Download as PDF 8326 Federal Register / Vol. 84, No. 45 / Thursday, March 7, 2019 / Notices from Ace-Federal Reporters, Inc. at (202) 347–3700. Commission conferences are accessible under section 508 of the Rehabilitation Act of 1973. For accessibility accommodations, please send an email to accessibility@ferc.gov or call toll free 1 (866) 208–3372 (voice) or (202) 502–8659 (TTY), or send a fax to (202) 208–2106 with the required accommodations. For more information about this technical conference, please contact Carolyn Templeton by phone at (202) 502–8785 or by email at carolyn.templeton@ferc.gov. For information related to logistics, please contact Sarah McKinley at (202) 502– 8368 or by email at sarah.mckinley@ ferc.gov. Dated: March 1, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–04145 Filed 3–6–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP19–52–000] amozie on DSK9F9SC42PROD with NOTICES Natural Gas Pipeline Company of America, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Lockridge Extension Pipeline Project and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Lockridge Extension Pipeline Project involving construction and operation of facilities by Natural Gas Pipeline Company of America, LLC (Natural) in Ward, Reeves, and Pecos Counties, Texas. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies about issues regarding the project. The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from its action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires the Commission to discover concerns the public may have about proposals. This process is referred VerDate Sep<11>2014 17:13 Mar 06, 2019 Jkt 247001 to as scoping. The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of issues to address in the EA. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC on or before 5:00pm Eastern Time on April 1, 2019. You can make a difference by submitting your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Commission staff will consider all filed comments during the preparation of the EA. If you sent comments on this project to the Commission before the opening of this docket on January 18, 2019, you will need to file those comments in Docket No. CP19–52–000 to ensure they are considered as part of this proceeding. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable easement agreement. You are not required to enter into an agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if you and the company do not reach an easement agreement, the pipeline company could initiate condemnation proceedings in court. In such instances, compensation would be determined by a judge in accordance with state law. Natural provided landowners with a fact sheet prepared by the FERC entitled An Interstate Natural Gas Facility On My Land? What Do I Need To Know? This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC website (www.ferc.gov) at https://www.ferc.gov/ resources/guides/gas/gas.pdf. PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 Public Participation The Commission offers a free service called eSubscription which makes it easy to stay informed of all issuances and submittals regarding the dockets/ projects to which you subscribe. These instant email notifications are the fastest way to receive notification and provide a link to the document files which can reduce the amount of time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/ esubscription.asp. For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208–3676 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded. (1) You can file your comments electronically using the eComment feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. Using eComment is an easy method for submitting brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature, which is located on the Commission’s website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on eRegister. You will be asked to select the type of filing you are making; a comment on a particular project is considered a Comment on a Filing; or (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (CP19–52– 000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Summary of the Proposed Project Natural proposes to construct, install, operate, and maintain the Project, which would provide up to 500 million standard cubic feet per day of firm transportation capacity southbound on Natural’s existing Lockridge Pipeline and the proposed project to the new bidirectional interconnect with TransPecos Pipeline, LLC at the Waha Hub, a major natural gas trading point in the Gulf region. The Lockridge Extension Pipeline Project would consist of the following facilities: E:\FR\FM\07MRN1.SGM 07MRN1 Federal Register / Vol. 84, No. 45 / Thursday, March 7, 2019 / Notices • Approximately 16.8 miles, of new 30-inch-diameter pipeline in Ward, Reeves, and Pecos Counties, Texas; • a new bidirectional interconnect, including two 10-inch-diameter ultrasonic meter runs and a 30-inchdiameter tap in Pecos County, Texas; and • appurtenant and auxiliary facilities, including: Æ two 30-inch-diameter tees, valves, and risers for potential future use; Æ piping and valves to interconnect the pipeline extension to the existing Lockridge Pipeline in Ward County, Texas; and Æ relocating the pig receiver currently at the beginning of the pipeline extension to the end of pipeline extension in Pecos County, Texas.1 The general location of the project facilities is shown in appendix 1.2 Land Requirements for Construction The proposed construction workspace for the project (i.e., temporary workspace, additional temporary workspace, access roads, contractor yards, aboveground appurtenant facilities) is approximately 341 acres. Operation of the project facilities would require approximately 103 acres that would be maintained as new permanent operational rights-of-way or as fee property for the aboveground appurtenant facilities and associated access roads. Approximately 91 percent of the proposed pipeline extension would be parallel and adjacent to existing utility (pipeline and powerline) rights-of-way. The EA Process amozie on DSK9F9SC42PROD with NOTICES The EA will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and soils; • water resources and wetlands; • vegetation and wildlife; • threatened and endangered species; • cultural resources; • land use; • air quality and noise; • public safety; and • cumulative impacts 1 A pig is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting internal inspections, or other purposes. 2 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called eLibrary or from the Commission’s Public Reference Room, 888 First Street NE, Washington, DC 20426, or call (202) 502– 8371. For instructions on connecting to eLibrary, refer to the last page of this notice. VerDate Sep<11>2014 17:13 Mar 06, 2019 Jkt 247001 8327 Commission staff will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present Commission staffs’ independent analysis of the issues. The EA will be available in electronic format in the public record through eLibrary 3 and the Commission’s website (https:// www.ferc.gov/industries/gas/enviro/ eis.asp). If eSubscribed, you will receive instant email notification when the EA is issued. The EA may be issued for an allotted public comment period. Commission staff will consider all comments on the EA before making recommendations to the Commission. To ensure Commission staff have the opportunity to address your comments, please carefully follow the instructions in the Public Participation section, beginning on page [2]. With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the EA.4 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If the Commission issues the EA for an allotted public comment period, a Notice of Availability of the EA will be sent to the environmental mailing list and will provide instructions to access the electronic document on the FERC’s website (www.ferc.gov). If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please return the attached ‘‘Mailing List Update Form’’ (appendix 2). Consultation Under Section 106 of the National Historic Preservation Act Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on General Search and enter the docket number in the Docket Number field, excluding the last three digits (i.e., CP19–52). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings. Public sessions or site visits will be posted on the Commission’s calendar located at www.ferc.gov/EventCalendar/ EventsList.aspx along with other related information. In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic Preservation Office, and to solicit their views and those of other government agencies, interested Native American Tribes, and the public on the project’s potential effects on historic properties.5 The EA for this project will document findings on the impacts on historic properties and summarize the status of consultations under section 106. 3 For instructions on connecting to eLibrary, refer to the last page of this notice. 4 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. 5 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. PO 00000 Frm 00033 Fmt 4703 Sfmt 9990 Dated: March 1, 2019. Kimberly D. Bose, Secretary. [FR Doc. 2019–04147 Filed 3–6–19; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\07MRN1.SGM 07MRN1

Agencies

[Federal Register Volume 84, Number 45 (Thursday, March 7, 2019)]
[Notices]
[Pages 8326-8327]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-04147]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-52-000]


Natural Gas Pipeline Company of America, LLC; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed Lockridge 
Extension Pipeline Project and Request for Comments on Environmental 
Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Lockridge Extension Pipeline 
Project involving construction and operation of facilities by Natural 
Gas Pipeline Company of America, LLC (Natural) in Ward, Reeves, and 
Pecos Counties, Texas. The Commission will use this EA in its decision-
making process to determine whether the project is in the public 
convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies about issues regarding the project. The National Environmental 
Policy Act (NEPA) requires the Commission to take into account the 
environmental impacts that could result from its action whenever it 
considers the issuance of a Certificate of Public Convenience and 
Necessity. NEPA also requires the Commission to discover concerns the 
public may have about proposals. This process is referred to as 
scoping. The main goal of the scoping process is to focus the analysis 
in the EA on the important environmental issues. By this notice, the 
Commission requests public comments on the scope of issues to address 
in the EA. To ensure that your comments are timely and properly 
recorded, please submit your comments so that the Commission receives 
them in Washington, DC on or before 5:00pm Eastern Time on April 1, 
2019.
    You can make a difference by submitting your specific comments or 
concerns about the project. Your comments should focus on the potential 
environmental effects, reasonable alternatives, and measures to avoid 
or lessen environmental impacts. Your input will help the Commission 
staff determine what issues they need to evaluate in the EA. Commission 
staff will consider all filed comments during the preparation of the 
EA.
    If you sent comments on this project to the Commission before the 
opening of this docket on January 18, 2019, you will need to file those 
comments in Docket No. CP19-52-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable easement agreement. You 
are not required to enter into an agreement. However, if the Commission 
approves the project, that approval conveys with it the right of 
eminent domain. Therefore, if you and the company do not reach an 
easement agreement, the pipeline company could initiate condemnation 
proceedings in court. In such instances, compensation would be 
determined by a judge in accordance with state law.
    Natural provided landowners with a fact sheet prepared by the FERC 
entitled An Interstate Natural Gas Facility On My Land? What Do I Need 
To Know? This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC website (www.ferc.gov) at https://www.ferc.gov/resources/guides/gas/gas.pdf.

Public Participation

    The Commission offers a free service called eSubscription which 
makes it easy to stay informed of all issuances and submittals 
regarding the dockets/projects to which you subscribe. These instant 
email notifications are the fastest way to receive notification and 
provide a link to the document files which can reduce the amount of 
time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/esubscription.asp.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or FercOnlineSupport@ferc.gov. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. Using eComment is an easy 
method for submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to Documents and Filings. With eFiling, you can provide 
comments in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on eRegister. You will be asked to select the type of filing you are 
making; a comment on a particular project is considered a Comment on a 
Filing; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP19-52-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    Natural proposes to construct, install, operate, and maintain the 
Project, which would provide up to 500 million standard cubic feet per 
day of firm transportation capacity southbound on Natural's existing 
Lockridge Pipeline and the proposed project to the new bidirectional 
interconnect with Trans-Pecos Pipeline, LLC at the Waha Hub, a major 
natural gas trading point in the Gulf region.
    The Lockridge Extension Pipeline Project would consist of the 
following facilities:

[[Page 8327]]

     Approximately 16.8 miles, of new 30-inch-diameter pipeline 
in Ward, Reeves, and Pecos Counties, Texas;
     a new bidirectional interconnect, including two 10-inch-
diameter ultrasonic meter runs and a 30-inch-diameter tap in Pecos 
County, Texas; and
     appurtenant and auxiliary facilities, including:
    [cir] two 30-inch-diameter tees, valves, and risers for potential 
future use;
    [cir] piping and valves to interconnect the pipeline extension to 
the existing Lockridge Pipeline in Ward County, Texas; and
    [cir] relocating the pig receiver currently at the beginning of the 
pipeline extension to the end of pipeline extension in Pecos County, 
Texas.\1\
---------------------------------------------------------------------------

    \1\ A pig is a tool that the pipeline company inserts into and 
pushes through the pipeline for cleaning the pipeline, conducting 
internal inspections, or other purposes.
---------------------------------------------------------------------------

    The general location of the project facilities is shown in appendix 
1.\2\
---------------------------------------------------------------------------

    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called eLibrary or from the Commission's Public 
Reference Room, 888 First Street NE, Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    The proposed construction workspace for the project (i.e., 
temporary workspace, additional temporary workspace, access roads, 
contractor yards, aboveground appurtenant facilities) is approximately 
341 acres. Operation of the project facilities would require 
approximately 103 acres that would be maintained as new permanent 
operational rights-of-way or as fee property for the aboveground 
appurtenant facilities and associated access roads.
    Approximately 91 percent of the proposed pipeline extension would 
be parallel and adjacent to existing utility (pipeline and powerline) 
rights-of-way.

The EA Process

    The EA will discuss impacts that could occur as a result of the 
construction and operation of the proposed project under these general 
headings:
     Geology and soils;
     water resources and wetlands;
     vegetation and wildlife;
     threatened and endangered species;
     cultural resources;
     land use;
     air quality and noise;
     public safety; and
     cumulative impacts
    Commission staff will also evaluate reasonable alternatives to the 
proposed project or portions of the project, and make recommendations 
on how to lessen or avoid impacts on the various resource areas.
    The EA will present Commission staffs' independent analysis of the 
issues. The EA will be available in electronic format in the public 
record through eLibrary \3\ and the Commission's website (https://www.ferc.gov/industries/gas/enviro/eis.asp). If eSubscribed, you will 
receive instant email notification when the EA is issued. The EA may be 
issued for an allotted public comment period. Commission staff will 
consider all comments on the EA before making recommendations to the 
Commission. To ensure Commission staff have the opportunity to address 
your comments, please carefully follow the instructions in the Public 
Participation section, beginning on page [2].
---------------------------------------------------------------------------

    \3\ For instructions on connecting to eLibrary, refer to the 
last page of this notice.
---------------------------------------------------------------------------

    With this notice, the Commission is asking agencies with 
jurisdiction by law and/or special expertise with respect to the 
environmental issues of this project to formally cooperate in the 
preparation of the EA.\4\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultation Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, the Commission is using this notice to initiate 
consultation with the applicable State Historic Preservation Office, 
and to solicit their views and those of other government agencies, 
interested Native American Tribes, and the public on the project's 
potential effects on historic properties.\5\ The EA for this project 
will document findings on the impacts on historic properties and 
summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \5\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. Commission staff will update the environmental 
mailing list as the analysis proceeds to ensure that Commission notices 
related to this environmental review are sent to all individuals, 
organizations, and government entities interested in and/or potentially 
affected by the proposed project.
    If the Commission issues the EA for an allotted public comment 
period, a Notice of Availability of the EA will be sent to the 
environmental mailing list and will provide instructions to access the 
electronic document on the FERC's website (www.ferc.gov). If you need 
to make changes to your name/address, or if you would like to remove 
your name from the mailing list, please return the attached ``Mailing 
List Update Form'' (appendix 2).

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website at www.ferc.gov using the eLibrary link. Click on the 
eLibrary link, click on General Search and enter the docket number in 
the Docket Number field, excluding the last three digits (i.e., CP19-
52). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or (866) 208-3676, or for TTY, contact (202) 
502-8659. The eLibrary link also provides access to the texts of all 
formal documents issued by the Commission, such as orders, notices, and 
rulemakings.
    Public sessions or site visits will be posted on the Commission's 
calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along 
with other related information.

    Dated: March 1, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-04147 Filed 3-6-19; 8:45 am]