Tennessee Gas Pipeline Company, LLC; Notice of Request Under Blanket Authorization, 8701-8702 [2019-04331]
Download as PDF
amozie on DSK9F9SC42PROD with NOTICES
Federal Register / Vol. 84, No. 47 / Monday, March 11, 2019 / Notices
Kentucky 42234, by telephone at (270)
483–2511.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
3 copies of filings made in the
proceeding with the Commission and
must provide a copy to the applicant
and to every other party. Only parties to
the proceeding can ask for court review
of Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
VerDate Sep<11>2014
18:41 Mar 08, 2019
Jkt 247001
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list and will be
notified of any meetings associated with
the Commission’s environmental review
process. Environmental commenters
will not be required to serve copies of
filed documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission and will not have the right
to seek court review of the
Commission’s final order.
As of the February 27, 2018 date of
the Commission’s order in Docket No.
CP16–4–001, the Commission will
apply its revised practice concerning
out-of-time motions to intervene in any
new Natural Gas Act section 3 or section
7 proceeding.1 Persons desiring to
become a party to a certificate
proceeding are to intervene in a timely
manner. If seeking to intervene out-oftime, the movant is required to show
good cause why the time limitation
should be waived, and should provide
justification by reference to factors set
forth in Rule 214(d)(1) of the
Commission’s Rules and Regulations.2
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 3 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
Comment Date: 5:00 p.m. Eastern
Time on March 20, 2019.
Dated: February 27, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–04321 Filed 3–8–19; 8:45 am]
BILLING CODE 6717–01–P
1 Tennessee Gas Pipeline Company, L.L.C., 162
FERC 61,167 at 50 (2018).
2 18 CFR 385.214(d)(1).
PO 00000
Frm 00041
Fmt 4703
Sfmt 4703
8701
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–100–000]
Tennessee Gas Pipeline Company,
LLC; Notice of Request Under Blanket
Authorization
Take notice that on February 28, 2019,
Tennessee Gas Pipeline Company,
L.L.C. (Tennessee), 1001 Louisiana
Street, Houston, Texas 77002, filed in
the above referenced docket a prior
notice request pursuant to sections
157.205 and 157.211(a)(2) of the
Commission’s regulations under the
Natural Gas Act (NGA) and its blanket
certificate issued in Docket No. CP82–
413–000 for authorization to construct
and operate a new delivery point to
serve the Hanscom Air Force Base
(Hanscom) in Middlesex County,
Massachusetts. Tennessee has already
installed a three-inch-diameter hot tap
assembly pursuant to the authority
granted in Docket No. CP14–483–000.
Once Hanscom completes the associated
meter station on its property, Tennessee
proposes to install electronic gas
measurement equipment, a flow
computer, power communications
equipment, and measurement
appurtenances, all located at the meter
station site. Tennessee states that the
facilities will be able to delivery up to
9.5 million cubic feet of natural gas per
day at an estimated cost of
approximately $65,000, all as more fully
set forth in the request which is on file
with the Commission and open to
public inspection.
The filing is available for review at
the Commission in the Public Reference
Room or may be viewed on the
Commission’s website web at https://
www.ferc.gov using the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding this
application should be directed Ben J.
Carranza, Director—Regulatory,
Tennessee Gas Pipeline Company,
L.L.C., 1001 Louisiana Street, Houston,
Texas 77002, by telephone at (713) 420–
5535, or by email at ben_carranza@
kindermorgan.com.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
E:\FR\FM\11MRN1.SGM
11MRN1
amozie on DSK9F9SC42PROD with NOTICES
8702
Federal Register / Vol. 84, No. 47 / Monday, March 11, 2019 / Notices
of intervention and pursuant to section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the EA
for this proposal. The filing of the EA
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list and will be
notified of any meetings associated with
the Commission’s environmental review
process. Environmental commenters
will not be required to serve copies of
filed documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 3 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
VerDate Sep<11>2014
18:41 Mar 08, 2019
Jkt 247001
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–04331 Filed 3–8–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER19–1179–000]
AES ES Gilbert, LLC; Supplemental
Notice That Initial Market-Based Rate
Filing Includes Request for Blanket
Section 204 Authorization
This is a supplemental notice in the
above-referenced Innovative AES ES
Gilbert, LLC’s application for marketbased rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is March 25,
2019.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
electronic review in the Commission’s
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
Public Reference Room in Washington,
DC. There is an eSubscription link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–04314 Filed 3–8–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD19–8–000]
Notice of Workshop: America’s Water
Infrastructure Act of 2018
The Federal Energy Regulatory
Commission (FERC or Commission) staff
will hold a workshop on April 4, 2019,
from 1:00 p.m. (EDT) to 4:45 p.m. (EDT)
in the Commission Meeting Room at 888
First Street NE, Washington, DC 20426.
The workshop will be open to the
public, and all interested parties are
invited to attend and participate. The
workshop will be led by Commission
staff, and may be attended by one or
more Commissioners. The workshop
will involve roundtable discussions by
a number of panelists and moderated by
Commission staff.
The purpose of the workshop is to
explore potential opportunities for
development of closed-loop pumped
storage projects at abandoned mine sites
in compliance with section 3004 of the
America’s Water Infrastructure Act of
2018. An agenda for the workshop is
attached to this notice. There will be
time for audience questions and
comments following each agenda
discussion topic.
A free webcast of this event will be
available through www.ferc.gov. Anyone
with internet access who wants to view
this event can do so by navigating to the
Calendar of Events at www.ferc.gov and
locating this event in the Calendar. The
Capitol Connection provides technical
support for webcasts and offers the
option of listening to the workshop via
phone-bridge for a fee. If you have any
questions, visit
www.CapitolConnection.org or call (703)
993–3100.
Those interested in attending the
workshop or viewing the webcast are
encouraged to register at https://
E:\FR\FM\11MRN1.SGM
11MRN1
Agencies
[Federal Register Volume 84, Number 47 (Monday, March 11, 2019)]
[Notices]
[Pages 8701-8702]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-04331]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP19-100-000]
Tennessee Gas Pipeline Company, LLC; Notice of Request Under
Blanket Authorization
Take notice that on February 28, 2019, Tennessee Gas Pipeline
Company, L.L.C. (Tennessee), 1001 Louisiana Street, Houston, Texas
77002, filed in the above referenced docket a prior notice request
pursuant to sections 157.205 and 157.211(a)(2) of the Commission's
regulations under the Natural Gas Act (NGA) and its blanket certificate
issued in Docket No. CP82-413-000 for authorization to construct and
operate a new delivery point to serve the Hanscom Air Force Base
(Hanscom) in Middlesex County, Massachusetts. Tennessee has already
installed a three-inch-diameter hot tap assembly pursuant to the
authority granted in Docket No. CP14-483-000. Once Hanscom completes
the associated meter station on its property, Tennessee proposes to
install electronic gas measurement equipment, a flow computer, power
communications equipment, and measurement appurtenances, all located at
the meter station site. Tennessee states that the facilities will be
able to delivery up to 9.5 million cubic feet of natural gas per day at
an estimated cost of approximately $65,000, all as more fully set forth
in the request which is on file with the Commission and open to public
inspection.
The filing is available for review at the Commission in the Public
Reference Room or may be viewed on the Commission's website web at
https://www.ferc.gov using the eLibrary link. Enter the docket number
excluding the last three digits in the docket number field to access
the document. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
Any questions regarding this application should be directed Ben J.
Carranza, Director--Regulatory, Tennessee Gas Pipeline Company, L.L.C.,
1001 Louisiana Street, Houston, Texas 77002, by telephone at (713) 420-
5535, or by email at ben_carranza@kindermorgan.com.
Any person or the Commission's staff may, within 60 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice
[[Page 8702]]
of intervention and pursuant to section 157.205 of the regulations
under the NGA (18 CFR 157.205), a protest to the request. If no protest
is filed within the time allowed therefore, the proposed activity shall
be deemed to be authorized effective the day after the time allowed for
filing a protest. If a protest is filed and not withdrawn within 30
days after the allowed time for filing a protest, the instant request
shall be treated as an application for authorization pursuant to
section 7 of the NGA.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the EA for this proposal. The filing of the EA in the Commission's
public record for this proceeding or the issuance of a Notice of
Schedule for Environmental Review will serve to notify federal and
state agencies of the timing for the completion of all necessary
reviews, and the subsequent need to complete all federal authorizations
within 90 days of the date of issuance of the Commission staff's EA.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list and will be
notified of any meetings associated with the Commission's environmental
review process. Environmental commenters will not be required to serve
copies of filed documents on all other parties. However, the non-party
commenters will not receive copies of all documents filed by other
parties or issued by the Commission and will not have the right to seek
court review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the eFiling link at
https://www.ferc.gov. Persons unable to file electronically should
submit an original and 3 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street NE, Washington,
DC 20426.
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-04331 Filed 3-8-19; 8:45 am]
BILLING CODE 6717-01-P