Great River Hydro, LLC; Notice of Authorization for Continued Project Operation, 21767 [2019-10048]
Download as PDF
Federal Register / Vol. 84, No. 94 / Wednesday, May 15, 2019 / Notices
This notice sets a deadline of 120
days from the date of this notice for
interested applicants, other than the
existing licensee, to file NOIs, PADs,
and requests to use the traditional
licensing process or alternative
procedures. A potential applicant that
timely files an NOI and PAD must file
an application for a subsequent license
no later than 18 months after the date
on which it filed its NOI.7
Questions concerning this notice
should be directed to Ryan Hansen at
(202) 502–8074 or ryan.hansen@
ferc.gov.
Dated: May 3, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–09977 Filed 5–14–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1904–000]
jbell on DSK3GLQ082PROD with NOTICES
Great River Hydro, LLC; Notice of
Authorization for Continued Project
Operation
On October 31, 2012 Great River
Hydro, LLC, licensee for the Vernon
Hydroelectric Project, filed an
Application for a New License pursuant
to the Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Vernon Hydroelectric Project is
located on the Connecticut River in
Orange and Windsor counties, Vermont,
and Grafton County, New Hampshire.
The license for Project No. 1904 was
issued for a period ending April 30,
2019. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
7 18
CFR 16.25(b)(1) (2018).
VerDate Sep<11>2014
22:43 May 14, 2019
Jkt 247001
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 1904
is issued to the licensee for a period
effective May1, 2019 through April 30,
2020, or until the issuance of a new
license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before April 30, 2020, notice
is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under
section 15(a)(1) of the FPA is renewed
automatically without further order or
notice by the Commission, unless the
Commission orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the licensee, Great River Hydro,
LLC, is authorized to continue operation
of the Vernon Hydroelectric Project
until such time as the Commission acts
on its application for a subsequent
license.
Dated: May 9, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–10048 Filed 5–14–19; 8:45 am]
BILLING CODE 6717–01–P
21767
Filed Date: 5/7/19.
Accession Number: 201905075127.
Comments/Protests Due: 5 p.m. ET
5/28/19.
Docket Numbers: RP19–1216–000.
Applicants: Texas Eastern
Transmission, LP.
Description: § 4(d) Rate Filing:
Negotiated Rates—May 2019 Cleanup
Filing to be effective 6/7/2019.
Filed Date: 5/8/19.
Accession Number: 20190508–5000.
Comments Due: 5 p.m. ET 5/20/19.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: May 9, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–10046 Filed 5–14–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
Combined Notice of Filings
Federal Energy Regulatory
Commission
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Number: PR19–59–000.
Applicants: Columbia Gas of Ohio,
Inc.
Description: Tariff filing per
284.123(b),(e)/: COH Rates effective May
1, 2019 to be effective 5/1/2019.
Filed Date: 5/7/19.
Accession Number: 201905075067.
Comments/Protests Due: 5 p.m. ET
5/28/19.
Docket Number: PR19–60–000.
Applicants: ONEOK WesTex
Transmission, L.L.C.
Description: Tariff filing per
284.123(b),(e)/: OWT PR16–11–003
–004 Compliance Filing to be effective
5/1/2019.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
[Project No. 1892–000]
Great River Hydro, LLC; Notice of
Authorization for Continued Project
Operation
On October 31, 2012 Great River
Hydro, LLC, licensee for the Wilder
Hydroelectric Project, filed an
Application for a New License pursuant
to the Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Wilder Hydroelectric Project is
located on the Connecticut River in
Orange and Windsor counties, Vermont,
and Grafton County, New Hampshire.
The license for Project No. 1892 was
issued for a period ending April 30,
2019. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
E:\FR\FM\15MYN1.SGM
15MYN1
Agencies
[Federal Register Volume 84, Number 94 (Wednesday, May 15, 2019)]
[Notices]
[Page 21767]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-10048]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 1904-000]
Great River Hydro, LLC; Notice of Authorization for Continued
Project Operation
On October 31, 2012 Great River Hydro, LLC, licensee for the Vernon
Hydroelectric Project, filed an Application for a New License pursuant
to the Federal Power Act (FPA) and the Commission's regulations
thereunder. The Vernon Hydroelectric Project is located on the
Connecticut River in Orange and Windsor counties, Vermont, and Grafton
County, New Hampshire.
The license for Project No. 1904 was issued for a period ending
April 30, 2019. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 1904 is issued to
the licensee for a period effective May1, 2019 through April 30, 2020,
or until the issuance of a new license for the project or other
disposition under the FPA, whichever comes first. If issuance of a new
license (or other disposition) does not take place on or before April
30, 2020, notice is hereby given that, pursuant to 18 CFR 16.18(c), an
annual license under section 15(a)(1) of the FPA is renewed
automatically without further order or notice by the Commission, unless
the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that the licensee, Great River Hydro, LLC, is authorized
to continue operation of the Vernon Hydroelectric Project until such
time as the Commission acts on its application for a subsequent
license.
Dated: May 9, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-10048 Filed 5-14-19; 8:45 am]