Federal Register / Vol. 84, No. 104 / Thursday, May 30, 2019 / Notices
• Email: nsfscqis@nsf.gov. Email
submissions should be machinereadable and not be copyright-protected.
Submissions should include ‘‘RFI
Response: National Strategic Overview
for Quantum Information Science’’ in
the subject line of the message.
• Direct input to the website: https://
www.surveymonkey.com/r/QIS-RFI_
Responses.
Instructions: Response to this RFI is
voluntary. Each individual or institution
is requested to submit only one
response. Submissions must not exceed
the equivalent of one page for each
question, or eight pages total, in 12
point or larger font, with a page number
provided on each page. Responses
should include the name of the
person(s) or organization(s) filing the
comment.
Responses to this RFI may be posted
online as discussions proceed.
Therefore, we request that no business
proprietary information, copyrighted
information, or personally identifiable
information be submitted in response to
this RFI.
In accordance with FAR 15.202(3),
responses to this notice are not offers
and cannot be accepted by the
Government for the purposes of forming
a binding contract. Responders are
solely responsible for all expenses
associated with responding to this RFI.
FOR FURTHER INFORMATION CONTACT: C.
Denise Caldwell at (703) 292–7371 or
nsfscqis@nsf.gov. Individuals who use a
telecommunications device for the deaf
(TDD) may call the Federal Information
Relay Service (FIRS) at 1–800–877–8339
between 8 a.m. and 8 p.m. (ET), Monday
through Friday for assistance.
SUPPLEMENTARY INFORMATION: The
National Science and Technology
Council’s Subcommittee on Quantum
Information Science released its
‘‘National Strategic Overview for
Quantum Information Science’’
(hereafter ‘‘Strategic Overview’’) in
September 2018. This document calls
upon agencies to develop plans to
address six identified key policy areas
to enable continued American
leadership in quantum information
science. On December 21, 2018, the
National Quantum Initiative Act was
signed into law to further the Nation’s
efforts in quantum information science.
Now the NSTC Subcommittee on
Quantum Information Science seeks
public input to inform the
Subcommittee as the Government
develops the means to address the
specific policy recommendations
included in the ‘‘Strategic Overview’’
and the overall goals of the National
Quantum Initiative Act. Responders are
VerDate Sep<11>2014
18:08 May 29, 2019
Jkt 247001
asked to answer one or more of the
following questions, consistent with the
prior published RFI:
1. What specific actions could the
U.S. Government take that would
contribute best to implementing the
policy recommendations in the Strategic
Overview? What challenges, not listed
in section 3, should also be taken into
account in implementation of the
Strategic Overview recommendations?
2. What are the scientific and
technological challenges that, with
substantial resources and focus over the
next ten years, will transform the QIS
research and development landscape?
3. Regarding industrial engagement,
what roles can the U.S. Government
play in enabling the innovation
ecosystem around QIS-related
technologies? Are there critical barriers
for industrial innovation in this space?
How can these barriers be addressed?
What role can the U.S. Government play
in mitigating early or premature
investment risks?
4. How can the U.S. Government
engage with academia and other
workforce development programs and
stakeholders to appropriately train and
maintain researchers in QIS while
expanding the size and scope of the
‘quantum-smart’ workforce?
5. What existing infrastructure should
be leveraged, and what new
infrastructure could be considered, to
foster future breakthroughs in QIS
research and development?
6. What other activities/partnerships
could the U.S. Government use to
engage with stakeholders to ensure
America’s prosperity and economic
growth through QIS research and
development?
7. How can the United States continue
to attract and retain the best domestic
and international talent and expertise in
QIS?
8. How can the United States ensure
that U.S. researchers in QIS have access
to cutting-edge international
technologies, research facilities, and
knowledge?
Reference: National Strategic
Overview for Quantum Information
Science, https://www.whitehouse.gov/
wp-content/uploads/2018/09/NationalStrategic-Overview-for-QuantumInformation-Science.pdf.
Submitted by the National Science
Foundation in support of the NSTC
Subcommittee on Quantum Information
Science on May 24, 2019.
Suzanne H. Plimpton,
Reports Clearance Officer, National Science
Foundation.
[FR Doc. 2019–11317 Filed 5–29–19; 8:45 am]
BILLING CODE 7555–01–P
PO 00000
Frm 00050
Fmt 4703
Sfmt 4703
25077
NUCLEAR REGULATORY
COMMISSION
[NRC–2016–0270 and NRC–2019–0086]
Guidance for Changes, Tests, and
Experiments
Nuclear Regulatory
Commission.
ACTION: Regulatory guide, issuance; draft
regulatory guide, request for comment.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing Revision 1
of regulatory guide (RG) 1.187,
‘‘Guidance for Implementation of 10
CFR 50.59, ‘Changes, Tests, and
Experiments.’ ’’ Concurrently the NRC is
issuing for public comment DG–1356,
which is proposed Revision 2 of RG
1.187.
SUMMARY:
Revision 1 to RG 1.187 is
available on May 30, 2019.
Submit comments on DG–1356 [NRC–
2019–0086] by July 15, 2019. Because of
the extensive communication about NEI
96–07 Appendix D over the past year,
the NRC believes that stakeholders will
be able to submit comments quickly. In
addition, the NRC seeks to issue DG–
1356 as expeditiously as possible.
Therefore, the NRC is publishing the
DG–1356 with a 45-day comment
period. Comments received after this
date will be considered if it is practical
to do so, but the NRC is able to ensure
consideration only for comments
received on or before this date.
Although a time limit is given,
comments and suggestions in
connection with items for inclusion in
guides currently being developed or
improvements in all published guides
are encouraged at any time.
ADDRESSES: Please refer to Docket ID
NRC–2016–0270 when contacting the
NRC about the availability of
information regarding RG 1.187,
Revision 1. You may obtain publiclyavailable information related to RG
1.187, Revision 1, by using any of the
following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for RG 1.187, Revision 1, by using
Docket ID NRC–2016–0270. Address
questions about NRC docket IDs in
regulations.gov to Jennifer Borges;
telephone: 301–287–9127; email:
Jennifer.Borges@nrc.gov. For technical
questions, contact the individual listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
DATES:
E:\FR\FM\30MYN1.SGM
30MYN1
25078
Federal Register / Vol. 84, No. 104 / Thursday, May 30, 2019 / Notices
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. Revision 1 to RG 1.187 and the
regulatory analysis may be found in
ADAMS under Accession Nos.
ML17195A655 and ML16089A379
respectively.
Please refer to Docket ID NRC–2019–
0086 when contacting the NRC about
DG–1356 (proposed RG 1.187, Revision
2). You may submit comments on DG–
1356 (ADAMS Accession No.
ML19045A435) by any of the following
methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID: NRC–2019–0086. Address
questions about NRC docket IDs in
regulations.gov to Jennifer Borges;
telephone: 301–287–9127; email:
Jennifer.Borges@nrc.gov. For technical
questions, contact the individuals listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• Mail comments to: Office of
Administration, Mail Stop: TWFN–
7A06, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001. ATTN: Program Management,
Announcements and Editing Staff.
For additional direction on obtaining
information and submitting comments,
see ‘‘Obtaining Information and
Submitting Comments’’ in the
SUPPLEMENTARY INFORMATION section of
this document.
Regulatory guides are not
copyrighted, and NRC approval is not
required to reproduce them.
FOR FURTHER INFORMATION CONTACT:
Philip McKenna, telephone: 301–415–
0037; email: Philip.McKenna@nrc.gov,
or Stephen Burton, telephone: 301–415–
0038; email: Stephen.Burton@nrc.gov.
Both are staff of the U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001.
SUPPLEMENTARY INFORMATION:
jbell on DSK3GLQ082PROD with NOTICES
I. Discussion
The NRC is issuing a revision to an
existing guide in the NRC’s ‘‘Regulatory
Guide’’ series. This series was
developed to describe, and make
available to the public, information
regarding methods that are acceptable to
the NRC staff for implementing specific
parts of the agency’s regulations,
techniques that the NRC staff uses in
evaluating specific issues or postulated
events, and data that the NRC staff
needs in its review of applications for
permits and licenses.
VerDate Sep<11>2014
18:08 May 29, 2019
Jkt 247001
The purpose of issuing the final RG
1.187, Revision 1, concurrent with
issuing DG–1356 for comment is to
provide clarity for, and coordination of,
NRC activities on guidance for
implementing section 50.59 of title 10 of
the Code of Federal Regulations (10
CFR).
Revision 1 of RG 1.187 was issued
with a temporary identification of Draft
Regulatory Guide, DG–1334. RG 1.187,
Revision 1, endorses, with clarifications,
Nuclear Energy Institute (NEI) 96–07,
‘‘Guidelines for 10 CFR 50.59
Evaluations,’’ which provides licensees
with a method that the staff considers
acceptable for use in complying with
the Commission’s regulations on the
process by which licensees, under
certain conditions, may make changes to
their facilities and procedures as
described in the final safety analysis
report (FSAR), and conduct tests or
experiments not described in the FSAR,
without prior NRC approval.
Concurrent with issuing Revision 1 of
RG 1.187, the NRC is issuing DG–1356
for public comment under NRC docket
number NRC–2019–0086. DG–1356
proposes additional guidance on digital
instrumentation and control
modifications. Specifically, DG–1356
endorses with exceptions and
clarifications, NEI 96–07, Appendix D,
Revision 0, ‘‘Supplemental Guidance for
Application of 10 CFR 50.59 to Digital
Modifications.’’ If finalized, DG–1356
would become RG 1.187, Revision 2.
II. Additional Information: RG 1.187,
Revision 1
The NRC published a notice of the
availability of DG–1334 in the Federal
Register on December 23, 2016 (81 FR
94275) for a 60-day public comment
period. The public comment period
closed on February 21, 2017. Public
comments on DG–1334 and the staff
responses to the public comments are
available in ADAMS under Accession
No. ML18123A363.
The NRC is issuing RG 1.187,
Revision 1, to implement lessonslearned from the NRC Report ‘‘Review
of Lessons Learned from the San Onofre
Steam Generator Tube Degradation
Event,’’ dated March 6, 2015. (ADAMS
Package Accession No. ML15062A125).
Specifically, RG 1.187, Revision 1,
clarifies statements in Section 4.3.8 of
NEI 96–07, Revision 1, regarding the
definition in 10 CFR 50.59(a)(2) of
‘‘departure from a method of evaluation
described in the FSAR (as updated).’’
Revision 1 also clarifies statements in
Section 4.3.5 of NEI 96–07, Revision 1,
regarding the meaning in 10 CFR
50.59(c)(2)(v) of ‘‘an accident of a
different type than any previously
PO 00000
Frm 00051
Fmt 4703
Sfmt 4703
evaluated in the final safety analysis
report (as updated).’’ This revision of
RG 1.187 explains how licensees should
apply these NEI guidelines to ensure
they are meeting the requirements of 10
CFR 50.59.
III. Additional Information: DG–1356
(Draft RG 1.187, Revision 2)
The NRC is issuing for public
comment a DG in the NRC’s ‘‘Regulatory
Guide’’ series. This series was
developed to describe and make
available to the public information
regarding methods that are acceptable to
the NRC staff for implementing specific
parts of the NRC’s regulations,
techniques that the staff uses in
evaluating specific issues or postulated
events, and data that the staff needs in
its review of applications for permits
and licenses.
The DG, titled, ‘‘Guidance for
Implementation of 10 CFR 50.59,
‘Changes, Tests, and Experiments,’ ’’
temporarily identified by its task
number, DG–1356, is proposed Revision
2 of RG 1.187. DG–1356 provides
guidance on complying with the
requirements of 10 CFR 50.59 when
performing a digital instrumentation
and controls (digital I&C) modification.
Specifically, Nuclear Energy Institute
(NEI) 96–07, Appendix D, Revision 0,
‘‘Supplemental Guidance for
Application of 10 CFR 50.59 to Digital
Modifications,’’ was submitted to the
NRC on November 30, 2018. As
discussed in Section C of RG 1.187, DG–
1356 endorses NEI 96–07 and finds that
it provides an acceptable approach for
the application of 10 CFR 50.59
guidance when conducting digital I&C
modifications, with certain exceptions
and clarifications.
DG–1356 is being issued for public
comment to facilitate the Commission’s
direction in the Staff Requirements
Memorandum (SRM)—SECY–16–0070,
‘‘Staff Requirements—SECY–16–0070—
Integrated Strategy to Modernize the
Nuclear Regulatory Commission’s
Digital Instrumentation and Control
Regulatory Infrastructure’’ (ADAMS
Accession No. ML16299A157). The NRC
staff has engaged the public, NEI, and
industry representatives to improve the
guidance for applying 10 CFR 50.59 to
digital I&C-related design modifications
as part of a broader effort to modernize
the regulatory infrastructure for digital
I&C.
IV. Congressional Review Act
RG 1.187, Revision 1, is a rule as
defined in the Congressional Review
Act (5 U.S.C. 801–808). However, the
Office of Management and Budget has
not found it to be a major rule as
E:\FR\FM\30MYN1.SGM
30MYN1
Federal Register / Vol. 84, No. 104 / Thursday, May 30, 2019 / Notices
For the Nuclear Regulatory Commission.
Thomas H. Boyce,
Chief, Regulatory Guidance and Generic
Issues Branch, Division of Engineering, Office
of Nuclear Regulatory Research.
defined in the Congressional Review
Act.
V. Backfitting and Issue Finality
Revision 1 of Regulatory Guide 1.187
[FR Doc. 2019–11246 Filed 5–29–19; 8:45 am]
Revision 1 of Regulatory Guide 1.187
clarifies statements in Section 4.3.8 and
4.3.5 of Nuclear Energy Institute (NEI)
96–07, Revision 1, ‘‘Guidelines for 10
CFR 50.59 Implementation’’
(ML003771157), which the NRC first
endorsed in RG 1.187, Rev 0
(ML003759710). Issuance of RG 1.187,
Revision 1, does not constitute
backfitting under § 50.109 and is not
otherwise inconsistent with issue
finality under 10 CFR part 52. As
discussed in the ‘‘Implementation’’
section of this RG, NRC staff does not
intend or approve any imposition or
backfitting of the guidance in this RG.
If, in the future, the NRC seeks to
impose a position in Revision 1 of RG
1.187 in a manner that does not provide
issue finality as described in an
applicable issue finality provision, then
the NRC must address the criteria for
avoiding issue finality as described in
the applicable issue finality provision.
jbell on DSK3GLQ082PROD with NOTICES
Draft Regulatory Guide DG–1356
Draft regulatory guide DG–1356, if
finalized as Regulatory Guide 1.187,
Revision 2, would endorse NEI 96–07,
Appendix D, with conditions and
clarifications. NEI 96–07, Appendix D,
and the NRC staff’s conditions and
clarifications, provide guidance on the
application of the 10 CFR 50.59 change
process to digital I&C modifications.
The draft regulatory guide, if finalized,
would not constitute backfitting as
defined in 10 CFR 50.109 (the Backfit
Rule) and is not otherwise inconsistent
with the issue finality provisions in 10
CFR part 52, ‘‘Licenses, Certifications
and Approvals for Nuclear Power
Plants.’’ As discussed in the
‘‘Implementation’’ section of this RG,
NRC staff does not intend or approve
any imposition or backfitting of the
guidance in this RG. If, in the future, the
NRC seeks to impose a position in
Revision 2 of RG 1.187 in a manner that
does not provide issue finality as
described in an applicable issue finality
provision, then the NRC must address
the criteria for avoiding issue finality as
described in the applicable issue finality
provision.
Dated at Rockville, Maryland, this 23rd day
of May, 2019.
VerDate Sep<11>2014
18:08 May 29, 2019
Jkt 247001
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–293; NRC–2019–0098]
Entergy Nuclear Operations, Inc.;
Pilgrim Nuclear Power Station
Nuclear Regulatory
Commission.
ACTION: Exemption; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) has issued a partial
exemption in response to a February 8,
2019, request from Entergy Nuclear
Operations, Inc. (the licensee or
Entergy). The issuance of the exemption
would grant Entergy a partial exemption
from regulations that require the
retention of records for certain systems,
structures, and components associated
with the Pilgrim Nuclear Power Station
(Pilgrim) until the termination of the
Pilgrim operating license.
DATES: The exemption was issued on
May 21, 2019.
ADDRESSES: Please refer to Docket ID
NRC–2019–0098 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2019–0098. Address
questions about NRC dockets IDs in
Regulations.gov to Jennifer Borges;
telephone: 301–287–9127; email:
Jennifer.Borges@nrc.gov. For technical
questions, contact the individual listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. The ADAMS accession number
for each document referenced (if it is
available in ADAMS) is provided the
first time that it is mentioned in this
document.
SUMMARY:
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
25079
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Scott P. Wall, Office of Nuclear Reactor
Regulation; U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001; telephone: 301–415–2855; email:
Scott.Wall@nrc.gov.
SUPPLEMENTARY INFORMATION: The text of
the exemption is attached.
Dated at Rockville, Maryland, this 24th day
of May 2019.
For the Nuclear Regulatory Commission.
John G. Lamb,
Senior Project Manager, Special Projects and
Process Branch, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
NUCLEAR REGULATORY
COMMISSION
Docket No. 50-293
Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station
Exemption
I. Background
The Pilgrim Nuclear Power Station
(Pilgrim) is a single-unit facility located
in the town of Plymouth, Plymouth
County, in the Commonwealth of
Massachusetts. It is situated on the
western coast of Cape Cod Bay, on
approximately 1,600 acres of land. The
Pilgrim facility employs a General
Electric boiling-water reactor nuclear
steam supply system licensed to
generate 2,028 megawatts-thermal. The
boiling-water reactor and supporting
facilities are owned and operated by the
Entergy Nuclear Operations, Inc.
(Entergy, the licensee). Entergy is the
holder of the Pilgrim Renewed Facility
Operating License No. DPR-35. The
license provides, among other things,
that the facility is subject to all rules,
regulations, and orders of the U.S.
Nuclear Regulatory Commission (NRC,
the Commission) now or hereafter in
effect.
By letter dated November 10, 2015
(Agencywide Documents Access and
Management System (ADAMS)
Accession No. ML15328A053), Entergy
submitted a notification to the NRC
indicating that it would permanently
shut down Pilgrim no later than June 1,
2019. Once Entergy certifies that it has
permanently defueled the Pilgrim
reactor vessel and placed the fuel in the
spent fuel pool (SFP), accordingly,
pursuant to § 50.82(a)(2) of Title 10 of
the Code of Federal Regulations (10
CFR), the Pilgrim renewed facility
E:\FR\FM\30MYN1.SGM
30MYN1
Agencies
[Federal Register Volume 84, Number 104 (Thursday, May 30, 2019)]
[Notices]
[Pages 25077-25079]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-11246]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2016-0270 and NRC-2019-0086]
Guidance for Changes, Tests, and Experiments
AGENCY: Nuclear Regulatory Commission.
ACTION: Regulatory guide, issuance; draft regulatory guide, request for
comment.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing
Revision 1 of regulatory guide (RG) 1.187, ``Guidance for
Implementation of 10 CFR 50.59, `Changes, Tests, and Experiments.' ''
Concurrently the NRC is issuing for public comment DG-1356, which is
proposed Revision 2 of RG 1.187.
DATES: Revision 1 to RG 1.187 is available on May 30, 2019.
Submit comments on DG-1356 [NRC-2019-0086] by July 15, 2019.
Because of the extensive communication about NEI 96-07 Appendix D over
the past year, the NRC believes that stakeholders will be able to
submit comments quickly. In addition, the NRC seeks to issue DG-1356 as
expeditiously as possible. Therefore, the NRC is publishing the DG-1356
with a 45-day comment period. Comments received after this date will be
considered if it is practical to do so, but the NRC is able to ensure
consideration only for comments received on or before this date.
Although a time limit is given, comments and suggestions in connection
with items for inclusion in guides currently being developed or
improvements in all published guides are encouraged at any time.
ADDRESSES: Please refer to Docket ID NRC-2016-0270 when contacting the
NRC about the availability of information regarding RG 1.187, Revision
1. You may obtain publicly-available information related to RG 1.187,
Revision 1, by using any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for RG 1.187, Revision 1, by using
Docket ID NRC-2016-0270. Address questions about NRC docket IDs in
regulations.gov to Jennifer Borges; telephone: 301-287-9127; email:
[email protected]. For technical questions, contact the
individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at
[[Page 25078]]
https://www.nrc.gov/reading-rm/adams.html. To begin the search, select
``Begin Web-based ADAMS Search.'' For problems with ADAMS, please
contact the NRC's Public Document Room (PDR) reference staff at 1-800-
397-4209, 301-415-4737, or by email to [email protected]. Revision 1
to RG 1.187 and the regulatory analysis may be found in ADAMS under
Accession Nos. ML17195A655 and ML16089A379 respectively.
Please refer to Docket ID NRC-2019-0086 when contacting the NRC
about DG-1356 (proposed RG 1.187, Revision 2). You may submit comments
on DG-1356 (ADAMS Accession No. ML19045A435) by any of the following
methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID: NRC-2019-0086. Address
questions about NRC docket IDs in regulations.gov to Jennifer Borges;
telephone: 301-287-9127; email: [email protected]. For technical
questions, contact the individuals listed in the FOR FURTHER
INFORMATION CONTACT section of this document.
Mail comments to: Office of Administration, Mail Stop:
TWFN-7A06, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001. ATTN: Program Management, Announcements and Editing Staff.
For additional direction on obtaining information and submitting
comments, see ``Obtaining Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
Regulatory guides are not copyrighted, and NRC approval is not
required to reproduce them.
FOR FURTHER INFORMATION CONTACT: Philip McKenna, telephone: 301-415-
0037; email: [email protected], or Stephen Burton, telephone: 301-
415-0038; email: [email protected]. Both are staff of the U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001.
SUPPLEMENTARY INFORMATION:
I. Discussion
The NRC is issuing a revision to an existing guide in the NRC's
``Regulatory Guide'' series. This series was developed to describe, and
make available to the public, information regarding methods that are
acceptable to the NRC staff for implementing specific parts of the
agency's regulations, techniques that the NRC staff uses in evaluating
specific issues or postulated events, and data that the NRC staff needs
in its review of applications for permits and licenses.
The purpose of issuing the final RG 1.187, Revision 1, concurrent
with issuing DG-1356 for comment is to provide clarity for, and
coordination of, NRC activities on guidance for implementing section
50.59 of title 10 of the Code of Federal Regulations (10 CFR).
Revision 1 of RG 1.187 was issued with a temporary identification
of Draft Regulatory Guide, DG-1334. RG 1.187, Revision 1, endorses,
with clarifications, Nuclear Energy Institute (NEI) 96-07, ``Guidelines
for 10 CFR 50.59 Evaluations,'' which provides licensees with a method
that the staff considers acceptable for use in complying with the
Commission's regulations on the process by which licensees, under
certain conditions, may make changes to their facilities and procedures
as described in the final safety analysis report (FSAR), and conduct
tests or experiments not described in the FSAR, without prior NRC
approval.
Concurrent with issuing Revision 1 of RG 1.187, the NRC is issuing
DG-1356 for public comment under NRC docket number NRC-2019-0086. DG-
1356 proposes additional guidance on digital instrumentation and
control modifications. Specifically, DG-1356 endorses with exceptions
and clarifications, NEI 96-07, Appendix D, Revision 0, ``Supplemental
Guidance for Application of 10 CFR 50.59 to Digital Modifications.'' If
finalized, DG-1356 would become RG 1.187, Revision 2.
II. Additional Information: RG 1.187, Revision 1
The NRC published a notice of the availability of DG-1334 in the
Federal Register on December 23, 2016 (81 FR 94275) for a 60-day public
comment period. The public comment period closed on February 21, 2017.
Public comments on DG-1334 and the staff responses to the public
comments are available in ADAMS under Accession No. ML18123A363.
The NRC is issuing RG 1.187, Revision 1, to implement lessons-
learned from the NRC Report ``Review of Lessons Learned from the San
Onofre Steam Generator Tube Degradation Event,'' dated March 6, 2015.
(ADAMS Package Accession No. ML15062A125).
Specifically, RG 1.187, Revision 1, clarifies statements in Section
4.3.8 of NEI 96-07, Revision 1, regarding the definition in 10 CFR
50.59(a)(2) of ``departure from a method of evaluation described in the
FSAR (as updated).'' Revision 1 also clarifies statements in Section
4.3.5 of NEI 96-07, Revision 1, regarding the meaning in 10 CFR
50.59(c)(2)(v) of ``an accident of a different type than any previously
evaluated in the final safety analysis report (as updated).'' This
revision of RG 1.187 explains how licensees should apply these NEI
guidelines to ensure they are meeting the requirements of 10 CFR 50.59.
III. Additional Information: DG-1356 (Draft RG 1.187, Revision 2)
The NRC is issuing for public comment a DG in the NRC's
``Regulatory Guide'' series. This series was developed to describe and
make available to the public information regarding methods that are
acceptable to the NRC staff for implementing specific parts of the
NRC's regulations, techniques that the staff uses in evaluating
specific issues or postulated events, and data that the staff needs in
its review of applications for permits and licenses.
The DG, titled, ``Guidance for Implementation of 10 CFR 50.59,
`Changes, Tests, and Experiments,' '' temporarily identified by its
task number, DG-1356, is proposed Revision 2 of RG 1.187. DG-1356
provides guidance on complying with the requirements of 10 CFR 50.59
when performing a digital instrumentation and controls (digital I&C)
modification. Specifically, Nuclear Energy Institute (NEI) 96-07,
Appendix D, Revision 0, ``Supplemental Guidance for Application of 10
CFR 50.59 to Digital Modifications,'' was submitted to the NRC on
November 30, 2018. As discussed in Section C of RG 1.187, DG-1356
endorses NEI 96-07 and finds that it provides an acceptable approach
for the application of 10 CFR 50.59 guidance when conducting digital
I&C modifications, with certain exceptions and clarifications.
DG-1356 is being issued for public comment to facilitate the
Commission's direction in the Staff Requirements Memorandum (SRM)--
SECY-16-0070, ``Staff Requirements--SECY-16-0070--Integrated Strategy
to Modernize the Nuclear Regulatory Commission's Digital
Instrumentation and Control Regulatory Infrastructure'' (ADAMS
Accession No. ML16299A157). The NRC staff has engaged the public, NEI,
and industry representatives to improve the guidance for applying 10
CFR 50.59 to digital I&C-related design modifications as part of a
broader effort to modernize the regulatory infrastructure for digital
I&C.
IV. Congressional Review Act
RG 1.187, Revision 1, is a rule as defined in the Congressional
Review Act (5 U.S.C. 801-808). However, the Office of Management and
Budget has not found it to be a major rule as
[[Page 25079]]
defined in the Congressional Review Act.
V. Backfitting and Issue Finality
Revision 1 of Regulatory Guide 1.187
Revision 1 of Regulatory Guide 1.187 clarifies statements in
Section 4.3.8 and 4.3.5 of Nuclear Energy Institute (NEI) 96-07,
Revision 1, ``Guidelines for 10 CFR 50.59 Implementation''
(ML003771157), which the NRC first endorsed in RG 1.187, Rev 0
(ML003759710). Issuance of RG 1.187, Revision 1, does not constitute
backfitting under Sec. 50.109 and is not otherwise inconsistent with
issue finality under 10 CFR part 52. As discussed in the
``Implementation'' section of this RG, NRC staff does not intend or
approve any imposition or backfitting of the guidance in this RG. If,
in the future, the NRC seeks to impose a position in Revision 1 of RG
1.187 in a manner that does not provide issue finality as described in
an applicable issue finality provision, then the NRC must address the
criteria for avoiding issue finality as described in the applicable
issue finality provision.
Draft Regulatory Guide DG-1356
Draft regulatory guide DG-1356, if finalized as Regulatory Guide
1.187, Revision 2, would endorse NEI 96-07, Appendix D, with conditions
and clarifications. NEI 96-07, Appendix D, and the NRC staff's
conditions and clarifications, provide guidance on the application of
the 10 CFR 50.59 change process to digital I&C modifications. The draft
regulatory guide, if finalized, would not constitute backfitting as
defined in 10 CFR 50.109 (the Backfit Rule) and is not otherwise
inconsistent with the issue finality provisions in 10 CFR part 52,
``Licenses, Certifications and Approvals for Nuclear Power Plants.'' As
discussed in the ``Implementation'' section of this RG, NRC staff does
not intend or approve any imposition or backfitting of the guidance in
this RG. If, in the future, the NRC seeks to impose a position in
Revision 2 of RG 1.187 in a manner that does not provide issue finality
as described in an applicable issue finality provision, then the NRC
must address the criteria for avoiding issue finality as described in
the applicable issue finality provision.
Dated at Rockville, Maryland, this 23rd day of May, 2019.
For the Nuclear Regulatory Commission.
Thomas H. Boyce,
Chief, Regulatory Guidance and Generic Issues Branch, Division of
Engineering, Office of Nuclear Regulatory Research.
[FR Doc. 2019-11246 Filed 5-29-19; 8:45 am]