P. under RP19–1045. Filed Date: 7/1/19. Accession Number: 20190701–5418. Comments Due: 5 p.m. ET 7/15/19. Docket Numbers: RP19–206–005. Applicants: Mississippi Canyon Gas Pipeline, L.L.C. Description: Compliance filing MCGP RP19–206 Compliance Filing to be effective 8/1/2019. Filed Date: 7/2/19. Accession Number: 20190702–5146. Comments Due: 5 p.m. ET 7/15/19. Docket Numbers: RP19–73–002. Applicants: El Paso Natural Gas Company, L.L.C. Description: Compliance filing FERC Form No. 501–G Settlement Implementation Filing to be effective 1/1/2019. Filed Date: 7/2/19. Accession Number: 20190702–5116. Comments Due: 5 p.m. ET 7/15/19. Docket Numbers: RP19–1375–000. Applicants: Texas Eastern Transmission, LP. Description: § 4(d) Rate Filing: July 2019 Name Change Cleanup Filing to be effective 8/5/2019. Filed Date: 7/5/19. Accession Number: 20190705–5101. Comments Due: 5 p.m. ET 7/17/19. Docket Numbers: RP19–1376–000. VerDate Sep<11>2014 16:08 Jul 12, 2019 Jkt 247001 Applicants: Texas Eastern Transmission, LP. Description: § 4(d) Rate Filing: Negotiated Rates—July 2019 Cleanup Filing to be effective 8/5/2019. Filed Date: 7/5/19. Accession Number: 20190705–5104. Comments Due: 5 p.m. ET 7/17/19. Docket Numbers: RP19–1377–000. Applicants: Algonquin Gas Transmission, LLC. Description: § 4(d) Rate Filing: Negotiated Rates—July 2019 Cleanup Filing to be effective 8/5/2019. Filed Date: 7/5/19. Accession Number: 20190705–5106. Comments Due: 5 p.m. ET 7/17/19. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: July 9, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–14925 Filed 7–12–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2042–191] Public Utility District No. 1 of Pend Oreille County, Washington; Notice of Application for Amendment of License, and Soliciting Comments, Motions To Intervene, and Protests Take notice that the following application has been filed with the Commission and is available for public inspection: a. Application Type: Request for Amendment of License. b. Project No.: 2042–191. c. Date Filed: June 10, 2019. d. Applicant: Public Utility District No. 1 of Pend Oreille County, Washington. PO 00000 Frm 00037 Fmt 4703 Sfmt 4703 33769 e. Name of Project: Box Canyon Hydroelectric Project. f. Location: The project is located on the Pend Oreille River in northeastern Washington and northwestern Idaho. The project occupies federal lands, including acreage within the Colville National Forest and the Kalispel Indian Reservation. g. Filed Pursuant to: The application for amendment of license was filed pursuant to 18 CFR 385.602 and 4.201. h. Applicant Contact: Tyler Whitney, General Counsel and Director of Regulatory & Government Affairs, Public Utility District No. 1 of Pend Oreille County, P.O. Box 190, 130 N Washington, Newport, Washington 99156, (509) 447–9331, twhitney@ popud.org; Craig Gannett, Davis Wright Tremaine LLP, 1201 Third Ave., Suite 2200, Seattle, WA 98101, (206) 757– 8048, craiggannett@dwt.com; and Walker Stanovsky, Davis Wright Tremaine LLP, 1201 Third Ave., Suite 2200, Seattle, WA 98101, (206) 757– 8259, walkerstanovsky@dwt.com. i. FERC Contact: Holly Frank, telephone: (202) 502–6833, and email address: holly.frank@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests is 30 days from the issuance date of this notice by the Commission. The Commission strongly encourages electronic filing. Please file motions to intervene, protests, comments, or recommendations using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–2042–191. k. Description of Request: On February 19, 2010, the Commission approved a license amendment to include revised conditions submitted by the Department of the Interior (Interior) and the U.S. Forest Service pursuant to section 4(e) of the Federal Power Act (FPA) and the fish passage measures prescribed by Interior pursuant to FPA section 18. Since then, the PUD has been implementing the terms of the amended license, with administrative changes to the sequence and schedule of E:\FR\FM\15JYN1.SGM 15JYN1

Agencies

[Federal Register Volume 84, Number 135 (Monday, July 15, 2019)]
[Notices]
[Pages 33768-33769]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-14928]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[ECOsponsible, LLC, Project No. 14987-000]


Notice of Preliminary Permit Application Accepted for Filing and 
Soliciting Comments, Motions To Intervene, and Competing Applications

    On April 18, 2019, ECOsponsible, LLC, filed an application for a 
preliminary permit, pursuant to section 4(f) of the Federal Power Act 
(FPA), proposing to study the feasibility of hydropower on the Oneida 
River in Onondaga and Oswego Counties, New York. The sole purpose of a 
preliminary permit, if issued, is to grant the permit holder priority 
to file a license application during the permit term. A preliminary 
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by 
others without the owners' express permission.
    The proposed Caughdenoy Lock Hydro Project would consist of the 
following: (1) An existing 15-foot-high, 550-foot-long flood control 
dam (i.e., the Caughdenoy Dam) and an associated impoundment; (2) three 
turbines for a total installed capacity of 3,000 kilowatts to be 
installed on the Oneida Canal; (3) a new 50-foot-long transmission line 
from the powerhouse to an existing grid interconnection point; and (4) 
appurtenant facilities. The proposed project would have an average 
annual generation of 13,446 megawatt-hours.
    Applicant Contact: Dennis Ryan, ECOsponsible, LLC, PO Box 114, West 
Falls, NY 14170; phone: (716) 222-2188.
    FERC Contact: Monir Chowdhury; phone: (202) 502-6736.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-14987-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of the 
Commission's website at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14987) in the docket number field to access 
the document. For assistance, contact FERC Online Support.


[[Page 33769]]


    Dated: July 9, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-14928 Filed 7-12-19; 8:45 am]
 BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.