Notice of Authorization for Continued Project Operation: Goodyear Lake Hydro, LLC, 8709-8710 [2019-04317]
Download as PDF
Federal Register / Vol. 84, No. 47 / Monday, March 11, 2019 / Notices
Additional Information
Additional information about the
projects are available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website (www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on General Search and enter the
docket number(s) in the Docket Number
field, excluding the last three digits (i.e.,
PF17–10 for the FM100 Project; PF19–
1 for the Leidy South Project). Be sure
you have selected an appropriate date
range. For assistance, please contact
FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at www.ferc.gov/EventCalendar/
EventsList.aspx along with other related
information.
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–04318 Filed 3–8–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2388–000]
amozie on DSK9F9SC42PROD with NOTICES
Notice of Authorization for Continued
Project Operation: City of Holyoke Gas
and Electric Department
On August 31, 2016, City of Holyoke
Gas and Electric Department, licensee
for the Holyoke No. 3 Hydroelectric
Project, filed an Application for a New
License pursuant to the Federal Power
Act (FPA) and the Commission’s
regulations thereunder. The Holyoke
No. 3 Hydroelectric Project is located
between the first and second canals
adjacent to the Connecticut River, in the
City of Holyoke in Hampton County,
Massachusetts.
The license for Project No. 2388 was
issued for a period ending February 20,
2019. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
VerDate Sep<11>2014
18:41 Mar 08, 2019
Jkt 247001
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2388
is issued to the licensee for a period
effective February 21, 2019 through
February 20, 2020, or until the issuance
of a new license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before February 20, 2020,
notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license
under section 15(a)(1) of the FPA is
renewed automatically without further
order or notice by the Commission,
unless the Commission orders
otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the licensee, City of Holyoke Gas
and Electric Department, Inc., is
authorized to continue operation of the
Holyoke No. 3 Hydroelectric Project
until such time as the Commission acts
on its application for a subsequent
license.
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–04316 Filed 3–8–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2788–000]
Notice of Authorization for Continued
Project Operation: Goodyear Lake
Hydro, LLC
On February 27, 2017, Goodyear Lake
Hydro, LLC, licensee for the
Colliersville Hydroelectric Project, filed
an Application for a New License
PO 00000
Frm 00049
Fmt 4703
Sfmt 4703
8709
pursuant to the Federal Power Act
(FPA) and the Commission’s regulations
thereunder. The Colliersville
Hydroelectric Project is located on the
North Branch of the Susquehanna River,
in the Town of Milford, Otsego County,
New York.
The license for Project No. 2788 was
issued for a period ending February 28,
2019. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2788
is issued to the licensee for a period
effective March 1, 2019 through
February 28, 2020, or until the issuance
of a new license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before February 28, 2020,
notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license
under section 15(a)(1) of the FPA is
renewed automatically without further
order or notice by the Commission,
unless the Commission orders
otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the licensee, Goodyear Lake Hydro,
LLC., is authorized to continue
operation of the Colliersville
Hydroelectric Project until such time as
the Commission acts on its application
for a subsequent license.
E:\FR\FM\11MRN1.SGM
11MRN1
8710
Federal Register / Vol. 84, No. 47 / Monday, March 11, 2019 / Notices
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
Description: § 205(d) Rate Filing:
Amendment to 5 WMPAs; SA No. 3147,
3318, 3524, 4083, 3094 re: Marina to
GRSP to be effective 10/11/2011.
Filed Date: 3/5/19.
Accession Number: 20190305–5153.
Comments Due: 5 p.m. ET 3/26/19.
[FR Doc. 2019–04317 Filed 3–8–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
amozie on DSK9F9SC42PROD with NOTICES
Combined Notice of Filings #2
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG19–64–000.
Applicants: Canal 3 Generating LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Canal 3 Generating
LLC.
Filed Date: 3/5/19.
Accession Number: 20190305–5197.
Comments Due: 5 p.m. ET 3/26/19.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER18–2030–001.
Applicants: Southwest Power Pool,
Inc.
Description: Compliance filing:
Request for Deferral of Effective Date—
Revisions to RNU Rounding Process to
be effective N/A.
Filed Date: 3/5/19.
Accession Number: 20190305–5198.
Comments Due: 5 p.m. ET 3/26/19.
Docket Numbers: ER19–836–001.
Applicants: El Paso Electric Company.
Description: Tariff Amendment:
Service Agreement No. 315, EDF PTP to
be effective 5/18/2019.
Filed Date: 3/5/19.
Accession Number: 20190305–5133.
Comments Due: 5 p.m. ET 3/26/19.
Docket Numbers: ER19–1188–000.
Applicants: RC Cape May Holdings,
LLC.
Description: Tariff Cancellation:
Notice of Cancellation of Reliability
Must-Run Agreement to be effective
5/1/2019.
Filed Date: 3/5/19.
Accession Number: 20190305–5129.
Comments Due: 5 p.m. ET 3/26/19.
Docket Numbers: ER19–1189–000.
Applicants: RC Cape May Holdings,
LLC.
Description: Tariff Cancellation: RC
Cape May Notice of Cancellation MBR
Tariff to be effective 5/1/2019.
Filed Date: 3/5/19.
Accession Number: 20190305–5132.
Comments Due: 5 p.m. ET 3/26/19.
Docket Numbers: ER19–1190–000.
Applicants: PJM Interconnection,
L.L.C.
VerDate Sep<11>2014
18:41 Mar 08, 2019
Jkt 247001
Docket Numbers: ER19–1191–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Brother Solar LGIA Filing to be effective
2/21/2019.
Filed Date: 3/5/19.
Accession Number: 20190305–5155.
Comments Due: 5 p.m. ET 3/26/19.
Docket Numbers: ER19–1193–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Kruger Energy North Sumter Solar LGIA
Filing to be effective 2/25/2019.
Filed Date: 3/5/19.
Accession Number: 20190305–5157.
Comments Due: 5 p.m. ET 3/26/19.
Docket Numbers: ER19–1194–000.
Applicants: Canal 3 Generating LLC.
Description: Baseline eTariff Filing:
Baseline New to be effective 3/6/2019.
Filed Date: 3/5/19.
Accession Number: 20190305–5191.
Comments Due: 5 p.m. ET 3/26/19.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–04329 Filed 3–8–19; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00050
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC19–65–000.
Applicants: Imperial Valley Solar,
LLC.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act, et al. of Imperial
Valley Solar, LLC.
Filed Date: 3/4/19.
Accession Number: 20190304–5169.
Comments Due: 5 p.m. ET 3/25/19.
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG19–63–000.
Applicants: AES ES Gilbert, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of AES ES Gilbert,
LLC.
Filed Date: 3/4/19.
Accession Number: 20190304–5207.
Comments Due: 5 p.m. ET 3/25/19.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–1338–003.
Applicants: Southern Indiana Gas and
Electric Company.
Description: Notice of Change in
Status of Southern Indiana Gas and
Electric Company.
Filed Date: 3/4/19.
Accession Number: 20190304–5198.
Comments Due: 5 p.m. ET 3/25/19.
Docket Numbers: ER10–1437–009.
Applicants: Tampa Electric Company.
Description: Notice of Change in
Status of Tampa Electric Company.
Filed Date: 3/4/19.
Accession Number: 20190304–5203.
Comments Due: 5 p.m. ET 3/25/19.
Docket Numbers: ER10–2732–016;
ER10–2733–016; ER10–2734–016;
ER10–2736–016; ER10–2737–016;
ER10–2741–016; ER10–2749–016;
ER10–2752–016; ER12–2492–012;
ER12–2493–012; ER12–2494–012;
ER12–2495–012; ER12–2496–012;
ER16–2455–006; ER16–2456–006;
ER16–2457–006; ER16–2458–006;
ER16–2459–006; ER18–1404–002.
Applicants: Emera Energy U.S.
Subsidiary No. 1, Inc, Emera Energy
U.S. Subsidiary No. 2, Inc., Emera
Energy Services Subsidiary No. 1 LLC,
Emera Energy Services Subsidiary No. 2
LLC, Emera Energy Services Subsidiary
No. 3 LLC, Emera Energy Services
E:\FR\FM\11MRN1.SGM
11MRN1
Agencies
[Federal Register Volume 84, Number 47 (Monday, March 11, 2019)]
[Notices]
[Pages 8709-8710]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-04317]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2788-000]
Notice of Authorization for Continued Project Operation: Goodyear
Lake Hydro, LLC
On February 27, 2017, Goodyear Lake Hydro, LLC, licensee for the
Colliersville Hydroelectric Project, filed an Application for a New
License pursuant to the Federal Power Act (FPA) and the Commission's
regulations thereunder. The Colliersville Hydroelectric Project is
located on the North Branch of the Susquehanna River, in the Town of
Milford, Otsego County, New York.
The license for Project No. 2788 was issued for a period ending
February 28, 2019. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2788 is issued to
the licensee for a period effective March 1, 2019 through February 28,
2020, or until the issuance of a new license for the project or other
disposition under the FPA, whichever comes first. If issuance of a new
license (or other disposition) does not take place on or before
February 28, 2020, notice is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under section 15(a)(1) of the FPA is
renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that the licensee, Goodyear Lake Hydro, LLC., is
authorized to continue operation of the Colliersville Hydroelectric
Project until such time as the Commission acts on its application for a
subsequent license.
[[Page 8710]]
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-04317 Filed 3-8-19; 8:45 am]
BILLING CODE 6717-01-P