Download as PDF Federal Register / Vol. 84, No. 55 / Thursday, March 21, 2019 / Proposed Rules 6. Comprehensive Emissions Inventory for the St. Louis Area As discussed above, section 172(c)(3) of the CAA requires areas to submit a comprehensive emissions inventory including direct PM and all four precursors (SO2, NOX, VOCs, and ammonia). Actual emissions contained in the submittal cover the general source categories of point sources, area sources, onroad mobile sources, and nonroad mobile sources for the base attainment year of 2008. For this reason, EPA proposes to approve the emissions inventory as complete and accurate, and meets the requirement of CAA section 172(c)(3). V. What are the effects of EPA’s actions? EPA is proposing to change the official designation of the St. Louis area for the 1997 annual PM2.5 NAAQS, found at 40 CFR part 81, from nonattainment to attainment. EPA is proposing to determine that the St. Louis area has attained the 1997 annual PM2.5 standard, based on the most recent three years of certified air quality data. This action also proposes to approve the maintenance plan for the 1997 annual PM2.5 NAAQS as revisions to the Illinois SIP for the St. Louis area. Also, the EPA proposes to approve the 2008 emissions inventory for the St. Louis area as well as the 2008 and 2030 MVEBs for the St. Louis area. These MVEBs will be used in future transportation conformity analyses for the area. In addition, if finalized, according to the Fine Particulate Matter National Ambient Air Quality Standards: State Implementation Plan Requirements (81 FR 58009, August 24, 2016), ‘‘for an area that is redesignated to attainment after the effective date of this final rule, the 1997 primary annual PM2.5 NAAQS will be revoked in such an area on the effective date of its redesignation to attainment for that NAAQS. After revocation of the 1997 primary annual PM2.5 NAAQS in a given area, the designation for that standard is no longer in effect.’’ amozie on DSK9F9SC42PROD with PROPOSALS VI. Statutory and Executive Order Reviews Under the CAA, redesignation of an area to attainment and the accompanying approval of the maintenance plan under CAA section 107(d)(3)(E) are actions that affect the status of a geographical area and do not impose any additional regulatory requirements on sources beyond those required by state law. A redesignation to attainment does not in and of itself VerDate Sep<11>2014 17:18 Mar 20, 2019 Jkt 247001 impose any new requirements, but rather results in the application of requirements contained in the CAA for areas that have been redesignated to attainment. Moreover, the Administrator is required to approve a SIP submission that complies with the provisions of the Act and applicable Federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in reviewing SIP submissions, EPA’s role is to approve state choices, provided that they meet the criteria of the CAA. Accordingly, this action merely approves state law as meeting Federal requirements and does not impose additional requirements beyond those imposed by state law. For these reasons, these actions: • Is not a significant regulatory action subject to review by the Office of Management and Budget under Executive Orders 12866 (58 FR 51735, October 4, 1993) and 13563 (76 FR 3821, January 21, 2011); • Is not an Executive Order 13771 (82 FR 9339, February 2, 2017) regulatory action because SIP approvals are exempted under Executive Order 12866; • Does not impose an information collection burden under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.); • Is certified as not having a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.); • Does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104–4); • Does not have Federalism implications as specified in Executive Order 13132 (64 FR 43255, August 10, 1999); • Is not an economically significant regulatory action based on health or safety risks subject to Executive Order 13045 (62 FR 19885, April 23, 1997); • Is not a significant regulatory action subject to Executive Order 13211 (66 FR 28355, May 22, 2001); • Is not subject to requirements of Section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the CAA; and • Does not provide EPA with the discretionary authority to address, as appropriate, disproportionate human health or environmental effects, using practicable and legally permissible methods, under Executive Order 12898 (59 FR 7629, February 16, 1994). In addition, the SIP is not approved to apply on any Indian reservation land or in any other area where EPA or an PO 00000 Frm 00031 Fmt 4702 Sfmt 4702 10469 Indian tribe has demonstrated that a tribe has jurisdiction. In those areas of Indian country, the rule does not have tribal implications and will not impose substantial direct costs on tribal governments or preempt tribal law as specified by Executive Order 13175 (65 FR 67249, November 9, 2000). List of Subjects 40 CFR Part 52 Environmental protection, Air pollution control, Incorporation by reference, Intergovernmental relations, Nitrogen dioxide, Particulate matter, Sulfur oxides. 40 CFR Part 81 Environmental protection, Air pollution control, National parks, Wilderness areas. Dated: March 11, 2019. Cheryl L. Newton, Acting Regional Administrator, Region 5. [FR Doc. 2019–05285 Filed 3–20–19; 8:45 am] BILLING CODE 6560–50–P AGENCY FOR INTERNATIONAL DEVELOPMENT 48 CFR Parts 739 and 752 [0412–AA87] United States Agency for International Development Acquisition Regulation (AIDAR): Security and Information Technology Requirements U.S. Agency for International Development. ACTION: Proposed rule. AGENCY: The U.S. Agency for International Development (USAID) seeks public comment on a proposed rule that would amend the USAID Acquisition Regulation (AIDAR) to incorporate a revised definition of information technology and other requirements relating to information security and information technology approvals. The Federal Information Technology Acquisition Reform Act requires improved management of the acquisition of Information technology resources. This proposed rule revising the AIDAR, if adopted, would provide increased oversight of contractor acquisition and use of information technology resources. DATES: Comments must be received no later than May 20, 2019. ADDRESSES: Address all comments concerning this notice to Carol Ketrick, Bureau for Management, Office of Acquisition and Assistance, Policy SUMMARY: E:\FR\FM\21MRP1.SGM 21MRP1 10470 Federal Register / Vol. 84, No. 55 / Thursday, March 21, 2019 / Proposed Rules Division (M/OAA/P), Room 867F, SA– 44, Washington, DC 20523–2052. Submit comments, identified by title of the action and Regulatory Information Number (RIN) by any of the following methods: 1. Through the Federal eRulemaking Portal at https://www.regulations.gov by following the instructions for submitting comments. 2. By Mail addressed to: USAID, Bureau for Management, Office of Acquisition & Assistance, Policy Division, Room 867–F, SA–44, Washington, DC 20523–2052. Comments on the information collection request under Section E, Paperwork Reduction Act must be submitted to both USAID and OMB/ OIRA as follows: USAID—Carol Ketrick at cketrick@ usaid.gov. OMB/OIRA—email to oira_ submission@omb.eop.gov, fax to (202) 395–6974, or mail to the Office of Information and Regulatory Affairs, Office of Management and Budget, 725 17th Street NW, Washington, DC 20503. FOR FURTHER INFORMATION CONTACT: Carol Ketrick, Telephone: 202–567– 4676 or email: cketrick@usaid.gov. SUPPLEMENTARY INFORMATION: amozie on DSK9F9SC42PROD with PROPOSALS A. Instructions All comments must be in writing and submitted through one of the methods specified in the Addresses section above. All submissions (and attachments) must include the title of the action and RIN for this rulemaking. Please include your name, title, organization, postal address, telephone number, and email address in the text of the message. Please note that USAID recommends sending all comments to the Federal eRulemaking Portal because security screening precautions have slowed the delivery and dependability of surface mail to USAID/Washington. All comments will be made available at https://www.regulations.gov for public review without change, including any personal information provided. We recommend that you do not submit information that you consider Confidential Business Information (CBI) or any information that is otherwise protected from disclosure by statute. USAID will only address comments that explain why this proposed rule would be inappropriate, ineffective, or unacceptable without a change. Comments that are insubstantial or outside the scope of the rule may not be considered. VerDate Sep<11>2014 17:18 Mar 20, 2019 Jkt 247001 B. Background On September 5, 2014, the Office of Management and Budget (OMB) and the National Security Council (NSC) convened a President’s Management Council, with one of the focus areas being improvement of cybersecurity in Federal acquisitions, in particular, accountability of contractors providing IT systems and services to the Federal government. Accordingly, USAID is taking steps to address information security for information and information systems that support the operations and assets of the agency, including those managed by contractors. The new requirements will strengthen protections of Agency information systems/facilities. Following the cybersecurity review directed by OMB ‘‘Follow-Up to President’s Management Council Cybersecurity Meeting, September 5, 2014’’, which was completed by the agency Office of the Chief of Information Officer (CIO) in October 2014, a revised clause 752.204–72 Access to USAID facilities and USAID’s Information Systems (now titled Homeland Security Presidential Directive-12 (HSPD–12) and Personal Identity Verification (PIV)), and new special contract requirements were developed and implemented on an interim basis under USAID Acquisition and Assistance Policy Directive (AAPD) 16–02 SPECIAL CONTRACT REQUIREMENTS FOR INFORMATION TECHNOLOGY (IT) on May 3, 2016. The requirements in the AAPD were updated and reissued as AAPD 16–02 (Revised) on May 1, 2018. The policy published in the AAPD 16–02 (Revised) provides a new definition of information technology, and includes various requirements applicable to information and system security, as well as requirements for Electronic and Information Technology Accessibility, software licenses, and prior agency approval of IT purchases. This AIDAR proposed rule, when finalized and effective, will establish the new definition, the revised AIDAR clause 752.204–72 Homeland Security Presidential Directive-12 (HSPD–12) and Personal Identity Verification (PIV), and AIDAR clauses based on some of the special contract requirements from the AAPD 16–02 (Revised). The remaining special contract requirements regarding information and system security in AAPD 16–02 (Revised) that are not included in this proposed rule will be assessed after finalization of the currently open FAR cases on Controlled Unclassified Information (CUI) and Breaches of Personally Identifiable PO 00000 Frm 00032 Fmt 4702 Sfmt 4702 Information (PII). In addition to the contract requirements originating from the AAPD 16–02 (Revised), a proposed clause providing requirements for development and/or maintenance of third-party USAID-financed websites is included in the rule. Accordingly, USAID is proposing to amend the U.S. Agency for International Development (USAID) Acquisition Regulation (AIDAR) to revise various sections that will implement policy and procedures for contracts and orders for, or include a requirement for, information technology (IT) supplies, services and/or systems. These requirements will ensure that contractors comply with the current Agency IT policies. The requirements in this proposed rule would implement the requirements under the following authorities: The E-Government Act of 2002; Federal Information Technology Acquisition Reform ACT (FITARA) (Section 831 of the National Defense Authorization Act for Fiscal Year 2015, Pub. L. 113–291) and; Section 508 of the Rehabilitation Act of 1973, as amended (29 U.S.C. 794d) (‘‘Section 508’’); Privacy Act of 1974 (5 U.S.C. 552a—the Act); Federal Information Security Management Act (FISMA) of 2002 (FISMA, Pub. L. 107–347. 44 U.S.C. 3531–3536); National Institute of Standards and Technology (NIST) Special Publication 800–53 revision 4 or the current version; and Office of Management and Budget (OMB) Circular A–130. USAID proposes to add AIDAR subpart 739, revise AIDAR 752.204–72, and include new clauses as follows: • FAR subpart 739 provides the Agency definition of ‘‘information technology’’ as issued in AAPD 16–02 (Revised). As part of the AAPD 16–02 (Revised), a Class Deviation to FAR Part 2.101(b) definition of ‘‘information technology’’ was approved by the head of the contracting activity. This new definition broadens and clarifies the definition to include services such as cloud services; it is derived from the definition set forth in the Office of Management and Budget’s (OMB’s) guidance at OMB Memo M–15–14, Management Oversight of Federal Information Technology dated June 10, 2015. AIDAR 739.2 adds this definition, which also appears at 752.239–XX Use of Information Technology Approval and 752.239–XX Limitation on Use of Information Technology. • AIDAR Clause 752.204–72 Access to USAID Facilities and USAID’s Information Systems is being replaced in its entirety with a new title Homeland Security Presidential Directive-12 (HSPD–12) and Personal E:\FR\FM\21MRP1.SGM 21MRP1 amozie on DSK9F9SC42PROD with PROPOSALS Federal Register / Vol. 84, No. 55 / Thursday, March 21, 2019 / Proposed Rules Identity Verification (PIV) and significant changes to reflect additional restrictions and reporting to better implement Homeland Security Presidential Directive-12 (HSPD–12) (August 27, 2004) and PIV procedures. The revision improves requirements for contractor personnel provided access to agency facilities and information systems, as well as timely monitoring of such access when the employee’s employment is terminated. The revised clause requires submission of staff reports listing employees that require access to USAID facilities or information systems, and also specifies the Agency’s authority to suspend or terminate the access to any systems and/ or facilities if an Information Security Incident or other electronic access violation, use, or misuse incident gives cause for such action. • AIDAR 752.204–XX USAIDFinanced Third-party websites requires that Contractors adhere to certain requirements when developing, launching, and maintaining a thirdparty website funded by USAID for the purpose of meeting the project implementation goals. This applies to sites hosted on environments external to USAID boundaries and not directly controlled by USAID policies and staff. The clause requires adherence to Agency branding requirements and limits the contractor to collecting only the amount of information necessary to complete the specific business need as required by statute, regulation, or Executive Order. • AIDAR 752.239–XX Limitation on Information Technology prohibits the acquisition of information technology under an award as defined in the clause unless prior approval is obtained from the contracting officer. The clause ensures that only information technology approved by the Agency Chief Information officer (CIO) is acquired, pursuant to the Federal Information Technology Acquisition Reform ACT (FITARA)(Section 831 of the National Defense Authorization Act for Fiscal Year 2015, Pub. L. 113–291). All agency IT investment decisions, including software and IT equipment, must be made consistent with the agency’s enterprise architecture. USAID must consider the total cost of ownership including the costs associated with risk issues, including security and privacy of data, and the costs of ensuring security of the IT system itself. This clause is consistent with the guidance promulgated by OMB in support of the Federal Information Technology Acquisition Reform Act (FITARA) and related information VerDate Sep<11>2014 17:18 Mar 20, 2019 Jkt 247001 technology (IT) management practices in OMB Memo M–15–14 Management Oversight of Federal Information Technology. • AIDAR 752.239–XX Software License addresses the need to ensure that acquired software is aligned with the agency’s enterprise architecture; it will also enable the Agency to consolidate licenses when appropriate in alignment with OMB Category Management Policy 16–1. The clause clarifies that renewal of software licenses may only occur in accordance with the mutual agreement of the parties; or an option renewal clause allowing the Government to unilaterally exercise one or more options to extend the term of the award. Since renewal of a software license would require the obligation of funds by the Federal Government, renewal must not be automatic. Commercial off the shelf software solutions are offered to the public under standard agreements that may take a variety of forms, including license agreements, terms of service (TOS), terms of sale or purchase, and similar agreements. Customarily, these standard agreements contain terms and conditions that are appropriate when the purchaser is a private party but are inappropriate when the purchaser is the Federal Government. • AIDAR 752.239–XX Information and Communication Technology (ICT) Accessibility requires contractors to implement Section 508 of the Rehabilitation Act of 1973, as amended (29 U.S.C. 794d) (‘‘Section 508’’). This clause applies to all development, procurement, maintenance, and information communication technology for use by USAID and members of the U.S. public. • AIDAR 752.239–XX Information Technology Approval requires that contractors acquire only the information technology specified in the contract, and specifies a process to request approval if the Contractor determines that acquisition of information technology is necessary to meet the Government’s requirements under the award. The clause ensures that only information technology approved by the Agency Chief Information Officer (CIO) is acquired, pursuant to the Federal Information Technology Acquisition Reform ACT (FITARA)(Section 831 of the National Defense Authorization Act for Fiscal Year 2015, Pub. L. 113–291). All agency IT investment decisions, including software and IT equipment, must be made consistent with the agency’s enterprise architecture. USAID must consider the total cost of ownership including the costs PO 00000 Frm 00033 Fmt 4702 Sfmt 4702 10471 associated with risk issues, including security and privacy of data, and the costs of ensuring security of the IT system itself. This clause is consistent with the guidance promulgated by OMB in support of the Federal Information Technology Acquisition Reform Act (FITARA) and related information technology (IT) management practices in OMB Memo M–15–14 Management Oversight of Federal Information Technology. • AIDAR 752.239–XX Skills and Certification Requirements for Privacy and Security Staff requires that Contractor personnel performing the roles of Information System Security Officer and Information Security Specialists possess a Certified Information Systems Security Professional (CISSP) certification. All USAID contractors who have significant information security responsibilities as defined by OPM 5 CFR part 930 must complete specialized IT security training. Additionally, contractor personnel filling the role of Privacy Analysts must possess a Certified Information Privacy Professional (CIPP) credential with a CIPP/US to ensure that Privacy Analysts have the expertise required to implement U.S. government privacy laws, regulations and policies specific to government practice. C. Regulatory Planning and Review This proposed rule has been determined to be ‘‘nonsignificant’’ under Executive Order 12866, Regulatory Planning and Review, dated September 30, 1993 and, therefore, is not subject to review. This proposed rule is not a major rule under 5 U.S.C. 804. D. Regulatory Flexibility Act The proposed rule does not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq. Therefore, an Initial Regulatory Flexibility Analysis has not been performed. E. Paperwork Reduction Act The Paperwork Reduction Act (44 U.S.C. chapter 35) applies. The proposed rule contains an information collection requirement. Accordingly, USAID has submitted a request to the Office of Management and Budget for approval of a new information collection requirement concerning ‘‘Access to USAID Facilities and USAID’s Information Systems’’ and the E:\FR\FM\21MRP1.SGM 21MRP1 amozie on DSK9F9SC42PROD with PROPOSALS 10472 Federal Register / Vol. 84, No. 55 / Thursday, March 21, 2019 / Proposed Rules monthly reports of employees requiring access. List of Subjects in 48 CFR parts 739 and 752 Access to USAID Facilities and USAID’s Information Systems Government procurement. For the reasons discussed in the preamble, USAID proposes to amend 48 CFR Parts 739 and 752 as set forth below: ■ 1. Add part 739 to read as follows: Public reporting burden for this collection of information is estimated to average initially eight hours immediately after contract award to develop the list of employee’s requiring access, then 2 hours per month to update such a list, including the time for reviewing instructions, gathering/ maintaining the employee names, and forwarding the list to the agency for processing. The recordkeeping requirements are minor. While a contractor is required to identify and submit the list of its employees who require access, there is no requirement to collect this information in a particular format for submission to the agency. The annual reporting burden is estimated as follows: Total number of respondents and the amount of time estimated for an average respondent to respond: 138 contractors; eight hours for the initial report, 24 hours annually thereafter for submission of the monthly reports. Total public burden (in hours) associated with the collection: 1,104 hours initially, and 3,312 hours annually thereafter. Total public burden (in cost) associated with the collection: Initial submission, $54,537, then $163,613 annually thereafter. When submitting comments on these information collections, your comments should address one or more of the following four points: (1) Evaluate whether the proposed collection of information is necessary for the proper performance of the functions of the agency, including whether the information will have practical utility; (2) Evaluate the accuracy of the agency’s estimate of the burden of the proposed collection of information, including the validity of the methodology and assumptions used; (3) Ways to enhance the quality, utility, and clarity of the information to be collected; and (4) Ways which USAID can minimize the burden of the collection of information on those who are to respond, including through the use of appropriate automated, electronic, mechanical, or other technological collection techniques or other forms of information technology, e.g., permitting electronic submission of responses. VerDate Sep<11>2014 17:18 Mar 20, 2019 Jkt 247001 PART 739—Acquisition of Information Technology Sec. 739.002 739.003 Definitions. As used in this part— Information Technology means (1) Any services or equipment, or interconnected system(s) or subsystem(s) of equipment, that are used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the agency; where (2) Such services or equipment are ‘‘used by an agency’’ if used by the agency directly or if used by a contractor under a contract with the agency that requires either use of the services or equipment or requires use of the services or equipment to a significant extent in the performance of a service or the furnishing of a product. (3) The term ‘‘information technology’’ includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including provisioned services such as cloud computing and support services that support any point of the lifecycle of the equipment or service), and related resources. (4) The term ‘‘information technology’’ does not include any equipment that is acquired by a contractor incidental to a contract that does not require use of the equipment. 739.003 [Reserved] PART 752—SOLICITATION PROVISIONS AND CONTRACT CLAUSES 2. The authority for part 752 continues to read as follows: ■ PO 00000 Frm 00034 Fmt 4702 3. Amend section 752.204–72 by revising the section heading and the clause to read as follows: ■ 752.204–72 Homeland Security Presidential Directive-12 (HSPD–12) and Personal Identity Verification (PIV). * * * * * Homeland Security Presidential Directive-12 (HSPD–12) and Personal Identity Verification (PIV) (Date) Definitions [Reserved] Authority: Sec. 621, Pub. L. 87–195, 75 Stat. 445, (22 U.S.C. 2381) as amended; E.O. 12163, Sept. 29, 1979, 44 FR 56673; and 3 CFR 1979 Comp., p. 435. 739.002 Authority: Sec. 621, Pub. L. 87–195, 75 Stat. 445, (22 U.S.C. 2381) as amended; E.O. 12163, Sept. 29, 1979, 44 FR 56673; and 3 CFR 1979 Comp., p. 435. Sfmt 4702 (a) Individuals engaged in the performance of this award as employees, consultants, or volunteers of the contractor must comply with all applicable HSPD–12 and PIV procedures, as described below, and any subsequent USAID or Government-wide HSPD–12 and PIV procedures/policies. (b) A U.S. citizen or resident alien engaged in the performance of this award as an employee, consultant, or volunteer of a U.S firm may obtain access to USAID facilities or logical access to USAID’s information systems only when and to the extent necessary to carry out this award and in accordance with this clause. The contractor’s employees, consultants, or volunteers who are not U.S. citizens or resident aliens as well as employees, consultants, or volunteers of non-U.S. firms, irrespective of their citizenship, will not be granted logical access to U.S. Government information technology systems (such as Phoenix, GLAAS, etc.) and must be escorted to use U.S. Government facilities (such as office space). (c) (1) No later than five business days after award, the Contractor must provide to the Contracting Officer’s Representative (COR) a complete list of employees that require access to USAID facilities or information systems. (2) Before a contractor (or a contractor employee, consultant, or volunteer) or subcontractor at any tier may obtain a USAID ID (new or replacement) authorizing the individual routine access to USAID facilities in the United States, or logical access to USAID’s information systems, the individual must provide two forms of identity source documents in original form to the Enrollment Office personnel when undergoing processing. One identity source document must be a valid Federal or State Governmentissued picture ID. Contractors may contact the USAID Security Office to obtain the list of acceptable forms of documentation. Submission of these documents, to include documentation of security background investigations, is mandatory in order for the contractor to receive a PIV or PIV-Alternative (PIV–A)/Facilities Access Card (FAC) card and be granted access to any of USAID’s information systems. All such individuals must physically present these two source documents for identity proofing at their enrollment. (d) The Contractor must send a staffing report to the COR by the fifth day of each month. The report must contain the listing of E:\FR\FM\21MRP1.SGM 21MRP1 Federal Register / Vol. 84, No. 55 / Thursday, March 21, 2019 / Proposed Rules all staff members with access who were separated or hired under this contract in the past sixty (60) calendar days. This report must be submitted even if no separations or hiring occurred during the reporting period. Failure to submit the ‘Contractor Staffing Change Report’ each month may, at USAID’s discretion, result in the suspension of all logical access to USAID information systems and/or facilities access associated with this contract. USAID will provide the contractor the format for this report. (e) Contractor employees are strictly prohibited from sharing logical access to USAID information systems and Sensitive Information. USAID will disable accounts and revoke logical access to USAID IT systems if Contractor employees share accounts. (f) USAID, at its discretion, may suspend or terminate the access to any systems and/ or facilities when an Information Security Incident or electronic access violation, use, or misuse incident gives cause for such action. The suspension or termination may last until such time as USAID determines that the situation has been corrected or no longer exists. (g) The Contractor must notify the COR and the USAID Service Desk at least five business days prior to the Contractor employee’s removal from the contract. For unplanned terminations of Contractor employees, the Contractor must immediately notify the COR and the USAID Service Desk (CIOHELPDESK@usaid.gov or (202) 712–1234). The Contractor or its Facilities Security Officer must return USAID PIV/FAC cards and remote authentication tokens issued to Contractor employees to the COR prior to departure of the employee or upon completion or termination of the contract, whichever occurs first. (h) The contractor is required to insert this clause (including this paragraph (h) in any subcontracts that require the subcontractor, subcontractor employee, or consultant to have routine physical access to USAID space or logical access to USAID’s information systems. (End of Clause) ■ 4. Add section 752.204–XX to read as follows: 752.204–XX Websites. USAID-Financed Third-Party Insert the following clause in USAIDfunded solicitations and contracts that require development and/or maintenance of a third-party website to achieve project implementation goals. amozie on DSK9F9SC42PROD with PROPOSALS USAID-Financed Third-Party Websites (Date) (a) Definitions: ‘‘Third-party websites’’ Websites hosted on environments external to USAID boundaries and not directly controlled by USAID policies and staff, except through the terms and conditions of a contract. Third-party websites include project websites. (b) The contractor must adhere to the following requirements when developing, launching, and maintaining a third-party VerDate Sep<11>2014 17:18 Mar 20, 2019 Jkt 247001 website funded by USAID for the purpose of meeting the project implementation goals: (1) Prior to website development, the Contractor must provide information as required in Section C-Statement of Work of the contract (including a copy of their Contractor’s privacy policy) to the Contracting Officer’s Representative (COR), for USAID’s Bureau for Legislative and Public Affairs (LPA) evaluation and approval. The Contractor must notify the COR of the website URL as far in advance of the site’s launch as possible and must not launch the website until USAID’s approval has been provided through the COR. The Contractor must provide the COR any changes to the Contractor’s privacy policy for the duration of the contract. (2) The Contractor must collect only the amount of information necessary to complete the specific business need as required by statute, regulation, or Executive Order. (3) The Contractor must comply with Agency branding and marking requirements comprised of the USAID logo and brandmark with the tagline ‘‘from the American people,’’ located on the USAID website at www.usaid.gov/branding, and USAID Graphics Standards manual at https:// www.usaid.gov. (4) The website must be marked on the index page of the site and every major entry point to the website with a disclaimer that states: ‘‘The information provided on this website is not official U.S. Government information and does not represent the views or positions of the U.S. Agency for International Development or the U.S. Government.’’ (5) The website must provide persons with disabilities access to information that is comparable to the access available to others. As such, all site content must be compliant with the requirements of the Section 508 of the Rehabilitation Act, as amended (29 U.S.C. 794d) (‘‘Section 508’’) and other terms and conditions of the contract. (6) The Contractor must identify and provide to the COR, in writing, the contact information for the Contractor’s information security point of contact. The contractor is responsible for updating the contact information whenever there is a change in personnel assigned to this role. (7) The Contractor must provide adequate protection from unauthorized access, alteration, disclosure, or misuse of information processed, stored, or transmitted on the websites. To minimize security risks and ensure the integrity and availability of information, the Contractor must use sound: System/software management; engineering and development; and secure-coding practices consistent with USAID standards and information security best practices. Rigorous security safeguards, including but not limited to, virus protection; network intrusion detection and prevention programs; and vulnerability management systems must be implemented and critical security issues must be resolved as quickly as possible or within 30 calendar days. Contact the USAID Chief Information Security Officer (CISO) at ISSO@usaid.gov for specific standards and guidance. (8) The Contractor must conduct periodic vulnerability scans, mitigate all security risks PO 00000 Frm 00035 Fmt 4702 Sfmt 4702 10473 identified during such scans, and report subsequent remediation actions to CISO at ISSO@usaid.gov and COR within 30 calendar days from the date vulnerabilities are identified. The report must include disclosure of the tools used to conduct the scans. Alternatively, the contractor may authorize USAID CISO at ISSO@usaid.gov to conduct periodic vulnerability scans via its Web-scanning program. The sole purpose of USAID scanning will be to minimize security risks. The Contractor will be responsible for taking the necessary remediation action and reporting to USAID as specified above. (c) For general information, agency graphics, metadata, privacy policy, and Section 508 compliance requirements, refer to https://www.usaid.gov. (End of Clause) 5. Add section 752.239–XX to read as follows: ■ 752.239–XX Limitation on Acquisition of Information Technology. Insert the following clause in all solicitations and contracts unless the special contract requirement Information Technology Approval is included. Limitation on Acquisition of Information Technology (Date) (a) Definitions. As used in this contract: Information Technology means (1) Any services or equipment, or interconnected system(s) or subsystem(s) of equipment, that are used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the agency; where (2) such services or equipment are ‘‘used by an agency’’ if used by the agency directly or if used by a contractor under a contract with the agency that requires either use of the services or equipment or requires use of the services or equipment to a significant extent in the performance of a service or the furnishing of a product. (3) The term ‘‘information technology’’ includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including provisioned services such as cloud computing and support services that support any point of the lifecycle of the equipment or service), and related resources. (4) The term ‘‘information technology’’ does not include any equipment that is acquired by a contractor incidental to a contract that does not require use of the equipment. (b) The Federal Information Technology Acquisition Reform Act (FITARA) requires Agency Chief Information Officer (CIO) review and approval of contracts that include information technology or information technology services. E:\FR\FM\21MRP1.SGM 21MRP1 10474 Federal Register / Vol. 84, No. 55 / Thursday, March 21, 2019 / Proposed Rules (c) The Contractor must not acquire information technology as defined in this clause without the prior written approval by the contracting officer as specified in this clause. (d) Request for Approval Requirements: (1) If the Contractor determines that any information technology will be necessary to meet the Government’s requirements or to facilitate activities in the Government’s statement of work, the Contractor must request prior written approval from the Contracting Officer. (2) As part of the request, the Contractor must provide the Contracting Officer a description and an estimate of the total cost of the information technology equipment, software, or services to be procured under this contract. The Contractor must simultaneously notify the Contracting Officer’s Representative (COR) and the Office of the Chief Information Office at ITAuthorization@usaid.gov. (e) The Contracting Officer will provide written approval to the Contractor through modification to the contract expressly specifying the information technology equipment, software, or services approved for purchase by the COR and the Agency CIO. The Contracting Officer will include the applicable clauses and any special contract requirements in the modification. (f) Except as specified in the contracting officer’s written approval, the Government is not obligated to reimburse the Contractor for any costs incurred for information technology as defined in this clause. Such approval does not relieve the Contractor from the responsibility to maintain current compliance at all times—including through any updates or modifications to the information technology—with all terms and conditions of the contract, as well as relevant statutes and regulations. (g) The Contractor must insert the substance of this clause, including this paragraph (g), in all subcontracts. (End of Clause) ■ 6. Add section 752.239–XX to read as follows: 752.239–XX Software License. Insert the following clause in solicitations and contracts for new software licenses or to renew existing licenses, and in solicitations and contracts which may include a requirement for new software licenses or renewal of existing licenses. amozie on DSK9F9SC42PROD with PROPOSALS Software License Addendum (Date) (a) This clause incorporates certain terms and conditions relating to Federal procurement actions. The terms and conditions of this Addendum take precedence over the terms and conditions contained in any license agreement or other contract documents entered into between the parties. (b) Governing Law: Federal procurement law and regulations, including the Contract Disputes Act, 41 U.S.C. 601 et seq., and the Federal Acquisition Regulation (FAR), govern VerDate Sep<11>2014 17:18 Mar 20, 2019 Jkt 247001 the agreement between the parties. Litigation arising out of this contract may be filed only in those fora that have jurisdiction over Federal procurement matters. (c) Attorney’s Fees: Attorney’s fees are payable by the Federal government in any action arising under this contract only pursuant to the Equal Access in Justice Act, 5 U.S.C. 504. (d) No Indemnification: The Federal government will not be liable for any claim for indemnification; such payments may violate the Anti-Deficiency Act, 31 U.S.C. 1341(a). (e) Assignment: Payments may only be assigned in accordance with the Assignment of Claims Act, 31 U.S.C. 3727, and FAR Subpart 32.8, ‘‘Assignment of Claims.’’ (f) Patent and Copyright Infringement: Patent or copyright infringement suits brought against the United States as a party may only be defended by the U.S. Department of Justice (28 U.S.C. 516). (g) Renewal of Support after Expiration of this Award: Service will not automatically renew after expiration of the initial term of award. (h) Renewal may only occur in accord with (1) the mutual agreement of the parties; or (2) an option renewal clause allowing the Government to unilaterally exercise one or more options to extend the term of the award. (1) Section 1194.21 Software applications and operating systems (2) 1194.22 Web-based intranet and internet information and applications; (3) Section 1194.23 Telecommunications products; (4) Section 1194.24 Video and multimedia products; (5) Section 1194.25 Self-contained, closed products; (6) Section 1194.26 Desktop and portable computers; (7) Section 1194.31 Functional performance criteria; and (8) Section 1194.41 Information, documentation, and support. (c) Deliverable(s) must incorporate these standards as well. (d) The final work product must include documentation that the deliverable conforms with the Section 508 Standards promulgated by the US Access Board. (End of Clause) ■ 8. Add section 752.239–XX to read as follows: 752.239–XX Use of Information Technology Approval. (End of Clause) ■ 7. Add section 752.239–72 to read as follows: Insert the following clause in all USAID solicitations and contracts for Information Technology (IT) services or supplies or include a requirement for the contractor to provide IT services or supplies. 752.239–72 Information and Communication Technology Accessibility. Use of Information Technology Notification (Date) Insert the following clause in solicitations and contracts that include acquisition of Information and Communication Technology (ICT) supplies and/or services for use by Federal employees or U.S. members of the public. Information and Communication Technology Accessibility (Date) (a) Federal agencies are required by Section 508 of the Rehabilitation Act of 1973, as amended (29 U.S.C. 794d), to offer access to information and communication technology for disabled individuals within its employment, and for disabled members of the public seeking information and services. This access must be comparable to that which is offered to similar individuals who do not have disabilities. Standards for complying with this law are prescribed by the Architectural and Transportation Barriers Compliance Board (‘‘The Access Board’’) in 36 CFR part 1194, which implements Section 508 of the Rehabilitation Act of 1973, as amended, and is viewable at https:// www.access-board.gov/sec508/508 standards.htm. The contractor must comply with any future updates of standards by the Access Board. (b) Except as indicated elsewhere in the contract, all ICT procured through this contract must meet the applicable accessibility standards at 36 CFR part 1194 as follows: PO 00000 Frm 00036 Fmt 4702 Sfmt 4702 (a) Definitions. As used in this contract: Information Technology means (1) Any services or equipment, or interconnected system(s) or subsystem(s) of equipment, that are used in the automatic acquisition, storage, analysis, evaluation, manipulation, management, movement, control, display, switching, interchange, transmission, or reception of data or information by the agency; where (2) Such services or equipment are ‘‘used by an agency’’ if used by the agency directly or if used by a contractor under a contract with the agency that requires either use of the services or equipment or requires use of the services or equipment to a significant extent in the performance of a service or the furnishing of a product. (3) The term ‘‘information technology’’ includes computers, ancillary equipment (including imaging peripherals, input, output, and storage devices necessary for security and surveillance), peripheral equipment designed to be controlled by the central processing unit of a computer, software, firmware and similar procedures, services (including provisioned services such as cloud computing and support services that support any point of the lifecycle of the equipment or service), and related resources. (4) The term ‘‘information technology’’ does not include any equipment that is acquired by a contractor incidental to a contract that does not require use of the equipment. (OMB M–15–14) (b) The Federal Information Technology Acquisition Reform Act (FITARA) requires E:\FR\FM\21MRP1.SGM 21MRP1 Federal Register / Vol. 84, No. 55 / Thursday, March 21, 2019 / Proposed Rules amozie on DSK9F9SC42PROD with PROPOSALS Agency Chief Information Officer (CIO) review and approval of contracts or interagency agreements for information technology or information technology services. (c) The approved information technology and/or information technology services are specified in the Schedule of this contract. The Contractor must not acquire additional information technology without the prior written approval of the Contracting Officer as specified in this clause. (d) Request for Approval Requirements: (1) If the Contractor determines that any information technology in addition to that information technology specified in the Schedule will be necessary to meet the Government’s requirements or to facilitate activities in the Government’s statement of work, the Contractor must request prior written approval from the Contracting Officer. (2) As part of the request, the Contractor must provide the Contracting Officer a description and an estimate of the total cost of the information technology equipment, software, or services to be procured under this contract. The Contractor must simultaneously notify the Contracting Officer’s Representative (COR) and the Office of the Chief Information Officer at ITAuthorization@usaid.gov. (e) The Contracting Officer will provide written approval to the Contractor expressly specifying the information technology equipment, software, or services approved for purchase by the COR and the Agency CIO. Additional clauses or special contract requirements may be applicable and will be VerDate Sep<11>2014 17:18 Mar 20, 2019 Jkt 247001 incorporated by the Contracting Officer through a modification to the contract. (f) Except as specified in the Contracting Officer’s written approval, the Government is not obligated to reimburse the Contractor for costs incurred in excess of the information technology equipment, software or services specified in the Schedule. Such approval does not relieve the Contractor from the responsibility to maintain current compliance at all times—including through any updates or modifications to the information technology—with meeting all terms and conditions of the contract, as well as relevant statutes and regulations. (d) The Contractor must insert the substance of this clause, including this paragraph (g), in all subcontracts. (End of Clause) ■ 9. Add section 752.239–XX to read as follows: 752.239–XX Skills and Certification Requirements for Privacy and Security Staff. Insert the following clause in solicitations and contracts for Information Technology (IT) services and in solicitations and contracts that include a component for IT services. Skills and Certification Requirements for Privacy and Security Staff (Date) (a) Applicability: This clause applies to the Contractor, its subcontractors and personnel providing support under this contract and PO 00000 Frm 00037 Fmt 4702 Sfmt 9990 10475 addresses the Privacy Act of 1974 (5 U.S.C. 552a—the Act) and Federal Information Security Management Act (FISMA) of 2002 (FISMA, Pub. L. 107–347. 44 U.S.C. 3531– 3536). (b) Contractor personnel filling the role of Information System Security Officer and Information Security Specialists must possess a Certified Information Systems Security Professional (CISSP) certification at time of contract award and maintain their certification throughout the period of performance. This will fulfill the requirements for specialized training due to the continuing education requirements for the certification. Contractor personnel must provide proof of their certification status upon request. (c) Contractor personnel filling the role of Privacy Analysts must possess a Certified Information Privacy Professional (CIPP) credential with a CIPP/USat the time of the contract award and must maintain the credential throughout the period of performance. This will fulfill the requirements for specialized training due to the continuing education requirements for the certification. Contractor personnel must provide proof of their certification status upon request. (End of Clause) Mark Walther, Chief Acquisition Officer, Acting. [FR Doc. 2019–04654 Filed 3–20–19; 8:45 am] BILLING CODE 6116–02–P E:\FR\FM\21MRP1.SGM 21MRP1

Agencies

[Federal Register Volume 84, Number 55 (Thursday, March 21, 2019)]
[Proposed Rules]
[Pages 10469-10475]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-04654]


=======================================================================
-----------------------------------------------------------------------

AGENCY FOR INTERNATIONAL DEVELOPMENT

48 CFR Parts 739 and 752

[0412-AA87]


United States Agency for International Development Acquisition 
Regulation (AIDAR): Security and Information Technology Requirements

AGENCY: U.S. Agency for International Development.

ACTION: Proposed rule.

-----------------------------------------------------------------------

SUMMARY: The U.S. Agency for International Development (USAID) seeks 
public comment on a proposed rule that would amend the USAID 
Acquisition Regulation (AIDAR) to incorporate a revised definition of 
information technology and other requirements relating to information 
security and information technology approvals. The Federal Information 
Technology Acquisition Reform Act requires improved management of the 
acquisition of Information technology resources. This proposed rule 
revising the AIDAR, if adopted, would provide increased oversight of 
contractor acquisition and use of information technology resources.

DATES: Comments must be received no later than May 20, 2019.

ADDRESSES: Address all comments concerning this notice to Carol 
Ketrick, Bureau for Management, Office of Acquisition and Assistance, 
Policy

[[Page 10470]]

Division (M/OAA/P), Room 867F, SA-44, Washington, DC 20523-2052. Submit 
comments, identified by title of the action and Regulatory Information 
Number (RIN) by any of the following methods:
    1. Through the Federal eRulemaking Portal at https://www.regulations.gov by following the instructions for submitting 
comments.
    2. By Mail addressed to: USAID, Bureau for Management, Office of 
Acquisition & Assistance, Policy Division, Room 867-F, SA-44, 
Washington, DC 20523-2052.
    Comments on the information collection request under Section E, 
Paperwork Reduction Act must be submitted to both USAID and OMB/OIRA as 
follows:
    USAID--Carol Ketrick at cketrick@usaid.gov.
    OMB/OIRA--email to oira_submission@omb.eop.gov, fax to (202) 395-
6974, or mail to the Office of Information and Regulatory Affairs, 
Office of Management and Budget, 725 17th Street NW, Washington, DC 
20503.

FOR FURTHER INFORMATION CONTACT: Carol Ketrick, Telephone: 202-567-4676 
or email: cketrick@usaid.gov.

SUPPLEMENTARY INFORMATION: 

A. Instructions

    All comments must be in writing and submitted through one of the 
methods specified in the Addresses section above. All submissions (and 
attachments) must include the title of the action and RIN for this 
rulemaking. Please include your name, title, organization, postal 
address, telephone number, and email address in the text of the 
message.
    Please note that USAID recommends sending all comments to the 
Federal eRulemaking Portal because security screening precautions have 
slowed the delivery and dependability of surface mail to USAID/
Washington.
    All comments will be made available at https://www.regulations.gov 
for public review without change, including any personal information 
provided. We recommend that you do not submit information that you 
consider Confidential Business Information (CBI) or any information 
that is otherwise protected from disclosure by statute.
    USAID will only address comments that explain why this proposed 
rule would be inappropriate, ineffective, or unacceptable without a 
change. Comments that are insubstantial or outside the scope of the 
rule may not be considered.

B. Background

    On September 5, 2014, the Office of Management and Budget (OMB) and 
the National Security Council (NSC) convened a President's Management 
Council, with one of the focus areas being improvement of cybersecurity 
in Federal acquisitions, in particular, accountability of contractors 
providing IT systems and services to the Federal government.
    Accordingly, USAID is taking steps to address information security 
for information and information systems that support the operations and 
assets of the agency, including those managed by contractors. The new 
requirements will strengthen protections of Agency information systems/
facilities.
    Following the cybersecurity review directed by OMB ``Follow-Up to 
President's Management Council Cybersecurity Meeting, September 5, 
2014'', which was completed by the agency Office of the Chief of 
Information Officer (CIO) in October 2014, a revised clause 752.204-72 
Access to USAID facilities and USAID's Information Systems (now titled 
Homeland Security Presidential Directive-12 (HSPD-12) and Personal 
Identity Verification (PIV)), and new special contract requirements 
were developed and implemented on an interim basis under USAID 
Acquisition and Assistance Policy Directive (AAPD) 16-02 SPECIAL 
CONTRACT REQUIREMENTS FOR INFORMATION TECHNOLOGY (IT) on May 3, 2016. 
The requirements in the AAPD were updated and reissued as AAPD 16-02 
(Revised) on May 1, 2018. The policy published in the AAPD 16-02 
(Revised) provides a new definition of information technology, and 
includes various requirements applicable to information and system 
security, as well as requirements for Electronic and Information 
Technology Accessibility, software licenses, and prior agency approval 
of IT purchases.
    This AIDAR proposed rule, when finalized and effective, will 
establish the new definition, the revised AIDAR clause 752.204-72 
Homeland Security Presidential Directive-12 (HSPD-12) and Personal 
Identity Verification (PIV), and AIDAR clauses based on some of the 
special contract requirements from the AAPD 16-02 (Revised). The 
remaining special contract requirements regarding information and 
system security in AAPD 16-02 (Revised) that are not included in this 
proposed rule will be assessed after finalization of the currently open 
FAR cases on Controlled Unclassified Information (CUI) and Breaches of 
Personally Identifiable Information (PII). In addition to the contract 
requirements originating from the AAPD 16-02 (Revised), a proposed 
clause providing requirements for development and/or maintenance of 
third-party USAID-financed websites is included in the rule.
    Accordingly, USAID is proposing to amend the U.S. Agency for 
International Development (USAID) Acquisition Regulation (AIDAR) to 
revise various sections that will implement policy and procedures for 
contracts and orders for, or include a requirement for, information 
technology (IT) supplies, services and/or systems. These requirements 
will ensure that contractors comply with the current Agency IT 
policies. The requirements in this proposed rule would implement the 
requirements under the following authorities: The E-Government Act of 
2002; Federal Information Technology Acquisition Reform ACT (FITARA) 
(Section 831 of the National Defense Authorization Act for Fiscal Year 
2015, Pub. L. 113-291) and; Section 508 of the Rehabilitation Act of 
1973, as amended (29 U.S.C. 794d) (``Section 508''); Privacy Act of 
1974 (5 U.S.C. 552a--the Act); Federal Information Security Management 
Act (FISMA) of 2002 (FISMA, Pub. L. 107-347. 44 U.S.C. 3531-3536); 
National Institute of Standards and Technology (NIST) Special 
Publication 800-53 revision 4 or the current version; and Office of 
Management and Budget (OMB) Circular A-130.
    USAID proposes to add AIDAR subpart 739, revise AIDAR 752.204-72, 
and include new clauses as follows:
     FAR subpart 739 provides the Agency definition of 
``information technology'' as issued in AAPD 16-02 (Revised). As part 
of the AAPD 16-02 (Revised), a Class Deviation to FAR Part 2.101(b) 
definition of ``information technology'' was approved by the head of 
the contracting activity. This new definition broadens and clarifies 
the definition to include services such as cloud services; it is 
derived from the definition set forth in the Office of Management and 
Budget's (OMB's) guidance at OMB Memo M-15-14, Management Oversight of 
Federal Information Technology dated June 10, 2015. AIDAR 739.2 adds 
this definition, which also appears at 752.239-XX Use of Information 
Technology Approval and 752.239-XX Limitation on Use of Information 
Technology.
     AIDAR Clause 752.204-72 Access to USAID Facilities and 
USAID's Information Systems is being replaced in its entirety with a 
new title Homeland Security Presidential Directive-12 (HSPD-12) and 
Personal

[[Page 10471]]

Identity Verification (PIV) and significant changes to reflect 
additional restrictions and reporting to better implement Homeland 
Security Presidential Directive-12 (HSPD-12) (August 27, 2004) and PIV 
procedures.
    The revision improves requirements for contractor personnel 
provided access to agency facilities and information systems, as well 
as timely monitoring of such access when the employee's employment is 
terminated. The revised clause requires submission of staff reports 
listing employees that require access to USAID facilities or 
information systems, and also specifies the Agency's authority to 
suspend or terminate the access to any systems and/or facilities if an 
Information Security Incident or other electronic access violation, 
use, or misuse incident gives cause for such action.
     AIDAR 752.204-XX USAID-Financed Third-party websites 
requires that Contractors adhere to certain requirements when 
developing, launching, and maintaining a third-party website funded by 
USAID for the purpose of meeting the project implementation goals. This 
applies to sites hosted on environments external to USAID boundaries 
and not directly controlled by USAID policies and staff. The clause 
requires adherence to Agency branding requirements and limits the 
contractor to collecting only the amount of information necessary to 
complete the specific business need as required by statute, regulation, 
or Executive Order.
     AIDAR 752.239-XX Limitation on Information Technology 
prohibits the acquisition of information technology under an award as 
defined in the clause unless prior approval is obtained from the 
contracting officer.
    The clause ensures that only information technology approved by the 
Agency Chief Information officer (CIO) is acquired, pursuant to the 
Federal Information Technology Acquisition Reform ACT (FITARA)(Section 
831 of the National Defense Authorization Act for Fiscal Year 2015, 
Pub. L. 113-291). All agency IT investment decisions, including 
software and IT equipment, must be made consistent with the agency's 
enterprise architecture. USAID must consider the total cost of 
ownership including the costs associated with risk issues, including 
security and privacy of data, and the costs of ensuring security of the 
IT system itself.
    This clause is consistent with the guidance promulgated by OMB in 
support of the Federal Information Technology Acquisition Reform Act 
(FITARA) and related information technology (IT) management practices 
in OMB Memo M-15-14 Management Oversight of Federal Information 
Technology.
     AIDAR 752.239-XX Software License addresses the need to 
ensure that acquired software is aligned with the agency's enterprise 
architecture; it will also enable the Agency to consolidate licenses 
when appropriate in alignment with OMB Category Management Policy 16-1.
    The clause clarifies that renewal of software licenses may only 
occur in accordance with the mutual agreement of the parties; or an 
option renewal clause allowing the Government to unilaterally exercise 
one or more options to extend the term of the award. Since renewal of a 
software license would require the obligation of funds by the Federal 
Government, renewal must not be automatic.
    Commercial off the shelf software solutions are offered to the 
public under standard agreements that may take a variety of forms, 
including license agreements, terms of service (TOS), terms of sale or 
purchase, and similar agreements. Customarily, these standard 
agreements contain terms and conditions that are appropriate when the 
purchaser is a private party but are inappropriate when the purchaser 
is the Federal Government.
     AIDAR 752.239-XX Information and Communication Technology 
(ICT) Accessibility requires contractors to implement Section 508 of 
the Rehabilitation Act of 1973, as amended (29 U.S.C. 794d) (``Section 
508''). This clause applies to all development, procurement, 
maintenance, and information communication technology for use by USAID 
and members of the U.S. public.
     AIDAR 752.239-XX Information Technology Approval requires 
that contractors acquire only the information technology specified in 
the contract, and specifies a process to request approval if the 
Contractor determines that acquisition of information technology is 
necessary to meet the Government's requirements under the award. The 
clause ensures that only information technology approved by the Agency 
Chief Information Officer (CIO) is acquired, pursuant to the Federal 
Information Technology Acquisition Reform ACT (FITARA)(Section 831 of 
the National Defense Authorization Act for Fiscal Year 2015, Pub. L. 
113-291). All agency IT investment decisions, including software and IT 
equipment, must be made consistent with the agency's enterprise 
architecture. USAID must consider the total cost of ownership including 
the costs associated with risk issues, including security and privacy 
of data, and the costs of ensuring security of the IT system itself.
    This clause is consistent with the guidance promulgated by OMB in 
support of the Federal Information Technology Acquisition Reform Act 
(FITARA) and related information technology (IT) management practices 
in OMB Memo M-15-14 Management Oversight of Federal Information 
Technology.
     AIDAR 752.239-XX Skills and Certification Requirements for 
Privacy and Security Staff requires that Contractor personnel 
performing the roles of Information System Security Officer and 
Information Security Specialists possess a Certified Information 
Systems Security Professional (CISSP) certification. All USAID 
contractors who have significant information security responsibilities 
as defined by OPM 5 CFR part 930 must complete specialized IT security 
training.
    Additionally, contractor personnel filling the role of Privacy 
Analysts must possess a Certified Information Privacy Professional 
(CIPP) credential with a CIPP/US to ensure that Privacy Analysts have 
the expertise required to implement U.S. government privacy laws, 
regulations and policies specific to government practice.

C. Regulatory Planning and Review

    This proposed rule has been determined to be ``nonsignificant'' 
under Executive Order 12866, Regulatory Planning and Review, dated 
September 30, 1993 and, therefore, is not subject to review.
    This proposed rule is not a major rule under 5 U.S.C. 804.

D. Regulatory Flexibility Act

    The proposed rule does not have a significant economic impact on a 
substantial number of small entities within the meaning of the 
Regulatory Flexibility Act, 5 U.S.C. 601, et seq. Therefore, an Initial 
Regulatory Flexibility Analysis has not been performed.

E. Paperwork Reduction Act

    The Paperwork Reduction Act (44 U.S.C. chapter 35) applies. The 
proposed rule contains an information collection requirement. 
Accordingly, USAID has submitted a request to the Office of Management 
and Budget for approval of a new information collection requirement 
concerning ``Access to USAID Facilities and USAID's Information 
Systems'' and the

[[Page 10472]]

monthly reports of employees requiring access.

Access to USAID Facilities and USAID's Information Systems

    Public reporting burden for this collection of information is 
estimated to average initially eight hours immediately after contract 
award to develop the list of employee's requiring access, then 2 hours 
per month to update such a list, including the time for reviewing 
instructions, gathering/maintaining the employee names, and forwarding 
the list to the agency for processing. The recordkeeping requirements 
are minor. While a contractor is required to identify and submit the 
list of its employees who require access, there is no requirement to 
collect this information in a particular format for submission to the 
agency.
    The annual reporting burden is estimated as follows:
    Total number of respondents and the amount of time estimated for an 
average respondent to respond: 138 contractors; eight hours for the 
initial report, 24 hours annually thereafter for submission of the 
monthly reports.
    Total public burden (in hours) associated with the collection: 
1,104 hours initially, and 3,312 hours annually thereafter.
    Total public burden (in cost) associated with the collection: 
Initial submission, $54,537, then $163,613 annually thereafter.
    When submitting comments on these information collections, your 
comments should address one or more of the following four points:
    (1) Evaluate whether the proposed collection of information is 
necessary for the proper performance of the functions of the agency, 
including whether the information will have practical utility;
    (2) Evaluate the accuracy of the agency's estimate of the burden of 
the proposed collection of information, including the validity of the 
methodology and assumptions used;
    (3) Ways to enhance the quality, utility, and clarity of the 
information to be collected; and
    (4) Ways which USAID can minimize the burden of the collection of 
information on those who are to respond, including through the use of 
appropriate automated, electronic, mechanical, or other technological 
collection techniques or other forms of information technology, e.g., 
permitting electronic submission of responses.

List of Subjects in 48 CFR parts 739 and 752

    Government procurement.

    For the reasons discussed in the preamble, USAID proposes to amend 
48 CFR Parts 739 and 752 as set forth below:

0
1. Add part 739 to read as follows:

PART 739--Acquisition of Information Technology

Sec.
739.002 Definitions
739.003 [Reserved]

    Authority:  Sec. 621, Pub. L. 87-195, 75 Stat. 445, (22 U.S.C. 
2381) as amended; E.O. 12163, Sept. 29, 1979, 44 FR 56673; and 3 CFR 
1979 Comp., p. 435.


739.002  Definitions.

    As used in this part--
    Information Technology means
    (1) Any services or equipment, or interconnected system(s) or 
subsystem(s) of equipment, that are used in the automatic acquisition, 
storage, analysis, evaluation, manipulation, management, movement, 
control, display, switching, interchange, transmission, or reception of 
data or information by the agency; where
    (2) Such services or equipment are ``used by an agency'' if used by 
the agency directly or if used by a contractor under a contract with 
the agency that requires either use of the services or equipment or 
requires use of the services or equipment to a significant extent in 
the performance of a service or the furnishing of a product.
    (3) The term ``information technology'' includes computers, 
ancillary equipment (including imaging peripherals, input, output, and 
storage devices necessary for security and surveillance), peripheral 
equipment designed to be controlled by the central processing unit of a 
computer, software, firmware and similar procedures, services 
(including provisioned services such as cloud computing and support 
services that support any point of the lifecycle of the equipment or 
service), and related resources.
    (4) The term ``information technology'' does not include any 
equipment that is acquired by a contractor incidental to a contract 
that does not require use of the equipment.


739.003  [Reserved]

PART 752--SOLICITATION PROVISIONS AND CONTRACT CLAUSES

0
2. The authority for part 752 continues to read as follows:

    Authority: Sec. 621, Pub. L. 87-195, 75 Stat. 445, (22 U.S.C. 
2381) as amended; E.O. 12163, Sept. 29, 1979, 44 FR 56673; and 3 CFR 
1979 Comp., p. 435.

0
3. Amend section 752.204-72 by revising the section heading and the 
clause to read as follows:


752.204-72  Homeland Security Presidential Directive-12 (HSPD-12) and 
Personal Identity Verification (PIV).

* * * * *

Homeland Security Presidential Directive-12 (HSPD-12) and Personal 
Identity Verification (PIV) (Date)

    (a) Individuals engaged in the performance of this award as 
employees, consultants, or volunteers of the contractor must comply 
with all applicable HSPD-12 and PIV procedures, as described below, 
and any subsequent USAID or Government-wide HSPD-12 and PIV 
procedures/policies.
    (b) A U.S. citizen or resident alien engaged in the performance 
of this award as an employee, consultant, or volunteer of a U.S firm 
may obtain access to USAID facilities or logical access to USAID's 
information systems only when and to the extent necessary to carry 
out this award and in accordance with this clause. The contractor's 
employees, consultants, or volunteers who are not U.S. citizens or 
resident aliens as well as employees, consultants, or volunteers of 
non-U.S. firms, irrespective of their citizenship, will not be 
granted logical access to U.S. Government information technology 
systems (such as Phoenix, GLAAS, etc.) and must be escorted to use 
U.S. Government facilities (such as office space).
    (c) (1) No later than five business days after award, the 
Contractor must provide to the Contracting Officer's Representative 
(COR) a complete list of employees that require access to USAID 
facilities or information systems.
    (2) Before a contractor (or a contractor employee, consultant, 
or volunteer) or subcontractor at any tier may obtain a USAID ID 
(new or replacement) authorizing the individual routine access to 
USAID facilities in the United States, or logical access to USAID's 
information systems, the individual must provide two forms of 
identity source documents in original form to the Enrollment Office 
personnel when undergoing processing. One identity source document 
must be a valid Federal or State Government-issued picture ID. 
Contractors may contact the USAID Security Office to obtain the list 
of acceptable forms of documentation. Submission of these documents, 
to include documentation of security background investigations, is 
mandatory in order for the contractor to receive a PIV or PIV-
Alternative (PIV-A)/Facilities Access Card (FAC) card and be granted 
access to any of USAID's information systems. All such individuals 
must physically present these two source documents for identity 
proofing at their enrollment.
    (d) The Contractor must send a staffing report to the COR by the 
fifth day of each month. The report must contain the listing of

[[Page 10473]]

all staff members with access who were separated or hired under this 
contract in the past sixty (60) calendar days. This report must be 
submitted even if no separations or hiring occurred during the 
reporting period. Failure to submit the `Contractor Staffing Change 
Report' each month may, at USAID's discretion, result in the 
suspension of all logical access to USAID information systems and/or 
facilities access associated with this contract. USAID will provide 
the contractor the format for this report.
    (e) Contractor employees are strictly prohibited from sharing 
logical access to USAID information systems and Sensitive 
Information. USAID will disable accounts and revoke logical access 
to USAID IT systems if Contractor employees share accounts.
    (f) USAID, at its discretion, may suspend or terminate the 
access to any systems and/or facilities when an Information Security 
Incident or electronic access violation, use, or misuse incident 
gives cause for such action. The suspension or termination may last 
until such time as USAID determines that the situation has been 
corrected or no longer exists.
    (g) The Contractor must notify the COR and the USAID Service 
Desk at least five business days prior to the Contractor employee's 
removal from the contract. For unplanned terminations of Contractor 
employees, the Contractor must immediately notify the COR and the 
USAID Service Desk (CIO-HELPDESK@usaid.gov or (202) 712-1234). The 
Contractor or its Facilities Security Officer must return USAID PIV/
FAC cards and remote authentication tokens issued to Contractor 
employees to the COR prior to departure of the employee or upon 
completion or termination of the contract, whichever occurs first.
    (h) The contractor is required to insert this clause (including 
this paragraph (h) in any subcontracts that require the 
subcontractor, subcontractor employee, or consultant to have routine 
physical access to USAID space or logical access to USAID's 
information systems.
(End of Clause)
0
4. Add section 752.204-XX to read as follows:


752.204-XX   USAID-Financed Third-Party Websites.

    Insert the following clause in USAID-funded solicitations and 
contracts that require development and/or maintenance of a third-party 
website to achieve project implementation goals.

USAID-Financed Third-Party Websites (Date)

    (a) Definitions: ``Third-party websites''
    Websites hosted on environments external to USAID boundaries and 
not directly controlled by USAID policies and staff, except through 
the terms and conditions of a contract. Third-party websites include 
project websites.
    (b) The contractor must adhere to the following requirements 
when developing, launching, and maintaining a third-party website 
funded by USAID for the purpose of meeting the project 
implementation goals:
    (1) Prior to website development, the Contractor must provide 
information as required in Section C-Statement of Work of the 
contract (including a copy of their Contractor's privacy policy) to 
the Contracting Officer's Representative (COR), for USAID's Bureau 
for Legislative and Public Affairs (LPA) evaluation and approval. 
The Contractor must notify the COR of the website URL as far in 
advance of the site's launch as possible and must not launch the 
website until USAID's approval has been provided through the COR. 
The Contractor must provide the COR any changes to the Contractor's 
privacy policy for the duration of the contract.
    (2) The Contractor must collect only the amount of information 
necessary to complete the specific business need as required by 
statute, regulation, or Executive Order.
    (3) The Contractor must comply with Agency branding and marking 
requirements comprised of the USAID logo and brandmark with the 
tagline ``from the American people,'' located on the USAID website 
at www.usaid.gov/branding, and USAID Graphics Standards manual at 
https://www.usaid.gov.
    (4) The website must be marked on the index page of the site and 
every major entry point to the website with a disclaimer that 
states:
    ``The information provided on this website is not official U.S. 
Government information and does not represent the views or positions 
of the U.S. Agency for International Development or the U.S. 
Government.''
    (5) The website must provide persons with disabilities access to 
information that is comparable to the access available to others. As 
such, all site content must be compliant with the requirements of 
the Section 508 of the Rehabilitation Act, as amended (29 U.S.C. 
794d) (``Section 508'') and other terms and conditions of the 
contract.
    (6) The Contractor must identify and provide to the COR, in 
writing, the contact information for the Contractor's information 
security point of contact. The contractor is responsible for 
updating the contact information whenever there is a change in 
personnel assigned to this role.
    (7) The Contractor must provide adequate protection from 
unauthorized access, alteration, disclosure, or misuse of 
information processed, stored, or transmitted on the websites. To 
minimize security risks and ensure the integrity and availability of 
information, the Contractor must use sound: System/software 
management; engineering and development; and secure-coding practices 
consistent with USAID standards and information security best 
practices. Rigorous security safeguards, including but not limited 
to, virus protection; network intrusion detection and prevention 
programs; and vulnerability management systems must be implemented 
and critical security issues must be resolved as quickly as possible 
or within 30 calendar days. Contact the USAID Chief Information 
Security Officer (CISO) at ISSO@usaid.gov for specific standards and 
guidance.
    (8) The Contractor must conduct periodic vulnerability scans, 
mitigate all security risks identified during such scans, and report 
subsequent remediation actions to CISO at ISSO@usaid.gov and COR 
within 30 calendar days from the date vulnerabilities are 
identified. The report must include disclosure of the tools used to 
conduct the scans. Alternatively, the contractor may authorize USAID 
CISO at ISSO@usaid.gov to conduct periodic vulnerability scans via 
its Web-scanning program. The sole purpose of USAID scanning will be 
to minimize security risks. The Contractor will be responsible for 
taking the necessary remediation action and reporting to USAID as 
specified above.
    (c) For general information, agency graphics, metadata, privacy 
policy, and Section 508 compliance requirements, refer to https://www.usaid.gov.

(End of Clause)
0
5. Add section 752.239-XX to read as follows:


752.239-XX  Limitation on Acquisition of Information Technology.

    Insert the following clause in all solicitations and contracts 
unless the special contract requirement Information Technology Approval 
is included.

Limitation on Acquisition of Information Technology (Date)

    (a) Definitions. As used in this contract:
    Information Technology means
    (1) Any services or equipment, or interconnected system(s) or 
subsystem(s) of equipment, that are used in the automatic 
acquisition, storage, analysis, evaluation, manipulation, 
management, movement, control, display, switching, interchange, 
transmission, or reception of data or information by the agency; 
where
    (2) such services or equipment are ``used by an agency'' if used 
by the agency directly or if used by a contractor under a contract 
with the agency that requires either use of the services or 
equipment or requires use of the services or equipment to a 
significant extent in the performance of a service or the furnishing 
of a product.
    (3) The term ``information technology'' includes computers, 
ancillary equipment (including imaging peripherals, input, output, 
and storage devices necessary for security and surveillance), 
peripheral equipment designed to be controlled by the central 
processing unit of a computer, software, firmware and similar 
procedures, services (including provisioned services such as cloud 
computing and support services that support any point of the 
lifecycle of the equipment or service), and related resources.
    (4) The term ``information technology'' does not include any 
equipment that is acquired by a contractor incidental to a contract 
that does not require use of the equipment.
    (b) The Federal Information Technology Acquisition Reform Act 
(FITARA) requires Agency Chief Information Officer (CIO) review and 
approval of contracts that include information technology or 
information technology services.

[[Page 10474]]

    (c) The Contractor must not acquire information technology as 
defined in this clause without the prior written approval by the 
contracting officer as specified in this clause.
    (d) Request for Approval Requirements:
    (1) If the Contractor determines that any information technology 
will be necessary to meet the Government's requirements or to 
facilitate activities in the Government's statement of work, the 
Contractor must request prior written approval from the Contracting 
Officer.
    (2) As part of the request, the Contractor must provide the 
Contracting Officer a description and an estimate of the total cost 
of the information technology equipment, software, or services to be 
procured under this contract. The Contractor must simultaneously 
notify the Contracting Officer's Representative (COR) and the Office 
of the Chief Information Office at ITAuthorization@usaid.gov.
    (e) The Contracting Officer will provide written approval to the 
Contractor through modification to the contract expressly specifying 
the information technology equipment, software, or services approved 
for purchase by the COR and the Agency CIO. The Contracting Officer 
will include the applicable clauses and any special contract 
requirements in the modification.
    (f) Except as specified in the contracting officer's written 
approval, the Government is not obligated to reimburse the 
Contractor for any costs incurred for information technology as 
defined in this clause. Such approval does not relieve the 
Contractor from the responsibility to maintain current compliance at 
all times--including through any updates or modifications to the 
information technology--with all terms and conditions of the 
contract, as well as relevant statutes and regulations.
    (g) The Contractor must insert the substance of this clause, 
including this paragraph (g), in all subcontracts.

(End of Clause)
0
6. Add section 752.239-XX to read as follows:


752.239-XX   Software License.

    Insert the following clause in solicitations and contracts for new 
software licenses or to renew existing licenses, and in solicitations 
and contracts which may include a requirement for new software licenses 
or renewal of existing licenses.

Software License Addendum (Date)

    (a) This clause incorporates certain terms and conditions 
relating to Federal procurement actions. The terms and conditions of 
this Addendum take precedence over the terms and conditions 
contained in any license agreement or other contract documents 
entered into between the parties.
    (b) Governing Law: Federal procurement law and regulations, 
including the Contract Disputes Act, 41 U.S.C. 601 et seq., and the 
Federal Acquisition Regulation (FAR), govern the agreement between 
the parties. Litigation arising out of this contract may be filed 
only in those fora that have jurisdiction over Federal procurement 
matters.
    (c) Attorney's Fees: Attorney's fees are payable by the Federal 
government in any action arising under this contract only pursuant 
to the Equal Access in Justice Act, 5 U.S.C. 504.
    (d) No Indemnification: The Federal government will not be 
liable for any claim for indemnification; such payments may violate 
the Anti-Deficiency Act, 31 U.S.C. 1341(a).
    (e) Assignment: Payments may only be assigned in accordance with 
the Assignment of Claims Act, 31 U.S.C. 3727, and FAR Subpart 32.8, 
``Assignment of Claims.''
    (f) Patent and Copyright Infringement: Patent or copyright 
infringement suits brought against the United States as a party may 
only be defended by the U.S. Department of Justice (28 U.S.C. 516).
    (g) Renewal of Support after Expiration of this Award: Service 
will not automatically renew after expiration of the initial term of 
award.
    (h) Renewal may only occur in accord with (1) the mutual 
agreement of the parties; or (2) an option renewal clause allowing 
the Government to unilaterally exercise one or more options to 
extend the term of the award.

(End of Clause)
0
7. Add section 752.239-72 to read as follows:


752.239-72   Information and Communication Technology Accessibility.

    Insert the following clause in solicitations and contracts that 
include acquisition of Information and Communication Technology (ICT) 
supplies and/or services for use by Federal employees or U.S. members 
of the public.

Information and Communication Technology Accessibility

    (Date)

    (a) Federal agencies are required by Section 508 of the 
Rehabilitation Act of 1973, as amended (29 U.S.C. 794d), to offer 
access to information and communication technology for disabled 
individuals within its employment, and for disabled members of the 
public seeking information and services. This access must be 
comparable to that which is offered to similar individuals who do 
not have disabilities. Standards for complying with this law are 
prescribed by the Architectural and Transportation Barriers 
Compliance Board (``The Access Board'') in 36 CFR part 1194, which 
implements Section 508 of the Rehabilitation Act of 1973, as 
amended, and is viewable at https://www.access-board.gov/sec508/508standards.htm. The contractor must comply with any future updates 
of standards by the Access Board.
    (b) Except as indicated elsewhere in the contract, all ICT 
procured through this contract must meet the applicable 
accessibility standards at 36 CFR part 1194 as follows:
    (1) Section 1194.21 Software applications and operating systems
    (2) 1194.22 Web-based intranet and internet information and 
applications;
    (3) Section 1194.23 Telecommunications products;
    (4) Section 1194.24 Video and multimedia products;
    (5) Section 1194.25 Self-contained, closed products;
    (6) Section 1194.26 Desktop and portable computers;
    (7) Section 1194.31 Functional performance criteria; and
    (8) Section 1194.41 Information, documentation, and support.
    (c) Deliverable(s) must incorporate these standards as well.
    (d) The final work product must include documentation that the 
deliverable conforms with the Section 508 Standards promulgated by 
the US Access Board.

(End of Clause)
0
8. Add section 752.239-XX to read as follows:


752.239-XX  Use of Information Technology Approval.

    Insert the following clause in all USAID solicitations and 
contracts for Information Technology (IT) services or supplies or 
include a requirement for the contractor to provide IT services or 
supplies.

Use of Information Technology Notification (Date)

    (a) Definitions. As used in this contract:
    Information Technology means
    (1) Any services or equipment, or interconnected system(s) or 
subsystem(s) of equipment, that are used in the automatic 
acquisition, storage, analysis, evaluation, manipulation, 
management, movement, control, display, switching, interchange, 
transmission, or reception of data or information by the agency; 
where
    (2) Such services or equipment are ``used by an agency'' if used 
by the agency directly or if used by a contractor under a contract 
with the agency that requires either use of the services or 
equipment or requires use of the services or equipment to a 
significant extent in the performance of a service or the furnishing 
of a product.
    (3) The term ``information technology'' includes computers, 
ancillary equipment (including imaging peripherals, input, output, 
and storage devices necessary for security and surveillance), 
peripheral equipment designed to be controlled by the central 
processing unit of a computer, software, firmware and similar 
procedures, services (including provisioned services such as cloud 
computing and support services that support any point of the 
lifecycle of the equipment or service), and related resources.
    (4) The term ``information technology'' does not include any 
equipment that is acquired by a contractor incidental to a contract 
that does not require use of the equipment. (OMB M-15-14)
    (b) The Federal Information Technology Acquisition Reform Act 
(FITARA) requires

[[Page 10475]]

Agency Chief Information Officer (CIO) review and approval of 
contracts or interagency agreements for information technology or 
information technology services.
    (c) The approved information technology and/or information 
technology services are specified in the Schedule of this contract. 
The Contractor must not acquire additional information technology 
without the prior written approval of the Contracting Officer as 
specified in this clause.
    (d) Request for Approval Requirements:
    (1) If the Contractor determines that any information technology 
in addition to that information technology specified in the Schedule 
will be necessary to meet the Government's requirements or to 
facilitate activities in the Government's statement of work, the 
Contractor must request prior written approval from the Contracting 
Officer.
    (2) As part of the request, the Contractor must provide the 
Contracting Officer a description and an estimate of the total cost 
of the information technology equipment, software, or services to be 
procured under this contract. The Contractor must simultaneously 
notify the Contracting Officer's Representative (COR) and the Office 
of the Chief Information Officer at ITAuthorization@usaid.gov.
    (e) The Contracting Officer will provide written approval to the 
Contractor expressly specifying the information technology 
equipment, software, or services approved for purchase by the COR 
and the Agency CIO. Additional clauses or special contract 
requirements may be applicable and will be incorporated by the 
Contracting Officer through a modification to the contract.
    (f) Except as specified in the Contracting Officer's written 
approval, the Government is not obligated to reimburse the 
Contractor for costs incurred in excess of the information 
technology equipment, software or services specified in the 
Schedule. Such approval does not relieve the Contractor from the 
responsibility to maintain current compliance at all times--
including through any updates or modifications to the information 
technology--with meeting all terms and conditions of the contract, 
as well as relevant statutes and regulations.
    (d) The Contractor must insert the substance of this clause, 
including this paragraph (g), in all subcontracts.

(End of Clause)
0
9. Add section 752.239-XX to read as follows:


752.239-XX  Skills and Certification Requirements for Privacy and 
Security Staff.

    Insert the following clause in solicitations and contracts for 
Information Technology (IT) services and in solicitations and contracts 
that include a component for IT services.

Skills and Certification Requirements for Privacy and Security Staff 
(Date)

    (a) Applicability: This clause applies to the Contractor, its 
subcontractors and personnel providing support under this contract 
and addresses the Privacy Act of 1974 (5 U.S.C. 552a--the Act) and 
Federal Information Security Management Act (FISMA) of 2002 (FISMA, 
Pub. L. 107-347. 44 U.S.C. 3531-3536).
    (b) Contractor personnel filling the role of Information System 
Security Officer and Information Security Specialists must possess a 
Certified Information Systems Security Professional (CISSP) 
certification at time of contract award and maintain their 
certification throughout the period of performance. This will 
fulfill the requirements for specialized training due to the 
continuing education requirements for the certification. Contractor 
personnel must provide proof of their certification status upon 
request.
    (c) Contractor personnel filling the role of Privacy Analysts 
must possess a Certified Information Privacy Professional (CIPP) 
credential with a CIPP/USat the time of the contract award and must 
maintain the credential throughout the period of performance. This 
will fulfill the requirements for specialized training due to the 
continuing education requirements for the certification. Contractor 
personnel must provide proof of their certification status upon 
request.

(End of Clause)

Mark Walther,
Chief Acquisition Officer, Acting.
[FR Doc. 2019-04654 Filed 3-20-19; 8:45 am]
 BILLING CODE 6116-02-P