Notice of Authorization for Continued Project Operation: City of Holyoke Gas and Electric Department, 8709 [2019-04316]
Download as PDF
Federal Register / Vol. 84, No. 47 / Monday, March 11, 2019 / Notices
Additional Information
Additional information about the
projects are available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC
website (www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on General Search and enter the
docket number(s) in the Docket Number
field, excluding the last three digits (i.e.,
PF17–10 for the FM100 Project; PF19–
1 for the Leidy South Project). Be sure
you have selected an appropriate date
range. For assistance, please contact
FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of all formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
Public sessions or site visits will be
posted on the Commission’s calendar
located at www.ferc.gov/EventCalendar/
EventsList.aspx along with other related
information.
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–04318 Filed 3–8–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2388–000]
amozie on DSK9F9SC42PROD with NOTICES
Notice of Authorization for Continued
Project Operation: City of Holyoke Gas
and Electric Department
On August 31, 2016, City of Holyoke
Gas and Electric Department, licensee
for the Holyoke No. 3 Hydroelectric
Project, filed an Application for a New
License pursuant to the Federal Power
Act (FPA) and the Commission’s
regulations thereunder. The Holyoke
No. 3 Hydroelectric Project is located
between the first and second canals
adjacent to the Connecticut River, in the
City of Holyoke in Hampton County,
Massachusetts.
The license for Project No. 2388 was
issued for a period ending February 20,
2019. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
VerDate Sep<11>2014
18:41 Mar 08, 2019
Jkt 247001
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2388
is issued to the licensee for a period
effective February 21, 2019 through
February 20, 2020, or until the issuance
of a new license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before February 20, 2020,
notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license
under section 15(a)(1) of the FPA is
renewed automatically without further
order or notice by the Commission,
unless the Commission orders
otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the licensee, City of Holyoke Gas
and Electric Department, Inc., is
authorized to continue operation of the
Holyoke No. 3 Hydroelectric Project
until such time as the Commission acts
on its application for a subsequent
license.
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–04316 Filed 3–8–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2788–000]
Notice of Authorization for Continued
Project Operation: Goodyear Lake
Hydro, LLC
On February 27, 2017, Goodyear Lake
Hydro, LLC, licensee for the
Colliersville Hydroelectric Project, filed
an Application for a New License
PO 00000
Frm 00049
Fmt 4703
Sfmt 4703
8709
pursuant to the Federal Power Act
(FPA) and the Commission’s regulations
thereunder. The Colliersville
Hydroelectric Project is located on the
North Branch of the Susquehanna River,
in the Town of Milford, Otsego County,
New York.
The license for Project No. 2788 was
issued for a period ending February 28,
2019. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 2788
is issued to the licensee for a period
effective March 1, 2019 through
February 28, 2020, or until the issuance
of a new license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before February 28, 2020,
notice is hereby given that, pursuant to
18 CFR 16.18(c), an annual license
under section 15(a)(1) of the FPA is
renewed automatically without further
order or notice by the Commission,
unless the Commission orders
otherwise.
If the project is not subject to section
15 of the FPA, notice is hereby given
that the licensee, Goodyear Lake Hydro,
LLC., is authorized to continue
operation of the Colliersville
Hydroelectric Project until such time as
the Commission acts on its application
for a subsequent license.
E:\FR\FM\11MRN1.SGM
11MRN1
Agencies
[Federal Register Volume 84, Number 47 (Monday, March 11, 2019)]
[Notices]
[Page 8709]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-04316]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2388-000]
Notice of Authorization for Continued Project Operation: City of
Holyoke Gas and Electric Department
On August 31, 2016, City of Holyoke Gas and Electric Department,
licensee for the Holyoke No. 3 Hydroelectric Project, filed an
Application for a New License pursuant to the Federal Power Act (FPA)
and the Commission's regulations thereunder. The Holyoke No. 3
Hydroelectric Project is located between the first and second canals
adjacent to the Connecticut River, in the City of Holyoke in Hampton
County, Massachusetts.
The license for Project No. 2388 was issued for a period ending
February 20, 2019. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1),
requires the Commission, at the expiration of a license term, to issue
from year-to-year an annual license to the then licensee under the
terms and conditions of the prior license until a new license is
issued, or the project is otherwise disposed of as provided in section
15 or any other applicable section of the FPA. If the project's prior
license waived the applicability of section 15 of the FPA, then, based
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c),
and as set forth at 18 CFR 16.21(a), if the licensee of such project
has filed an application for a subsequent license, the licensee may
continue to operate the project in accordance with the terms and
conditions of the license after the minor or minor part license
expires, until the Commission acts on its application. If the licensee
of such a project has not filed an application for a subsequent
license, then it may be required, pursuant to 18 CFR 16.21(b), to
continue project operations until the Commission issues someone else a
license for the project or otherwise orders disposition of the project.
If the project is subject to section 15 of the FPA, notice is
hereby given that an annual license for Project No. 2388 is issued to
the licensee for a period effective February 21, 2019 through February
20, 2020, or until the issuance of a new license for the project or
other disposition under the FPA, whichever comes first. If issuance of
a new license (or other disposition) does not take place on or before
February 20, 2020, notice is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under section 15(a)(1) of the FPA is
renewed automatically without further order or notice by the
Commission, unless the Commission orders otherwise.
If the project is not subject to section 15 of the FPA, notice is
hereby given that the licensee, City of Holyoke Gas and Electric
Department, Inc., is authorized to continue operation of the Holyoke
No. 3 Hydroelectric Project until such time as the Commission acts on
its application for a subsequent license.
Dated: March 5, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-04316 Filed 3-8-19; 8:45 am]