Federal Register / Vol. 84, No. 96 / Friday, May 17, 2019 / Notices
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov.
FOR FURTHER INFORMATION CONTACT: Mr.
George Wunder, Office of the New
Reactors, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001; telephone 301–415–1494 or email
at George.Wunder@nrc.gov.
SUPPLEMENTARY INFORMATION: On
November 3, 2009, as noticed in the
Federal Register (74 FR 58323), the staff
issued its Final Interim Staff Guidance,
DC/COL–ISG–10, ‘‘Review of Evaluation
to Address Adverse Flow Effects in
Equipment Other than Reactor
Internals’’ (ADAMS Accession No.
ML092890285). This document is being
withdrawn because on March 6, 2017,
the staff issued Revision 4 to Sections
3.9.2 and 3.9.5 of NUREG–0800
(ADAMS Accession No. ML16133A418),
incorporating the guidance of DC/COL–
ISG–10 and, therefore, superseding it.
Therefore, as of the date of this notice,
DC/COL–ISG–10 is withdrawn.
Dated at Rockville, Maryland, this 14th day
of May 2019.
For the Nuclear Regulatory Commission.
Jennivine K. Rankin,
Acting Chief, Licensing Branch 3, Division
of Licensing, Siting, and Environmental
Analysis, Office of New Reactors.
[FR Doc. 2019–10316 Filed 5–16–19; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2008–0089]
Final Interim Staff Guidance DC/COL–
ISG–03: Probabilistic Risk Assessment
Information To Support Design
Certification and Combined License
Applications
Nuclear Regulatory
Commission.
ACTION: Interim staff guidance;
withdrawal.
jbell on DSK3GLQ082PROD with NOTICES
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is withdrawing its
Final Interim Staff Guidance (ISG) DC/
COL–ISG–03, ‘‘Probabilistic Risk
Assessment Information to Support
Design Certification and Combined
SUMMARY:
VerDate Sep<11>2014
17:05 May 16, 2019
Jkt 247001
License Applications.’’ This ISG served
to supplement the guidance provided to
the staff in Section 19.0, ‘‘Probabilistic
Risk Assessment and Severe Accident
Evaluation for New Reactors,’’ of
NUREG–0800, ‘‘Standard Review Plan
for the Review of Safety Analysis
Reports for Nuclear Power Plants: LWR
Edition,’’ concerning the review of
probabilistic risk assessment
information and severe accident
assessment submitted to support design
certification (DC) and combined license
(COL) applications. The NRC staff issues
ISG to facilitate timely implementation
of current staff guidance and to facilitate
activities associated with review of
applications for DC and COLs by the
Office of New Reactors. The NRC staff
incorporated the approved DC/COL–ISG
into Revision 3 to Section 19.0 of
NUREG–0800 dated December 2015.
With the issuance of Revision 3 to
Section 19.0 of NUREG–0800, the staff
has determined that DC/COL–ISG–03 is
no longer necessary and should be
withdrawn.
DATES: The date of the withdrawal of
Final Interim Staff Guidance DC/COL–
ISG–03 is May 17, 2019.
ADDRESSES: Please refer to Docket ID:
NRC–2008–0089 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2008–0089. Address
questions about Docket IDs in
Regulations.gov to Jennifer Borges;
telephone: 301–287–9221; email:
Jennifer.Borges@nrc.gov. For technical
questions, contact the individual listed
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov.
FOR FURTHER INFORMATION CONTACT: Mr.
George Wunder, Office of the New
Reactors, U.S. Nuclear Regulatory
Commission, Washington, DC, 20555–
0001; telephone 301–415–1494 or email
at George.Wunder@nrc.gov.
SUPPLEMENTARY INFORMATION: On June
11, 2008, as noticed in the Federal
PO 00000
Frm 00094
Fmt 4703
Sfmt 4703
22523
Register (73 FR 34347), the staff issued
Final Interim Staff Guidance (ISG) DC/
COL–ISG–03, ‘‘Probabilistic Risk
Assessment Information to Support
Design Certification and Combined
License Applications’’ (ADAMS
Accession No. ML081430047). This
document is being withdrawn because
on January 21, 2016, the staff issued
Revision 3 to Section 19.0 of NUREG–
0800 incorporating the guidance of DC/
COL–ISG–03 (ADAMS Accession No.
ML15085A093) and, therefore,
superseding it. Therefore, as of the date
of this notice, DC/COL–ISG–03 is
withdrawn.
Dated at Rockville, Maryland, this 14th day
of May 2019.
For the Nuclear Regulatory Commission.
Jennivine K. Rankin,
Acting Branch Chief, Licensing Branch 3,
Division of Licensing, Siting, and
Environmental Analysis, Office of New
Reactors.
[FR Doc. 2019–10319 Filed 5–16–19; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 52–047; NRC–2016–0119]
Tennessee Valley Authority; Clinch
River Nuclear Site
Nuclear Regulatory
Commission.
ACTION: Early site permit application;
receipt.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is giving notice once
each week for four consecutive weeks
for an application from Tennessee
Valley Authority (TVA), for an early site
permit (ESP) for the Clinch River
Nuclear Site located in Oak Ridge,
Tennessee.
SUMMARY:
The ESP application was
received on May 12, 2016 and
supplemented with Revision 2 on
January 18, 2019.
ADDRESSES: Please refer to Docket ID
NRC–2016–0119 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2016–0119. Address
questions about NRC docket IDs in
Regulations.gov to Jennifer Borges;
telephone: 301–287–9127; email:
Jennifer.Borges@nrc.gov. For technical
questions, contact the individuals listed
DATES:
E:\FR\FM\17MYN1.SGM
17MYN1
22524
Federal Register / Vol. 84, No. 96 / Friday, May 17, 2019 / Notices
jbell on DSK3GLQ082PROD with NOTICES
in the FOR FURTHER INFORMATION
CONTACT section of this document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. The ADAMS accession number
for each document referenced (if it is
available in ADAMS) is provided the
first time that it is mentioned in this
document. For the convenience of the
reader, instructions about obtaining
materials referenced in this document
are provided in the ‘‘Availability of
Documents’’ section of this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Mallecia Sutton, telephone: 301–415–
0673, email: Mallecia.Sutton@nrc.gov or
Allen Fetter, telephone: 301–415–8556,
email: Allen.Fetter@nrc.gov. Both staff
of the U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001.
SUPPLEMENTARY INFORMATION:
I. Background
TVA (the applicant) has filed an
application for an ESP for the Clinch
River Nuclear Site located in Oak Ridge,
Tennessee (ADAMS Accession No.
ML16139A752), under Section 103 of
the Atomic Energy Act of 1954, as
amended, and part 52 of title 10 of the
Code of Federal Regulations (10 CFR),
‘‘Licenses, Certifications, and Approvals
for Nuclear Power Plants.’’ TVA filed
Revision 2 of the application dated
January 18, 2019 (ADAMS Accession
No. ML19030A485). Through the
application, which is currently under
review by the NRC staff, the applicant
seeks an ESP separate from the filing of
an application for a construction permit
(CP) or combined license (COL) for a
nuclear power facility. The ESP process
allows resolution of issues relating to
siting. At any time during the period of
an ESP (up to 20 years), the permit
holder may reference the permit in an
application for a CP or COL. The
information submitted by the applicant
includes certain administrative
information, as well as technical
information submitted pursuant to 10
CFR 52.24(a) and 10 CFR 51.105(a).
VerDate Sep<11>2014
17:05 May 16, 2019
Jkt 247001
These notices are being provided in
accordance with the requirements in 10
CFR 50.43(a)(3).
II. Availability of Documents
The documents identified in the
following table are available to
interested persons through one or more
of the following methods, as indicated.
ADAMS
accession
No.
Document
ESP application Cover Letter
ESP application Administrative Information.
ESP application Site Safety
Analysis Report.
ESP application Environmental Report.
ESP application Emergency
Plan.
ESP application Exemptions
and Departures.
ESP application Enclosures ..
ML19030A485
ML18003A298
ML19030A358
ML19030A478
ML18003A485
ML19030A479
ML19030A568
Dated at Rockville, Maryland, this 13th day
of May, 2019.
For the Nuclear Regulatory Commission.
Jennivine K. Rankin,
Acting Chief, Licensing Branch 3, Division
of New Reactor Licensing, Office of New
Reactors.
[FR Doc. 2019–10127 Filed 5–16–19; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2019–0036]
Information Collection: NRC Form 313,
‘‘Application for Materials License’’ and
NRC Forms 313A (RSO), 313A (AMP),
313A (ANP), 313A (AUD), 313A (AUT),
and 313A (AUS)’’
Nuclear Regulatory
Commission.
ACTION: Notice of submission to the
Office of Management and Budget;
request for comment.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) has recently
submitted a request for renewal of an
existing collection of information to the
Office of Management and Budget
(OMB) for review. The information
collection is entitled, ‘‘NRC Form 313,
‘Application for Materials License’ and
NRC Forms 313A (RSO), 313A (AMP),
313A (ANP), 313A (AUD), 313A (AUT),
and 313A (AUS)’’.
DATES: Submit comments by June 17,
2019. Comments received after this date
will be considered if it is practical to do
so, but the Commission is able to ensure
SUMMARY:
PO 00000
Frm 00095
Fmt 4703
Sfmt 4703
consideration only for comments
received before this date.
ADDRESSES: Submit comments directly
to the OMB reviewer at: OMB Office of
Information and Regulatory Affairs
(3150–0120), Attn: Desk Officer for the
Nuclear Regulatory Commission, 725
17th Street NW, Washington, DC 20503;
email: oira_submission@omb.eop.gov.
FOR FURTHER INFORMATION CONTACT:
David Cullison, NRC Clearance Officer,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–2084; email:
INFOCOLLECTS.Resource@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and
Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC–2019–
0036 when contacting the NRC about
the availability of information for this
action. You may obtain publiclyavailable information related to this
action by any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2019–0036.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘ADAMS Public Documents’’ and then
select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
• NRC’s Clearance Officer: A copy of
the collection of information and related
instructions may be obtained without
charge by contacting the NRC’s
Clearance Officer, David Cullison,
Office of the Chief Information Officer,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–2084; email:
INFOCOLLECTS.Resource@NRC.GOV.
B. Submitting Comments
The NRC cautions you not to include
identifying or contact information in
comment submissions that you do not
want to be publicly disclosed in your
comment submission. All comment
submissions are posted at https://
www.regulations.gov and entered into
ADAMS. Comment submissions are not
E:\FR\FM\17MYN1.SGM
17MYN1
Agencies
[Federal Register Volume 84, Number 96 (Friday, May 17, 2019)]
[Notices]
[Pages 22523-22524]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-10127]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 52-047; NRC-2016-0119]
Tennessee Valley Authority; Clinch River Nuclear Site
AGENCY: Nuclear Regulatory Commission.
ACTION: Early site permit application; receipt.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is giving notice
once each week for four consecutive weeks for an application from
Tennessee Valley Authority (TVA), for an early site permit (ESP) for
the Clinch River Nuclear Site located in Oak Ridge, Tennessee.
DATES: The ESP application was received on May 12, 2016 and
supplemented with Revision 2 on January 18, 2019.
ADDRESSES: Please refer to Docket ID NRC-2016-0119 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC-2016-0119. Address
questions about NRC docket IDs in Regulations.gov to Jennifer Borges;
telephone: 301-287-9127; email: [email protected]. For technical
questions, contact the individuals listed
[[Page 22524]]
in the FOR FURTHER INFORMATION CONTACT section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or
by email to [email protected]. The ADAMS accession number for each
document referenced (if it is available in ADAMS) is provided the first
time that it is mentioned in this document. For the convenience of the
reader, instructions about obtaining materials referenced in this
document are provided in the ``Availability of Documents'' section of
this document.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Mallecia Sutton, telephone: 301-415-
0673, email: [email protected] or Allen Fetter, telephone: 301-
415-8556, email: [email protected]. Both staff of the U.S. Nuclear
Regulatory Commission, Washington, DC 20555-0001.
SUPPLEMENTARY INFORMATION:
I. Background
TVA (the applicant) has filed an application for an ESP for the
Clinch River Nuclear Site located in Oak Ridge, Tennessee (ADAMS
Accession No. ML16139A752), under Section 103 of the Atomic Energy Act
of 1954, as amended, and part 52 of title 10 of the Code of Federal
Regulations (10 CFR), ``Licenses, Certifications, and Approvals for
Nuclear Power Plants.'' TVA filed Revision 2 of the application dated
January 18, 2019 (ADAMS Accession No. ML19030A485). Through the
application, which is currently under review by the NRC staff, the
applicant seeks an ESP separate from the filing of an application for a
construction permit (CP) or combined license (COL) for a nuclear power
facility. The ESP process allows resolution of issues relating to
siting. At any time during the period of an ESP (up to 20 years), the
permit holder may reference the permit in an application for a CP or
COL. The information submitted by the applicant includes certain
administrative information, as well as technical information submitted
pursuant to 10 CFR 52.24(a) and 10 CFR 51.105(a). These notices are
being provided in accordance with the requirements in 10 CFR
50.43(a)(3).
II. Availability of Documents
The documents identified in the following table are available to
interested persons through one or more of the following methods, as
indicated.
------------------------------------------------------------------------
Document ADAMS accession No.
------------------------------------------------------------------------
ESP application Cover Letter.............. ML19030A485
ESP application Administrative Information ML18003A298
ESP application Site Safety Analysis ML19030A358
Report.
ESP application Environmental Report...... ML19030A478
ESP application Emergency Plan............ ML18003A485
ESP application Exemptions and Departures. ML19030A479
ESP application Enclosures................ ML19030A568
------------------------------------------------------------------------
Dated at Rockville, Maryland, this 13th day of May, 2019.
For the Nuclear Regulatory Commission.
Jennivine K. Rankin,
Acting Chief, Licensing Branch 3, Division of New Reactor Licensing,
Office of New Reactors.
[FR Doc. 2019-10127 Filed 5-16-19; 8:45 am]
BILLING CODE 7590-01-P