PennEast Pipeline Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed PennEast Pipeline Project Amendment, and Request for Comments on Environmental Issues, 10811-10812 [2019-05495]

Download as PDF Federal Register / Vol. 84, No. 56 / Friday, March 22, 2019 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP19–78–000] PennEast Pipeline Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed PennEast Pipeline Project Amendment, and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the PennEast Pipeline Project Amendment involving construction and operation of facilities by PennEast Pipeline Company, LLC (PennEast) in Luzerne, Carbon, Monroe, and Northampton counties, Pennsylvania. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies about issues regarding the project. The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from its action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires the Commission to discover concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC on or before 5:00 p.m. Eastern Time on April 15, 2019. You can make a difference by submitting your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Commission staff will consider all filed comments during the preparation of the EA. If you sent comments on this project to the Commission before the opening of VerDate Sep<11>2014 17:37 Mar 21, 2019 Jkt 247001 this docket on February 1, 2019, you will need to file those comments in Docket No. CP19–78–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable easement agreement. You are not required to enter into an agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if you and the company do not reach an easement agreement, the pipeline company could initiate condemnation proceedings in court. In such instances, compensation would be determined by a judge in accordance with state law. PennEast provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC website (www.ferc.gov) at https://www.ferc.gov/ resources/guides/gas/gas.pdf. Public Participation The Commission offers a free service called eSubscription which makes it easy to stay informed of all issuances and submittals regarding the dockets/ projects to which you subscribe. These instant email notifications are the fastest way to receive notification and provide a link to the document files which can reduce the amount of time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/ esubscription.asp. For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208–3676 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 10811 (1) You can file your comments electronically using the eComment feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. Using eComment is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making; a comment on a particular project is considered a ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (CP19–78– 000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Summary of the Proposed Project PennEast proposes to amend their Certificate Order that was issued on January 19, 2018 under docket CP15– 558–000. Four modifications that are outside the certificated route have been proposed and/or are not able to be approved as variances under CP15–558– 000. The modifications were designed to optimize the design of the PennEast Pipeline Project and respond to agency requests. The PennEast Pipeline Project Amendment would consist of the following four amendments, all in Pennsylvania: • Saylor Avenue (Ave.) Realignment, Plains Township (Twp.), Luzerne County; • Interstate 81 Workspace Adjustment, Plains Twp., Luzerne County; • Appalachian Trail PPL Electric Utilities Crossing Realignment, Lower Towamensing Twp. Carbon County, Eldred Twp. Monroe County, and Moore Twp. Northampton County; and • Freemansburg Ave. Realignment, Bethlehem Twp., Northampton County. The general location of the project facilities is shown in appendix 1.1 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this E:\FR\FM\22MRN1.SGM Continued 22MRN1 10812 Federal Register / Vol. 84, No. 56 / Friday, March 22, 2019 / Notices Land Requirements for Construction Construction of the proposed facilities would disturb about 106 acres of land for the aboveground facilities and the pipeline. Following construction, PennEast would maintain about 39.7 acres for permanent operation of the project’s facilities; the remaining acreage would be restored and revert to former uses. About 39 percent of the proposed pipeline route would parallel existing pipeline, utility, or road rightsof-way. The EA Process The EA will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and soils; • water resources and wetlands; • vegetation and wildlife; • threatened and endangered species; • cultural resources; • land use; • air quality and noise; • public safety; and • cumulative impacts. Commission staff will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present Commission staffs’ independent analysis of the issues. The EA will be available in electronic format in the public record through eLibrary 2 and the Commission’s website (https:// www.ferc.gov/industries/gas/enviro/ eis.asp). If eSubscribed, you will receive instant email notification when the EA is issued. The EA may be issued for an allotted public comment period. Commission staff will consider all comments on the EA before making recommendations to the Commission. To ensure Commission staff have the opportunity to address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2. With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the EA.3 Agencies that would like to notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE, Washington, DC 20426, or call (202) 502– 8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 2 For instructions on connecting to eLibrary, refer to the last page of this notice. 3 The Council on Environmental Quality regulations addressing cooperating agency VerDate Sep<11>2014 17:37 Mar 21, 2019 Jkt 247001 request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultation Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic Preservation Office, and to solicit their views and those of other government agencies, interested Native American tribes, and the public on the project’s potential effects on historic properties.4 The EA for this project will document findings on the impacts on historic properties and summarize the status of consultations under section 106. Currently Identified Environmental Issues Commission staff have already identified several issues that deserve attention based on a preliminary review of the proposed facilities and the environmental information provided by PennEast. This preliminary list of issues may be changed based on your comments and our analysis. • Safety; • threatened and endangered species; • water resources and wetlands; • Appalachian National Scenic Trail crossing; • preserved lands; and • arsenic and geologic resources. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. Commission staff will update the environmental mailing list as the analysis proceeds to responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If the Commission issues the EA for an allotted public comment period, a Notice of Availability of the EA will be sent to the environmental mailing list and will provide instructions to access the electronic document on the FERC’s website (www.ferc.gov). If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please return the attached ‘‘Mailing List Update Form’’ (appendix 2). Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number in the ‘‘Docket Number’’ field, excluding the last three digits (i.e., CP19–78). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. Public sessions or site visits will be posted on the Commission’s calendar located at www.ferc.gov/EventCalendar/ EventsList.aspx along with other related information. Dated: March 15, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–05495 Filed 3–21–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2195–161] Portland General Electric Company; Notice of Availability of Environmental Assessment In accordance with the National Environmental Policy Act of 1969 and the Federal Energy Regulatory Commission’s (Commission) regulations, 18 CFR part 380 (Order No. 486, 52 FR 47897), the Office of Energy Projects has reviewed an application E:\FR\FM\22MRN1.SGM 22MRN1

Agencies

[Federal Register Volume 84, Number 56 (Friday, March 22, 2019)]
[Notices]
[Pages 10811-10812]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-05495]



[[Page 10811]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-78-000]


PennEast Pipeline Company, LLC; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed PennEast Pipeline Project 
Amendment, and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the PennEast Pipeline Project 
Amendment involving construction and operation of facilities by 
PennEast Pipeline Company, LLC (PennEast) in Luzerne, Carbon, Monroe, 
and Northampton counties, Pennsylvania. The Commission will use this EA 
in its decision-making process to determine whether the project is in 
the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies about issues regarding the project. The National Environmental 
Policy Act (NEPA) requires the Commission to take into account the 
environmental impacts that could result from its action whenever it 
considers the issuance of a Certificate of Public Convenience and 
Necessity. NEPA also requires the Commission to discover concerns the 
public may have about proposals. This process is referred to as 
``scoping.'' The main goal of the scoping process is to focus the 
analysis in the EA on the important environmental issues. By this 
notice, the Commission requests public comments on the scope of the 
issues to address in the EA. To ensure that your comments are timely 
and properly recorded, please submit your comments so that the 
Commission receives them in Washington, DC on or before 5:00 p.m. 
Eastern Time on April 15, 2019.
    You can make a difference by submitting your specific comments or 
concerns about the project. Your comments should focus on the potential 
environmental effects, reasonable alternatives, and measures to avoid 
or lessen environmental impacts. Your input will help the Commission 
staff determine what issues they need to evaluate in the EA. Commission 
staff will consider all filed comments during the preparation of the 
EA.
    If you sent comments on this project to the Commission before the 
opening of this docket on February 1, 2019, you will need to file those 
comments in Docket No. CP19-78-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable easement agreement. You 
are not required to enter into an agreement. However, if the Commission 
approves the project, that approval conveys with it the right of 
eminent domain. Therefore, if you and the company do not reach an 
easement agreement, the pipeline company could initiate condemnation 
proceedings in court. In such instances, compensation would be 
determined by a judge in accordance with state law.
    PennEast provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC website (www.ferc.gov) at https://www.ferc.gov/resources/guides/gas/gas.pdf.

Public Participation

    The Commission offers a free service called eSubscription which 
makes it easy to stay informed of all issuances and submittals 
regarding the dockets/projects to which you subscribe. These instant 
email notifications are the fastest way to receive notification and 
provide a link to the document files which can reduce the amount of 
time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/esubscription.asp.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or FercOnlineSupport@ferc.gov. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. Using eComment is an easy 
method for submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. With eFiling, you can provide 
comments in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; a comment on a particular project is considered a ``Comment 
on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP19-78-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    PennEast proposes to amend their Certificate Order that was issued 
on January 19, 2018 under docket CP15-558-000. Four modifications that 
are outside the certificated route have been proposed and/or are not 
able to be approved as variances under CP15-558-000. The modifications 
were designed to optimize the design of the PennEast Pipeline Project 
and respond to agency requests.
    The PennEast Pipeline Project Amendment would consist of the 
following four amendments, all in Pennsylvania:
     Saylor Avenue (Ave.) Realignment, Plains Township (Twp.), 
Luzerne County;
     Interstate 81 Workspace Adjustment, Plains Twp., Luzerne 
County;
     Appalachian Trail PPL Electric Utilities Crossing 
Realignment, Lower Towamensing Twp. Carbon County, Eldred Twp. Monroe 
County, and Moore Twp. Northampton County; and
     Freemansburg Ave. Realignment, Bethlehem Twp., Northampton 
County.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE, Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.

---------------------------------------------------------------------------

[[Page 10812]]

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 106 
acres of land for the aboveground facilities and the pipeline. 
Following construction, PennEast would maintain about 39.7 acres for 
permanent operation of the project's facilities; the remaining acreage 
would be restored and revert to former uses. About 39 percent of the 
proposed pipeline route would parallel existing pipeline, utility, or 
road rights-of-way.

The EA Process

    The EA will discuss impacts that could occur as a result of the 
construction and operation of the proposed project under these general 
headings:
     Geology and soils;
     water resources and wetlands;
     vegetation and wildlife;
     threatened and endangered species;
     cultural resources;
     land use;
     air quality and noise;
     public safety; and
     cumulative impacts.
    Commission staff will also evaluate reasonable alternatives to the 
proposed project or portions of the project, and make recommendations 
on how to lessen or avoid impacts on the various resource areas.
    The EA will present Commission staffs' independent analysis of the 
issues. The EA will be available in electronic format in the public 
record through eLibrary \2\ and the Commission's website (https://www.ferc.gov/industries/gas/enviro/eis.asp). If eSubscribed, you will 
receive instant email notification when the EA is issued. The EA may be 
issued for an allotted public comment period. Commission staff will 
consider all comments on the EA before making recommendations to the 
Commission. To ensure Commission staff have the opportunity to address 
your comments, please carefully follow the instructions in the Public 
Participation section, beginning on page 2.
---------------------------------------------------------------------------

    \2\ For instructions on connecting to eLibrary, refer to the 
last page of this notice.
---------------------------------------------------------------------------

    With this notice, the Commission is asking agencies with 
jurisdiction by law and/or special expertise with respect to the 
environmental issues of this project to formally cooperate in the 
preparation of the EA.\3\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultation Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, the Commission is using this notice to initiate 
consultation with the applicable State Historic Preservation Office, 
and to solicit their views and those of other government agencies, 
interested Native American tribes, and the public on the project's 
potential effects on historic properties.\4\ The EA for this project 
will document findings on the impacts on historic properties and 
summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Currently Identified Environmental Issues

    Commission staff have already identified several issues that 
deserve attention based on a preliminary review of the proposed 
facilities and the environmental information provided by PennEast. This 
preliminary list of issues may be changed based on your comments and 
our analysis.
     Safety;
     threatened and endangered species;
     water resources and wetlands;
     Appalachian National Scenic Trail crossing;
     preserved lands; and
     arsenic and geologic resources.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. Commission staff will update the environmental 
mailing list as the analysis proceeds to ensure that Commission notices 
related to this environmental review are sent to all individuals, 
organizations, and government entities interested in and/or potentially 
affected by the proposed project.
    If the Commission issues the EA for an allotted public comment 
period, a Notice of Availability of the EA will be sent to the 
environmental mailing list and will provide instructions to access the 
electronic document on the FERC's website (www.ferc.gov). If you need 
to make changes to your name/address, or if you would like to remove 
your name from the mailing list, please return the attached ``Mailing 
List Update Form'' (appendix 2).

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website at www.ferc.gov using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number 
in the ``Docket Number'' field, excluding the last three digits (i.e., 
CP19-78). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or (866) 208-3676, or for TTY, contact (202) 
502-8659. The eLibrary link also provides access to the texts of all 
formal documents issued by the Commission, such as orders, notices, and 
rulemakings.
    Public sessions or site visits will be posted on the Commission's 
calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along 
with other related information.

    Dated: March 15, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-05495 Filed 3-21-19; 8:45 am]
 BILLING CODE 6717-01-P