Combined Notice of Filings #1, 20873-20875 [2019-09718]

Download as PDF Federal Register / Vol. 84, No. 92 / Monday, May 13, 2019 / Notices Filed Date: 5/1/19. Accession Number: 20190501–5445. Comments Due: 5 p.m. ET 5/22/19. Docket Number: PR19–58–000. Applicants: Bayonne Energy Center, LLC. Description: Tariff filing per 284.224/ .123: Baseline Refiling to be effective 10/1/2019. Filed Date: 5/1/19. Accession Number: 201905015318. Comments/Protests Due: 5 p.m. ET 5/22/19. Docket Numbers: RP19–1185–000. Applicants: Alliance Pipeline L.P. Description: Operational Purchases and Sales Report of Alliance Pipeline L.P. under RP19–1185. Filed Date: 4/30/19. Accession Number: 20190430–5451. Comments Due: 5 p.m. ET 5/13/19. Docket Numbers: RP19–423–001. Applicants: Tallgrass Interstate Gas Transmission, LLC. Description: Pre-Arranged/Pre-Agreed (Petition for Approval of Settlement) Filing, et al. of Tallgrass Interstate Gas Transmission, LLC under RP19–423. Filed Date: 5/1/19. Accession Number: 20190501–5451. Comments Due: 5 p.m. ET 5/13/19. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified date(s). Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: May 6, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–09772 Filed 5–10–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Jkt 247001 1 Ares EIF Management, LLC, Competitive Power Ventures, Inc., Invenergy Thermal Development LLC, J–POWER USA Development Co., Ltd., Panda Power Generation Infrastructure Fund, LLC, Tenaska, Inc., Vistra Energy Corp. PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 (collectively Petitioners), filed a petition for a declaratory order regarding proposed revenue requirements and cost-based rates for merchant generators providing reactive power service to the PJM Interconnection, L.L.C. market, as more fully explained in the petition. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Petitioner. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 5 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the website that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern time on June 3, 2019. Dated: May 3, 2019. Kimberly D. Bose, Secretary. Take notice that on May 3, 2019, pursuant to Rule 207 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.207 (2017), Indicated Generation Owners 1 DEPARTMENT OF ENERGY jbell on DSK3GLQ082PROD with NOTICES Dated: May 7, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. Indicated Generation Owners; Notice of Petition for Declaratory Order BILLING CODE 6717–01–P 16:29 May 10, 2019 Docket Numbers: RP19–1213–000. Applicants: Total Peaking Services, L.L.C. Description: Compliance filing TPS Order No. 587–Y Compliance Filing Changes to be effective 8/1/2019. Filed Date: 5/6/19. Accession Number: 20190506–5137. Comments Due: 5 p.m. ET 5/20/19. Docket Numbers: RP19–257–003. Applicants: Southwest Gas Storage Company. Description: Compliance filing SWG Cost and Revenue Study in Compliance. Filed Date: 5/6/19. Accession Number: 20190506–5061. Comments Due: 5 p.m. ET 5/20/19. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. [Docket No. EL19–70–000] [FR Doc. 2019–09714 Filed 5–10–19; 8:45 am] VerDate Sep<11>2014 Filings Instituting Proceedings 20873 [FR Doc. 2019–09708 Filed 5–10–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC19–84–000. E:\FR\FM\13MYN1.SGM 13MYN1 jbell on DSK3GLQ082PROD with NOTICES 20874 Federal Register / Vol. 84, No. 92 / Monday, May 13, 2019 / Notices Applicants: Oregon Trail Wind Park, LLC, Payne’s Ferry Wind Park, LLC, Pilgrim Stage Station Wind Park, LLC, Yahoo Creek Wind Park, LLC. Description: Application for Authorization Under Section 203 of the Federal Power Act, et al. of Oregon Trail Wind Park, LLC, et al. Filed Date: 5/2/19. Accession Number: 20190502–5140. Comments Due: 5 p.m. ET 5/23/19. Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG19–95–000. Applicants: Glen Ullin Energy Center, LLC. Description: Self-Certification of EG or FC of Glen Ullin Energy Center, LLC. Filed Date: 5/3/19. Accession Number: 20190503–5112. Comments Due: 5 p.m. ET 5/24/19. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–2718–032; ER10–2719–032. Applicants: Cogen Technologies Linden Venture, L.P., East Coast Power Linden Holding, L.L.C. Description: Supplement to November 26, 2018 Notice of Non-Material Change in Status of Cogen Technologies Linden Venture, L.P., et al. Filed Date: 5/3/19. Accession Number: 20190503–5084. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER17–1531–003. Applicants: CPV Fairview, LLC. Description: Supplement to January 17, 2019 Notice of Change in Status of CPV Fairview, LLC. Filed Date: 5/3/19. Accession Number: 20190503–5100. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1153–001. Applicants: California Independent System Operator Corporation. Description: Tariff Amendment: 2019–05–03 Deficiency Filing InverterBased Interconnection Requirements to be effective 4/30/2019. Filed Date: 5/3/19. Accession Number: 20190503–5081. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1339–001. Applicants: Duke Energy Progress, LLC. Description: Tariff Amendment: Clarifying Amendment to Recovery of Storm Rates and Reqt for Expedited Action to be effective 5/15/2019. Filed Date: 5/3/19. Accession Number: 20190503–5066. Comments Due: 5 p.m. ET 5/10/19. Docket Numbers: ER19–1374–001. Applicants: Midcontinent Independent System Operator, Inc. VerDate Sep<11>2014 16:29 May 10, 2019 Jkt 247001 Description: Tariff Amendment: 2019–05–02_SA 3271 BondurantMontezuma 345kV Structure Replacement Sub MPFCA to be effective 3/20/2019. Filed Date: 5/2/19. Accession Number: 20190502–5095. Comments Due: 5 p.m. ET 5/13/19. Docket Numbers: ER19–1375–001. Applicants: Midcontinent Independent System Operator, Inc.. Description: Tariff Amendment: 2019–05–03_SA 3273 150 Mvar Cap Bank at Blackhawk 345kV Sub MPFCA to be effective 3/20/2019. Filed Date: 5/3/19. Accession Number: 20190503–5036. Comments Due: 5 p.m. ET 5/13/19. Docket Numbers: ER19–1378–001. Applicants: Midcontinent Independent System Operator, Inc. Description: Tariff Amendment: 2019–05–03_SA 3274 1x50 Mvar Cap Bank at Midport 161 kV MPFCA Sub to be effective 3/20/2019. Filed Date: 5/3/19. Accession Number: 20190503–5096. Comments Due: 5 p.m. ET 5/13/19. Docket Numbers: ER19–1639–001. Applicants: South Peak Wind LLC. Description: Tariff Amendment: Amendment to market-based rate application to be effective 6/21/2019. Filed Date: 5/3/19. Accession Number: 20190503–5042. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1771–000. Applicants: GridLiance Heartland LLC. Description: Limited Revisions to Attachment O Formula Rate Template and Implementation Protocols of GridLiance Heartland LLC.. Filed Date: 5/2/19. Accession Number: 20190502–5139. Comments Due: 5 p.m. ET 5/23/19. Docket Numbers: ER19–1772–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Amendment to ISA, Service Agreement No. 4121, Queue No. NQ113 to be effective 2/25/2019. Filed Date: 5/3/19. Accession Number: 20190503–5041. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1773–000. Applicants: Alabama Power Company. Description: § 205(d) Rate Filing: Three Rocks Solar (Evergreen Solar) LGIA Filing to be effective 4/22/2019. Filed Date: 5/3/19. Accession Number: 20190503–5043. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1774–000. Applicants: Alabama Power Company. PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 Description: § 205(d) Rate Filing: Turkey Run LGIA Filing to be effective 4/22/2019. Filed Date: 5/3/19. Accession Number: 20190503–5044. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1775–000. Applicants: Southern California Edison Company. Description: § 205(d) Rate Filing: SCE Recollation of TO Tariff Filing 2b of 3 to be effective 5/1/2019. Filed Date: 5/3/19. Accession Number: 20190503–5048. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1776–000. Applicants: Southern California Edison Company. Description: Tariff Cancellation: Notice of Cancellation GIA & DSA Dwight ES 1 Project SA Nos. 1055–1056 to be effective 4/29/2019. Filed Date: 5/3/19. Accession Number: 20190503–5062. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1777–000. Applicants: Midwest Energy, Inc. Description: Petition for Temporary Waiver of Midwest Energy, Inc. Filed Date: 5/3/19. Accession Number: 20190503–5063. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1778–000. Applicants: Glen Ullin Energy Center, LLC. Description: Baseline eTariff Filing: Market-Based Rate Application to be effective 5/6/2019. Filed Date: 5/3/19. Accession Number: 20190503–5092. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1779–000. Applicants: Midcontinent Independent System Operator, Inc. Description: § 205(d) Rate Filing: 2019–05–03_SA 1632 ITC MidwestOsceola Windpower 3rd Rev GIA (G426 G538) to be effective 4/19/2019. Filed Date: 5/3/19. Accession Number: 20190503–5094. Comments Due: 5 p.m. ET 5/24/19. Docket Numbers: ER19–1780–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 3550 WAPA & City of Moorhead MN Interconnection Agreement to be effective 5/2/2019. Filed Date: 5/3/19. Accession Number: 20190503–5114. Comments Due: 5 p.m. ET 5/24/19. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings E:\FR\FM\13MYN1.SGM 13MYN1 Federal Register / Vol. 84, No. 92 / Monday, May 13, 2019 / Notices must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: May 3, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–09718 Filed 5–10–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP19–218–000] jbell on DSK3GLQ082PROD with NOTICES Equitrans, L.P.; Notice of Request Under Blanket Authorization Take notice that on April 24, 2019, Equitrans, L.P., 2200 Energy Drive Canonsburg, PA 15317, filed a prior notice application pursuant to sections 157.205, 157.208(c), and 157.216(b) of the Federal Energy Regulatory Commission’s (Commission) regulations under the Natural Gas Act (NGA), and Equitrans blanket certificate issued in Docket No. CP96–532–000. Equitrans requests authorization to abandon and replace two segments of its TP–4555 pipeline (Bare Pipe Replacement Project), one of the pipelines which comprises Equitrans’ Allegheny Valley Connector System. The replacement segments, which are located in Westmoreland County, Pennsylvania, total approximately 3.92 miles, all as more fully set forth in the application, which is open to the public for inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Specifically, Equitrans is proposing to abandon approximately 3.85 miles of 20-inch diameter pipeline on the TP– 4555 pipeline and replace it with approximately 3.92 miles of 20-inch VerDate Sep<11>2014 16:29 May 10, 2019 Jkt 247001 diameter pipeline. The TP–4555 pipeline is part of Equitrans’ Allegheny Valley Connector System. Any questions regarding this application should be directed to Matthew Eggerding Assistant General Counsel, 2200 Energy Drive, Canonsburg, PA 15317, or call (412) 553–5786, or by email: meggerding@ equitransmidstream.com. Any person or the Commission’s staff may, within 60 days after issuance of the instant notice by the Commission, file pursuant to Rule 214 of the Commission’s Procedural Rules (18 CFR 385.214) a motion to intervene or notice of intervention and pursuant to Section 157.205 of the regulations under the NGA (18 CFR 157.205), a protest to the request. If no protest is filed within the time allowed therefore, the proposed activity shall be deemed to be authorized effective the day after the time allowed for filing a protest. If a protest is filed and not withdrawn within 30 days after the allowed time for filing a protest, the instant request shall be treated as an application for authorization pursuant to section 7 of the NGA. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding, or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission’s environmental mailing list, and will be notified of any meetings associated with the Commission’s environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenter will PO 00000 Frm 00030 Fmt 4703 Sfmt 4703 20875 not receive copies of all documents filed by other parties or issued by the Commission and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 3 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Dated: May 3, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–09707 Filed 5–10–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER19–1778–000] Glen Ullin Energy Center, LLC.; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding of Glen Ullin Energy Center, LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is May 28, 2019. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor E:\FR\FM\13MYN1.SGM 13MYN1

Agencies

[Federal Register Volume 84, Number 92 (Monday, May 13, 2019)]
[Notices]
[Pages 20873-20875]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-09718]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Combined Notice of Filings #1

    Take notice that the Commission received the following electric 
corporate filings:

    Docket Numbers: EC19-84-000.

[[Page 20874]]

    Applicants: Oregon Trail Wind Park, LLC, Payne's Ferry Wind Park, 
LLC, Pilgrim Stage Station Wind Park, LLC, Yahoo Creek Wind Park, LLC.
    Description: Application for Authorization Under Section 203 of the 
Federal Power Act, et al. of Oregon Trail Wind Park, LLC, et al.
    Filed Date: 5/2/19.
    Accession Number: 20190502-5140.
    Comments Due: 5 p.m. ET 5/23/19.

    Take notice that the Commission received the following exempt 
wholesale generator filings:

    Docket Numbers: EG19-95-000.
    Applicants: Glen Ullin Energy Center, LLC.
    Description: Self-Certification of EG or FC of Glen Ullin Energy 
Center, LLC.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5112.
    Comments Due: 5 p.m. ET 5/24/19.

    Take notice that the Commission received the following electric 
rate filings:

    Docket Numbers: ER10-2718-032; ER10-2719-032.
    Applicants: Cogen Technologies Linden Venture, L.P., East Coast 
Power Linden Holding, L.L.C.
    Description: Supplement to November 26, 2018 Notice of Non-Material 
Change in Status of Cogen Technologies Linden Venture, L.P., et al.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5084.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER17-1531-003.
    Applicants: CPV Fairview, LLC.
    Description: Supplement to January 17, 2019 Notice of Change in 
Status of CPV Fairview, LLC.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5100.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1153-001.
    Applicants: California Independent System Operator Corporation.
    Description: Tariff Amendment: 2019-05-03 Deficiency Filing 
Inverter-Based Interconnection Requirements to be effective 4/30/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5081.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1339-001.
    Applicants: Duke Energy Progress, LLC.
    Description: Tariff Amendment: Clarifying Amendment to Recovery of 
Storm Rates and Reqt for Expedited Action to be effective 5/15/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5066.
    Comments Due: 5 p.m. ET 5/10/19.

    Docket Numbers: ER19-1374-001.
    Applicants: Midcontinent Independent System Operator, Inc.
    Description: Tariff Amendment: 2019-05-02_SA 3271 Bondurant-
Montezuma 345kV Structure Replacement Sub MPFCA to be effective 3/20/
2019.
    Filed Date: 5/2/19.
    Accession Number: 20190502-5095.
    Comments Due: 5 p.m. ET 5/13/19.

    Docket Numbers: ER19-1375-001.
    Applicants: Midcontinent Independent System Operator, Inc..
    Description: Tariff Amendment: 2019-05-03_SA 3273 150 Mvar Cap Bank 
at Blackhawk 345kV Sub MPFCA to be effective 3/20/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5036.
    Comments Due: 5 p.m. ET 5/13/19.

    Docket Numbers: ER19-1378-001.
    Applicants: Midcontinent Independent System Operator, Inc.
    Description: Tariff Amendment: 2019-05-03_SA 3274 1x50 Mvar Cap 
Bank at Midport 161 kV MPFCA Sub to be effective 3/20/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5096.
    Comments Due: 5 p.m. ET 5/13/19.

    Docket Numbers: ER19-1639-001.
    Applicants: South Peak Wind LLC.
    Description: Tariff Amendment: Amendment to market-based rate 
application to be effective 6/21/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5042.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1771-000.
    Applicants: GridLiance Heartland LLC.
    Description: Limited Revisions to Attachment O Formula Rate 
Template and Implementation Protocols of GridLiance Heartland LLC..
    Filed Date: 5/2/19.
    Accession Number: 20190502-5139.
    Comments Due: 5 p.m. ET 5/23/19.

    Docket Numbers: ER19-1772-000.
    Applicants: PJM Interconnection, L.L.C.
    Description: Sec.  205(d) Rate Filing: Amendment to ISA, Service 
Agreement No. 4121, Queue No. NQ113 to be effective 2/25/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5041.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1773-000.
    Applicants: Alabama Power Company.
    Description: Sec.  205(d) Rate Filing: Three Rocks Solar (Evergreen 
Solar) LGIA Filing to be effective 4/22/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5043.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1774-000.
    Applicants: Alabama Power Company.
    Description: Sec.  205(d) Rate Filing: Turkey Run LGIA Filing to be 
effective 4/22/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5044.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1775-000.
    Applicants: Southern California Edison Company.
    Description: Sec.  205(d) Rate Filing: SCE Recollation of TO Tariff 
Filing 2b of 3 to be effective 5/1/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5048.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1776-000.
    Applicants: Southern California Edison Company.
    Description: Tariff Cancellation: Notice of Cancellation GIA & DSA 
Dwight ES 1 Project SA Nos. 1055-1056 to be effective 4/29/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5062.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1777-000.
    Applicants: Midwest Energy, Inc.
    Description: Petition for Temporary Waiver of Midwest Energy, Inc.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5063.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1778-000.
    Applicants: Glen Ullin Energy Center, LLC.
    Description: Baseline eTariff Filing: Market-Based Rate Application 
to be effective 5/6/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5092.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1779-000.
    Applicants: Midcontinent Independent System Operator, Inc.
    Description: Sec.  205(d) Rate Filing: 2019-05-03_SA 1632 ITC 
Midwest-Osceola Windpower 3rd Rev GIA (G426 G538) to be effective 4/19/
2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5094.
    Comments Due: 5 p.m. ET 5/24/19.

    Docket Numbers: ER19-1780-000.
    Applicants: Southwest Power Pool, Inc.
    Description: Sec.  205(d) Rate Filing: 3550 WAPA & City of Moorhead 
MN Interconnection Agreement to be effective 5/2/2019.
    Filed Date: 5/3/19.
    Accession Number: 20190503-5114.
    Comments Due: 5 p.m. ET 5/24/19.

    The filings are accessible in the Commission's eLibrary system by 
clicking on the links or querying the docket number.
    Any person desiring to intervene or protest in any of the above 
proceedings

[[Page 20875]]

must file in accordance with Rules 211 and 214 of the Commission's 
Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern 
time on the specified comment date. Protests may be considered, but 
intervention is necessary to become a party to the proceeding.
    eFiling is encouraged. More detailed information relating to filing 
requirements, interventions, protests, service, and qualifying 
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676 
(toll free). For TTY, call (202) 502-8659.

    Dated: May 3, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-09718 Filed 5-10-19; 8:45 am]
 BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.