Great River Hydro, LLC; Notice of Authorization for Continued Project Operation, 21770-21771 [2019-10043]
Download as PDF
jbell on DSK3GLQ082PROD with NOTICES
21770
Federal Register / Vol. 84, No. 94 / Wednesday, May 15, 2019 / Notices
Applicants: Mitsui Bussan
Commodities, Ltd.
Description: Compliance filing:
Application for Market Based Rate to be
effective 8/19/2019.
Filed Date: 5/8/19.
Accession Number: 20190508–5111.
Comments Due: 5 p.m. ET 5/29/19.
Docket Numbers: ER19–1807–000.
Applicants: PacifiCorp.
Description: Tariff Cancellation:
Termination of Invenergy Solar E&P
Agreement to be effective 7/29/2019.
Filed Date: 5/8/19.
Accession Number: 20190508–5112.
Comments Due: 5 p.m. ET 5/29/19.
Docket Numbers: ER19–1808–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
American Electric Power Service
Corporation.
Description: § 205(d) Rate Filing:
2019–05–09_Rate Schedule 53_Duke
IMTCo Revenue Distribution Agreement
to be effective 6/1/2019.
Filed Date: 5/9/19.
Accession Number: 20190509–5019.
Comments Due: 5 p.m. ET 5/30/19.
Docket Numbers: ER19–1809–000.
Applicants: Southwestern Electric
Power Company.
Description: § 205(d) Rate Filing:
SWEPCO-Bentonville POD#8 DPA
Cancellation to be effective 5/1/2019.
Filed Date: 5/9/19.
Accession Number: 20190509–5034.
Comments Due: 5 p.m. ET 5/30/19.
Docket Numbers: ER19–1810–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, SA No. 5361; Queue No.
AB2–099 to be effective 4/9/2019.
Filed Date: 5/9/19.
Accession Number: 20190509–5050.
Comments Due: 5 p.m. ET 5/30/19.
Docket Numbers: ER19–1811–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing: GIA
Tulare Solar 5 Project SA No. 1079 to
be effective 5/10/2019.
Filed Date: 5/9/19.
Accession Number: 20190509–5051.
Comments Due: 5 p.m. ET 5/30/19.
Docket Numbers: ER19–1812–000.
Applicants: CED Wistaria Solar, LLC.
Description: § 205(d) Rate Filing:
Filing of a Certificate of Concurrence to
be effective 5/8/2019.
Filed Date: 5/9/19.
Accession Number: 20190509–5052.
Comments Due: 5 p.m. ET 5/30/19.
Docket Numbers: ER19–1813–000.
Applicants: CED Wistaria Solar, LLC.
Description: § 205(d) Rate Filing:
Filing of a Certificate of Concurrence to
be effective 5/8/2019.
VerDate Sep<11>2014
22:43 May 14, 2019
Jkt 247001
Filed Date: 5/9/19.
Accession Number: 20190509–5079.
Comments Due: 5 p.m. ET 5/30/19.
Docket Numbers: ER19–1814–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA SA No. 5359; Queue No.
AB1–141/AB1–142 to be effective 4/9/
2019.
Filed Date: 5/9/19.
Accession Number: 20190509–5081.
Comments Due: 5 p.m. ET 5/30/19.
Docket Numbers: ER19–1815–000.
Applicants: Southern California
Edison Company.
Description: Tariff Cancellation:
Cancel Letter Agmt Southern California
Renewable Partners—Vision Wind
Project to be effective 3/21/2019.
Filed Date: 5/9/19.
Accession Number: 20190509–5083.
Comments Due: 5 p.m. ET 5/30/19.
Docket Numbers: ER19–1816–000.
Applicants: Pacific Gas and Electric
Company.
Description: § 205(d) Rate Filing: TO
Tariff Revision to Formula Capital
Structure Calculation to be effective
7/8/2019.
Filed Date: 5/9/19.
Accession Number: 20190509–5084.
Comments Due: 5 p.m. ET 5/30/19.
Docket Numbers: ER19–1817–000.
Applicants: Virginia Electric and
Power Company.
Description: Compliance filing:
Informational Filing—Amend PPA with
Birchwood Power Partners, L.P. to be
effective N/A.
Filed Date: 5/9/19.
Accession Number: 20190509–5105.
Comments Due: 5 p.m. ET 5/30/19.
Take notice that the Commission
received the following electric securities
filings:
Docket Numbers: ES19–29–000.
Applicants: Golden Spread Electric
Cooperative, Inc.
Description: Application under
Section 204 of the Federal Power Act for
Continue Authorization to Issue
Securities of Golden Spread Electric
Cooperative, Inc.
Filed Date: 5/9/19.
Accession Number: 20190509–5056.
Comments Due: 5 p.m. ET 5/30/19.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: May 9, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–10045 Filed 5–14–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1855–000]
Great River Hydro, LLC; Notice of
Authorization for Continued Project
Operation
On October 31, 2012 Great River
Hydro, LLC, licensee for the Bellows
Falls Hydroelectric Project, filed an
Application for a New License pursuant
to the Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Bellows Falls Hydroelectric Project
is located on the Connecticut River in
Windham County, VT and Cheshire
County, NH.
The license for Project No. 1855 was
issued for a period ending April 30,
2019. Section 15(a) (1) of the FPA, 16
U.S.C. 808(a) (1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
E:\FR\FM\15MYN1.SGM
15MYN1
Federal Register / Vol. 84, No. 94 / Wednesday, May 15, 2019 / Notices
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 1855
is issued to the licensee for a period
effective May1, 2019 through April 30,
2020, or until the issuance of a new
license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before April 30, 2020, notice
is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under
section 15(a)(1) of the FPA is renewed
automatically without further order or
notice by the Commission, unless the
Commission orders otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the licensee, Great River Hydro,
LLC, is authorized to continue operation
of the Bellows Falls Hydroelectric
Project until such time as the
Commission acts on its application for
a subsequent license.
Dated: May 9, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–10043 Filed 5–14–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Western Area Power Administration
Falcon and Amistad Projects—Rate
Order No. WAPA–186
Western Area Power
Administration, DOE.
ACTION: Notice of rate order extending
firm power formula rate.
AGENCY:
The Under Secretary of
Energy approves, on an interim basis,
the extension of the existing Falcon and
Amistad Projects’ (Projects) firm power
formula rate through June 7, 2024 and
will submit them to the Federal Energy
Regulatory Commission (FERC) for
confirmation and approval on a final
basis. The existing firm power formula
rate is set to expire June 7, 2019. This
rate extension makes no change to the
existing formula rate.
DATES: The firm power formula rate will
be placed into effect on an interim basis
June 8, 2019.
FOR FURTHER INFORMATION CONTACT: Mr.
Steven R. Johnson, Colorado River
Storage Project (CRSP) Manager, CRSP
Management Center, Western Area
Power Administration, 299 South Main
Street, Suite 200, Salt Lake City, UT
84111; (970) 252–3000; email johnsons@
jbell on DSK3GLQ082PROD with NOTICES
SUMMARY:
VerDate Sep<11>2014
22:43 May 14, 2019
Jkt 247001
wapa.gov, or Mr. Thomas Hackett, Rates
Manager, CRSP Management Center,
(801) 524–5503 or email hackett@
wapa.gov.
SUPPLEMENTARY INFORMATION: By
Delegation Order No. 00–037.00B,
effective November 19, 2016, the
Secretary of Energy delegated: (1) The
authority to develop power and
transmission rates to Western Area
Power Administration’s (WAPA)
Administrator; (2) the authority to
confirm, approve, and place such rates
into effect on an interim basis to the
Deputy Secretary of Energy; and (3) the
authority to confirm, approve, and place
into effect on a final basis, or to remand
or disapprove such rates, to FERC. In
Delegation Order No. 00–002.00Q,
effective November 1, 2018, the
Secretary of Energy also delegated to the
Under Secretary of Energy the authority
to confirm, approve, and place into
effect on an interim basis power and
transmission rates for WAPA. This
extension is issued in accordance with
the Delegation Order and DOE rate
extension procedures at 10 CFR
903.23(a).
The Falcon and Amistad Dams are
features of international water storage
projects located on the Rio Grande
between Texas and Mexico. Under the
terms of Contract No. 7–07–50–P0890,
dated August 9, 1977, as amended
(Contract), WAPA markets the power
from these dams to South Texas Electric
Cooperative, Inc. (STEC). The firm
power formula rate for the Projects was
approved by the Federal Power
Commission, predecessor of FERC, in
Docket No. E–9566 on August 12, 1977
(59 FPC 1653), for a 5-year period
effective on the date of initial operation
of Amistad Power Plant, June 8, 1983.1
WAPA calculates the annual
installment to be paid by STEC for the
power generated at the Falcon and
Amistad power plants on or before
August 31 of the year preceding the
fiscal year to which it pertains, and
identifies this amount in a rate
schedule. WAPA uses each annual
installment to pay the annual amortized
portion of the United States’ investment
in the Falcon and Amistad hydroelectric
facilities, with interest, and the
associated operation, maintenance, and
administrative costs. This repayment
schedule is not dependent upon the
power and energy made available for
sale or the rate of generation each year.
STEC, as the sole customer that takes
1 FERC subsequently approved multiple 5-year
rate extensions of the same formula rate, most
recently on April 9, 2015, in Docket No. EF14–9–
000, which extended the rate through June 7, 2019
(151 FERC ¶ 62,027).
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
21771
service from the Projects, submitted a
letter in support of this rate extension.
Following DOE’s review of WAPA’s
proposal,2 I hereby approve Rate Order
No. WAPA–186 on an interim basis,
which extends, without adjustment, the
Projects’ firm power formula rate
through June 7, 2024. Rate Order No.
WAPA–186 will be submitted to FERC
for confirmation and approval on a final
basis.
Dated: May 8, 2019.
Mark W. Menezes,
Under Secretary of Energy.
DEPARTMENT OF ENERGY
UNDER SECRETARY
In the matter of: Western Area Power
Administration Extension for Falcon and
Amistad Projects’ Firm Power Formula Rate)
Rate Order No. WAPA–186
ORDER CONFIRMING, APPROVING,
AND PLACING THE FALCON AND
AMISTAD PROJECTS’ FIRM POWER
FORMULA RATE INTO EFFECT ON
AN INTERIM BASIS
This Rate Order extends a firm power
formula rate. The extension is
undertaken pursuant to section 302 of
the Department of Energy (DOE)
Organization Act (42 U.S.C. 7152),
which transferred to, and vested in, the
Secretary of Energy the power marketing
functions of the Secretary of the Interior
and the Bureau of Reclamation, under
the Reclamation Act of 1902 (ch. 1093,
32 Stat. 388), as amended and
supplemented by subsequent laws,
particularly section 9(c) of the
Reclamation Project Act of 1939 (43
U.S.C. 485h(c)), and specifically
includes ‘‘the transmission and
disposition of the electric power and
energy generated at Falcon Dam and
Amistad Dam, international storage
reservoir projects on the Rio Grande,
pursuant to the Act of June 18, 1954, as
amended by the Act of December 23,
1963.’’
By Delegation Order No. 00–037.00B,
effective November 19, 2016, the
Secretary of Energy delegated: (1) the
authority to develop power and
transmission rates to the Administrator
of the Western Area Power
Administration (WAPA); (2) the
authority to confirm, approve, and place
into effect such rates on an interim basis
to the Deputy Secretary of Energy; and
(3) the authority to confirm, approve,
and place into effect on a final basis, or
to remand or disapprove such rates, to
the Federal Energy Regulatory
2 WAPA’s proposal was published on December
26, 2018 (83 FR 66,257).
E:\FR\FM\15MYN1.SGM
15MYN1
Agencies
[Federal Register Volume 84, Number 94 (Wednesday, May 15, 2019)]
[Notices]
[Pages 21770-21771]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-10043]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 1855-000]
Great River Hydro, LLC; Notice of Authorization for Continued
Project Operation
On October 31, 2012 Great River Hydro, LLC, licensee for the
Bellows Falls Hydroelectric Project, filed an Application for a New
License pursuant to the Federal Power Act (FPA) and the Commission's
regulations thereunder. The Bellows Falls Hydroelectric Project is
located on the Connecticut River in Windham County, VT and Cheshire
County, NH.
The license for Project No. 1855 was issued for a period ending
April 30, 2019. Section 15(a) (1) of the FPA, 16 U.S.C. 808(a) (1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the
[[Page 21771]]
Commission issues someone else a license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 1855 is issued to
the licensee for a period effective May1, 2019 through April 30, 2020,
or until the issuance of a new license for the project or other
disposition under the FPA, whichever comes first. If issuance of a new
license (or other disposition) does not take place on or before April
30, 2020, notice is hereby given that, pursuant to 18 CFR 16.18(c), an
annual license under section 15(a)(1) of the FPA is renewed
automatically without further order or notice by the Commission, unless
the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that the licensee, Great River Hydro, LLC, is authorized
to continue operation of the Bellows Falls Hydroelectric Project until
such time as the Commission acts on its application for a subsequent
license.
Dated: May 9, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-10043 Filed 5-14-19; 8:45 am]
BILLING CODE 6717-01-P