Combined Notice of Filings #1, 13281-13283 [2019-06590]
Download as PDF
Federal Register / Vol. 84, No. 65 / Thursday, April 4, 2019 / Notices
Dated: April 1, 2019.
Kate Mullan,
PRA Coordinator, Information Collection
Clearance Program, Information Management
Branch, Office of the Chief Information
Officer.
[FR Doc. 2019–06608 Filed 4–3–19; 8:45 am]
BILLING CODE 4000–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14958–000]
jbell on DSK30RV082PROD with NOTICES
Oceanus Power & Water, LLC; Notice
of Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
On December 27, 2018, Oceanus
Power & Water, LLC, filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
feasibility of the Integrated Pumped
Hydroelectric Reverse Osmosis Clean
Energy System at the Vandenberg Air
Force Base (IPHROCES at Vandenberg
AFB Project or project) to be located on
coast of the Pacific Ocean, near
Vandenberg Air Force, Santa Barbara
County, California. The sole purpose of
a preliminary permit, if issued, is to
grant the permit holder priority to file
a license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist of
the following: (1) A rock-fill dam
(dimensions and position to be
determined based energy and water
storage volume requirements under the
permit term, if issued); (2) a upper
reservoir having a total storage capacity
of 5,000 acre-feet at a normal maximum
operating elevation of 1,310 feet mean
sea level (msl); (3) two 12,450-foot-long,
11-foot-diameter penstocks running
above ground between the upper
reservoir and the powerhouse; (4) an
underground powerhouse with
approximate footprint of 0.4-acre and
containing two variable speed reversible
Francis reversible pump/turbine-motor/
generator units rated for 75 megawatts
each at 1,310 feet of gross head; (5) a 50foot-high seawater reverse osmosis
desalinization facility with an
approximate footprint of 15-acres
located approximately 325-feet from the
powerhouse; (6) two 11-foot-diameter
tailrace pipelines, each with six 35-foot-
VerDate Sep<11>2014
17:25 Apr 03, 2019
Jkt 247001
long, 11-foot-diameter Johnson screens,
extending from the powerhouse to the
intake/outlet structure; (7) a seawater
intake/outlet structure located in the
Pacific Ocean; (8) a brine concentrate
storage lagoon to store brine concentrate
during times when the project is
inoperable or in pumping mode; (9) a
10-mile-long, transmission line
extending from the project to the
existing Divide Substation (the point of
interconnection), the number of circuits,
voltage, and configuration to be
determined during the term of the
permit, if issued; and (10) appurtenant
facilities. The lower reservoir for the
proposed project would be the Pacific
Ocean. The estimated annual generation
of the IPHROCES at Vandenberg AFB
Project would be 415 gigawatt-hours.
Applicant Contact: Mr. Neal Aronson,
Director, President/CEO, Oceanus
Power & Water, LLC, 900 High Street,
Palo Alto, California 94301; phone:
(650) 380–3323.
FERC Contact: Kelly Wolcott; phone:
(202) 502–6480.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–14958–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s website at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14958) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
13281
Dated: March 29, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–06596 Filed 4–3–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC19–38–000.
Applicants: Northern States Power
Company, a Minnesota corporation,
Mankato Energy Center, LLC, Mankato
Energy Center II, LLC.
Description: Supplement to December
18, 2018 Joint Application
Authorization (Exhibit N) of Northern
States Power Company, a Minnesota
corporation, et al.
Filed Date: 3/29/19.
Accession Number: 20190329–5322.
Comments Due: 5 p.m. ET 4/12/19.
Docket Numbers: EC19–46–000.
Applicants: Orange and Rockland
Utilities, Inc.
Description: Clarification and Revised
Exhibits A and B to January 15, 2019
Application for order pursuant to
Section 203 of the Federal Power Act of
Orange and Rockland Utilities, Inc.
Filed Date: 3/28/19.
Accession Number: 20190328–5326.
Comments Due: 5 p.m. ET 4/11/19.
Docket Numbers: EC19–72–000.
Applicants: Northern States Power
Company, a Minnesota corporation,
Lake Benton Power Partners II, LLC.
Description: Joint Application for
Authorization Under Section 203 of the
Federal Power Act, et al. of Northern
States Power Company, a Minnesota
corporation, et al.
Filed Date: 3/28/19.
Accession Number: 20190328–5318.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: EC19–73–000.
Applicants: NGV Emerald Acquisition
Co., LLC, Great Plains Windpark Legacy,
LLC.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act, et al. of NGV
Emerald Acquisition Co., LLC, et al.
Filed Date: 3/28/19.
Accession Number: 20190328–5323.
Comments Due: 5 p.m. ET 4/18/19.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2422–006.
E:\FR\FM\04APN1.SGM
04APN1
jbell on DSK30RV082PROD with NOTICES
13282
Federal Register / Vol. 84, No. 65 / Thursday, April 4, 2019 / Notices
Applicants: Rocky Mountain Power,
LLC.
Description: Notice of Non-Material
Change in Status of Rocky Mountain
Power, LLC.
Filed Date: 3/28/19.
Accession Number: 20190328–5286.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER16–2716–005.
Applicants: NextEra Energy
Transmission MidAtlantic, LLC.
Description: Compliance filing:
NextEra Energy Transmission
MidAtlantic Revised Compliance Filing
to be effective 11/30/2016.
Filed Date: 3/29/19.
Accession Number: 20190329–5362.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER16–2719–007.
Applicants: NextEra Energy
Transmission New York, Inc.
Description: Compliance filing:
NextEra Energy Transmission New York
Revised Compliance Filing to be
effective 11/30/2016.
Filed Date: 3/29/19.
Accession Number: 20190329–5363.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1103–001.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Tariff Amendment:
2019–03–28_Amendment to Attachment
X revisions for Hybrid Interconnection
to be effective 3/28/2019.
Filed Date: 3/28/19.
Accession Number: 20190328–5259.
Comments Due: 5 p.m. ET 4/8/19.
Docket Numbers: ER19–1464–000.
Applicants: Sierra Pacific Power
Company.
Description: § 205(d) Rate Filing:
Service Agreement No. 18–00088 EPC
SPPC/Fallon to be effective 3/29/2019.
Filed Date: 3/28/19.
Accession Number: 20190328–5253.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER19–1465–000.
Applicants: Sierra Pacific Power
Company.
Description: § 205(d) Rate Filing:
Service Agreement No. 18–00089
Amded NITSA SPPC/Fallon to be
effective 5/28/2019.
Filed Date: 3/28/19.
Accession Number: 20190328–5254.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER19–1466–000.
Applicants: Pacific Gas and Electric
Company.
Description: § 205(d) Rate Filing:
PG&E Steelhead BESS SGIA (SA 416) to
be effective 5/27/2019.
Filed Date: 3/28/19.
Accession Number: 20190328–5271.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER19–1467–000.
VerDate Sep<11>2014
17:25 Apr 03, 2019
Jkt 247001
Applicants: Arizona Public Service
Company.
Description: Tariff Cancellation:
Cancellation of Service Agreement Nos.
308, 352, 357, and 358 to be effective
5/28/2019.
Filed Date: 3/28/19.
Accession Number: 20190328–5277.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER19–1468–000.
Applicants: Niagara Mohawk Power
Corporation, New York Independent
System Operator, Inc.
Description: § 205(d) Rate Filing: 205
Cost Reimbursement Agreement (SA
2448) NMPC and NYPA to be effective
3/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5003.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1469–000.
Applicants: New England Power Pool
Participants Committee.
Description: § 205(d) Rate Filing:
April 2019 Membership Filing to be
effective 4/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5071.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1470–000.
Applicants: ISO New England Inc.,
Emera Maine.
Description: § 205(d) Rate Filing:
Emera Maine; Changes to ISO–NE
OATT Schedule 21–EM to be effective
6/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5082.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1471–000.
Applicants: Wisconsin Electric Power
Company.
Description: § 205(d) Rate Filing:
Update to Reactive Supply Service
Revenue Requirement to be effective 4/
1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5087.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1472–000.
Applicants: Wisconsin Electric Power
Company.
Description: Notice of Cancellation of
Rate Schedule No. 103 of Wisconsin
Electric Power Company.
Filed Date: 3/28/19.
Accession Number: 20190328–5314.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER19–1473–000.
Applicants: AES Alamitos Energy,
LLC.
Description: Baseline eTariff Filing:
AES Alamitos Energy MBR Application
to be effective 5/29/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5126.
Comments Due: 5 p.m. ET 4/19/19.
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
Docket Numbers: ER19–1474–000.
Applicants: AES Huntington Beach
Energy, LLC.
Description: Baseline eTariff Filing:
AES Huntington Beach Energy
Application to be effective 5/29/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5143.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1475–000.
Applicants: Potomac Electric Power
Company, PJM Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
PEPCO submits revisions to OATT, Att.
H–9A and H–9B re: True-up to be
effective 6/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5170.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1476–000.
Applicants: Duke Energy Progress,
LLC.
Description: § 205(d) Rate Filing: DEPFayetteville PWC (RS No. 184)
Amended PSCA to be effective 6/1/
2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5190.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1477–000.
Applicants: Entergy Louisiana, LLC.
Description: § 205(d) Rate Filing:
ELL–SRMPA 15th Extension of Interim
Agreement to be effective 4/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5198.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1478–000.
Applicants: Commonwealth Edison
Company, PJM Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
ComEd submits revisions to OATT, Att.
H–13A re: Superconductor Cable Project
to be effective 5/28/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5200.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1479–000.
Applicants: Trans-Allegheny
Interstate Line Company, PJM
Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
TrAILCo submits Transmission Facility
Interconnection Agreement, SA No.
4239 to be effective 5/30/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5204.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19–1480–000.
Applicants: Southern California
Edison Company.
Description: § 205(d) Rate Filing: 2019
TACBAA Update to be effective 6/1/
2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5211.
Comments Due: 5 p.m. ET 4/19/19.
E:\FR\FM\04APN1.SGM
04APN1
Federal Register / Vol. 84, No. 65 / Thursday, April 4, 2019 / Notices
Docket Numbers: ER19–1481–000.
Applicants: Trans-Allegheny
Interstate Line Company, PJM
Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
TrAILCo submits Transmission Facility
Interconnection Agreement, SA No.
4368 to be effective 5/30/2019.
Filed Date: 3/29/19.
Accession Number: 20190329–5212.
Comments Due: 5 p.m. ET 4/19/19.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 29, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–06590 Filed 4–3–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER19–1461–000]
jbell on DSK30RV082PROD with NOTICES
Greenlight Energy Inc.; Supplemental
Notice That Initial Market-Based Rate
Filing Includes Request for Blanket
Section 204 Authorization
This is a supplemental notice in the
above-referenced Greenlight Energy
Inc.’s application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
VerDate Sep<11>2014
17:25 Apr 03, 2019
Jkt 247001
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is April 18,
2019.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an eSubscription link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: March 29, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–06592 Filed 4–3–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD10–12–010]
Increasing Market and Planning
Efficiency and Enhancing Resilience
Through Improved Software; Notice of
Technical Conference: Increasing
Real-Time and Day-Ahead Market
Efficiency and Enhancing Resilience
Through Improved Software
Take notice that Commission staff
will convene a technical conference on
June 25, 26, and 27, 2019 to discuss
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
13283
opportunities for increasing real-time
and day-ahead market efficiency and
enhancing the resilience of the bulk
power system through improved
software. A detailed agenda with the list
of and times for the selected speakers
will be published on the Commission’s
website 1 after May 13, 2019.
Staff has held similar conferences in
this proceeding in the past few years, all
focused on enhancing market efficiency.
The Commission last year initiated a
proceeding in Docket No. AD18–7 to
explore bulk power system resilience
issues and expanded the scope of the
2018 conference to include
opportunities for enhancing resilience
through improved software. As in past
conferences, this conference will bring
together experts from diverse
backgrounds and experiences, including
electric system operators, software
developers, and those from government,
research centers and academia for the
purposes of stimulating discussion,
sharing information, and identifying
fruitful avenues for research concerning
the technical aspects of improved
software for increasing efficiency and
resilience of the bulk power system.
This conference is intended to build
on the discussions initiated in the
previous Commission staff technical
conferences on increasing market and
planning efficiency and for enhancing
resilience through improved software. A
number of the topics that have been
discussed during previous conferences
have relevance to resilience in addition
to market efficiency. Staff will be
facilitating a discussion to explore
research and operational advances with
respect to market modeling that appear
to have significant promise for potential
efficiency improvements. Given the
priority the Commission places on
resilience, presentations that also
discuss research and operational
advances that could enhance resilience
of the bulk power system are
encouraged. Broadly, such topics fall
into the following categories:
(1) Improvements to the
representation of physical constraints
that are either not currently modeled or
currently modeled using mathematical
approximations (e.g., voltage and
reactive power constraints, stability
constraints, fuel delivery constraints,
and constraints related to
contingencies);
(2) Consideration of uncertainty to
better maximize economic efficiency
(expected market surplus) and better
understand events that could impact
resilience of the bulk power system, e.g.,
1 https://www.ferc.gov/industries/electric/indusact/market-planning.asp.
E:\FR\FM\04APN1.SGM
04APN1
Agencies
[Federal Register Volume 84, Number 65 (Thursday, April 4, 2019)]
[Notices]
[Pages 13281-13283]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-06590]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
corporate filings:
Docket Numbers: EC19-38-000.
Applicants: Northern States Power Company, a Minnesota corporation,
Mankato Energy Center, LLC, Mankato Energy Center II, LLC.
Description: Supplement to December 18, 2018 Joint Application
Authorization (Exhibit N) of Northern States Power Company, a Minnesota
corporation, et al.
Filed Date: 3/29/19.
Accession Number: 20190329-5322.
Comments Due: 5 p.m. ET 4/12/19.
Docket Numbers: EC19-46-000.
Applicants: Orange and Rockland Utilities, Inc.
Description: Clarification and Revised Exhibits A and B to January
15, 2019 Application for order pursuant to Section 203 of the Federal
Power Act of Orange and Rockland Utilities, Inc.
Filed Date: 3/28/19.
Accession Number: 20190328-5326.
Comments Due: 5 p.m. ET 4/11/19.
Docket Numbers: EC19-72-000.
Applicants: Northern States Power Company, a Minnesota corporation,
Lake Benton Power Partners II, LLC.
Description: Joint Application for Authorization Under Section 203
of the Federal Power Act, et al. of Northern States Power Company, a
Minnesota corporation, et al.
Filed Date: 3/28/19.
Accession Number: 20190328-5318.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: EC19-73-000.
Applicants: NGV Emerald Acquisition Co., LLC, Great Plains Windpark
Legacy, LLC.
Description: Application for Authorization Under Section 203 of the
Federal Power Act, et al. of NGV Emerald Acquisition Co., LLC, et al.
Filed Date: 3/28/19.
Accession Number: 20190328-5323.
Comments Due: 5 p.m. ET 4/18/19.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER10-2422-006.
[[Page 13282]]
Applicants: Rocky Mountain Power, LLC.
Description: Notice of Non-Material Change in Status of Rocky
Mountain Power, LLC.
Filed Date: 3/28/19.
Accession Number: 20190328-5286.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER16-2716-005.
Applicants: NextEra Energy Transmission MidAtlantic, LLC.
Description: Compliance filing: NextEra Energy Transmission
MidAtlantic Revised Compliance Filing to be effective 11/30/2016.
Filed Date: 3/29/19.
Accession Number: 20190329-5362.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER16-2719-007.
Applicants: NextEra Energy Transmission New York, Inc.
Description: Compliance filing: NextEra Energy Transmission New
York Revised Compliance Filing to be effective 11/30/2016.
Filed Date: 3/29/19.
Accession Number: 20190329-5363.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1103-001.
Applicants: Midcontinent Independent System Operator, Inc.
Description: Tariff Amendment: 2019-03-28_Amendment to Attachment X
revisions for Hybrid Interconnection to be effective 3/28/2019.
Filed Date: 3/28/19.
Accession Number: 20190328-5259.
Comments Due: 5 p.m. ET 4/8/19.
Docket Numbers: ER19-1464-000.
Applicants: Sierra Pacific Power Company.
Description: Sec. 205(d) Rate Filing: Service Agreement No. 18-
00088 EPC SPPC/Fallon to be effective 3/29/2019.
Filed Date: 3/28/19.
Accession Number: 20190328-5253.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER19-1465-000.
Applicants: Sierra Pacific Power Company.
Description: Sec. 205(d) Rate Filing: Service Agreement No. 18-
00089 Amded NITSA SPPC/Fallon to be effective 5/28/2019.
Filed Date: 3/28/19.
Accession Number: 20190328-5254.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER19-1466-000.
Applicants: Pacific Gas and Electric Company.
Description: Sec. 205(d) Rate Filing: PG&E Steelhead BESS SGIA (SA
416) to be effective 5/27/2019.
Filed Date: 3/28/19.
Accession Number: 20190328-5271.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER19-1467-000.
Applicants: Arizona Public Service Company.
Description: Tariff Cancellation: Cancellation of Service Agreement
Nos. 308, 352, 357, and 358 to be effective 5/28/2019.
Filed Date: 3/28/19.
Accession Number: 20190328-5277.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER19-1468-000.
Applicants: Niagara Mohawk Power Corporation, New York Independent
System Operator, Inc.
Description: Sec. 205(d) Rate Filing: 205 Cost Reimbursement
Agreement (SA 2448) NMPC and NYPA to be effective 3/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5003.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1469-000.
Applicants: New England Power Pool Participants Committee.
Description: Sec. 205(d) Rate Filing: April 2019 Membership Filing
to be effective 4/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5071.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1470-000.
Applicants: ISO New England Inc., Emera Maine.
Description: Sec. 205(d) Rate Filing: Emera Maine; Changes to ISO-
NE OATT Schedule 21-EM to be effective 6/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5082.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1471-000.
Applicants: Wisconsin Electric Power Company.
Description: Sec. 205(d) Rate Filing: Update to Reactive Supply
Service Revenue Requirement to be effective 4/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5087.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1472-000.
Applicants: Wisconsin Electric Power Company.
Description: Notice of Cancellation of Rate Schedule No. 103 of
Wisconsin Electric Power Company.
Filed Date: 3/28/19.
Accession Number: 20190328-5314.
Comments Due: 5 p.m. ET 4/18/19.
Docket Numbers: ER19-1473-000.
Applicants: AES Alamitos Energy, LLC.
Description: Baseline eTariff Filing: AES Alamitos Energy MBR
Application to be effective 5/29/2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5126.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1474-000.
Applicants: AES Huntington Beach Energy, LLC.
Description: Baseline eTariff Filing: AES Huntington Beach Energy
Application to be effective 5/29/2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5143.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1475-000.
Applicants: Potomac Electric Power Company, PJM Interconnection,
L.L.C.
Description: Sec. 205(d) Rate Filing: PEPCO submits revisions to
OATT, Att. H-9A and H-9B re: True-up to be effective 6/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5170.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1476-000.
Applicants: Duke Energy Progress, LLC.
Description: Sec. 205(d) Rate Filing: DEP-Fayetteville PWC (RS No.
184) Amended PSCA to be effective 6/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5190.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1477-000.
Applicants: Entergy Louisiana, LLC.
Description: Sec. 205(d) Rate Filing: ELL-SRMPA 15th Extension of
Interim Agreement to be effective 4/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5198.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1478-000.
Applicants: Commonwealth Edison Company, PJM Interconnection,
L.L.C.
Description: Sec. 205(d) Rate Filing: ComEd submits revisions to
OATT, Att. H-13A re: Superconductor Cable Project to be effective 5/28/
2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5200.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1479-000.
Applicants: Trans-Allegheny Interstate Line Company, PJM
Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: TrAILCo submits Transmission
Facility Interconnection Agreement, SA No. 4239 to be effective 5/30/
2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5204.
Comments Due: 5 p.m. ET 4/19/19.
Docket Numbers: ER19-1480-000.
Applicants: Southern California Edison Company.
Description: Sec. 205(d) Rate Filing: 2019 TACBAA Update to be
effective 6/1/2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5211.
Comments Due: 5 p.m. ET 4/19/19.
[[Page 13283]]
Docket Numbers: ER19-1481-000.
Applicants: Trans-Allegheny Interstate Line Company, PJM
Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: TrAILCo submits Transmission
Facility Interconnection Agreement, SA No. 4368 to be effective 5/30/
2019.
Filed Date: 3/29/19.
Accession Number: 20190329-5212.
Comments Due: 5 p.m. ET 4/19/19.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: March 29, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-06590 Filed 4-3-19; 8:45 am]