Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization, 8091-8092 [2019-03999]
Download as PDF
Federal Register / Vol. 84, No. 44 / Wednesday, March 6, 2019 / Notices
FERC) issued its Notice of Application
for the Project. Among other things, that
notice alerted agencies issuing federal
authorizations of the requirement to
complete all necessary reviews and to
reach a final decision on a request for
a federal authorization within 90 days of
the date of issuance of the Commission
staff’s Environmental Assessment (EA)
for the Project. This instant notice
identifies the FERC staff’s planned
schedule for the completion of the EA
for the Project.
SCHEDULE FOR ENVIRONMENTAL
REVIEW
Issuance of EA ......................
90-day Federal Authorization
Decision Deadline.
April 8, 2019.
July 7, 2019.
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
Columbia’s Project would consist of
replacing 60.8 miles of aging 20- to 24inch-diameter pipeline with 66.2 miles
of new 36-inch-diameter pipeline on
Columbia’s existing Line R–501,
constructing 0.2 mile of 4-inch-diameter
pipeline for the Wellston Lateral,
installing four new mainline valves, and
modifying existing compressor and
regulator stations, all in Ohio and West
Virginia. The project would also
abandon 1.1 miles of 2- to 3-inchdiameter distribution pipeline. The new
pipeline would be 5.4 miles longer than
the existing pipeline to avoid steep land
contours.
Background
On October 16, 2017, the Commission
issued a Notice of Intent to Prepare an
Environmental Assessment for the
Planned Buckeye Xpress Project,
Request for Comments on
Environmental Issues, and Notice of
Public Scoping Sessions (NOI). The NOI
was issued during the pre-filing review
of the Project in Docket No. PF17–6 and
was sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries and newspapers. In response to
the NOI, the Commission received
comments from the U.S. Environmental
Protection Agency, the U.S. Fish and
Wildlife Service, the Bureau of Indian
Affairs, the Ohio Farm Bureau, the Ohio
Environmental Protection Agency, the
Sierra Club, the Center for Biological
Diversity, the Ohio Environmental
VerDate Sep<11>2014
18:35 Mar 05, 2019
Jkt 247001
Council, the Ohio Valley Conservation
Coalition, and four landowners. Major
issues raised during scoping include
alternatives, greenhouse gas emissions,
the need for an environmental impact
statement instead of an environmental
assessment, upstream and downstream
impacts, climate impacts, induced
development, compliance with Wayne
National Forest’s 2006 Forest Plan, and
that the project is not needed. All
substantive comments will be addressed
in the EA.
The U.S. Forest Service and the U.S.
Army Corps of Engineers are
cooperating agencies in the preparation
of the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
eLibrary link, select General Search
from the eLibrary menu, enter the
selected date range and Docket Number
excluding the last three digits (i.e.,
CP18–137), and follow the instructions.
For assistance with access to eLibrary,
the helpline can be reached at (866)
208–3676, TTY (202) 502–8659, or at
FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: February 28, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–03997 Filed 3–5–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP19–89–000]
Columbia Gas Transmission, LLC;
Notice of Request Under Blanket
Authorization
Take notice that on February 19, 2019,
Columbia Gas Transmission, LLC
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
8091
(Columbia), 700 Louisiana Street,
Houston, Texas 77002, filed in Docket
No. CP19–89–000, a Prior Notice
Request pursuant to sections 157.205
and 157.213(b) of the Commission’s
regulations under the Natural Gas Act
(NGA), and Columbia’s blanket
certificate issued in Docket No. CP83–
76–000, requesting authorization to
construct and operate two new
horizontal injection/withdrawal (I/W)
storage wells and approximately 450
feet of associated 6-inch-diameter
pipeline and appurtenances at
Columbia’s Pavonia Storage Field
located in Ashland County, Ohio.
Columbia states the proposed wells will
provide approximately 17.4 MMcf/d of
restored deliverability to the Columbia
storage system and cost approximately
$10 million, all as more fully described
in the application which is on file with
the Commission and open to public
inspection. The filing may also be
viewed on the web at https://
www.ferc.gov using the eLibrary link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TTY, (202)
502–8659.
Any questions regarding this prior
notice should be directed to Linda
Farquhar, Manager, Project
Determinations & Regulatory
Administration, Columbia Gas
Transmission, LLC, 700 Louisiana
Street, Suite 700, Houston, Texas 77002,
by phone at (832) 320–5685, by fax at
(832) 320–6685, or by email at
linda_farquhar@transcanada.com.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
E:\FR\FM\06MRN1.SGM
06MRN1
8092
Federal Register / Vol. 84, No. 44 / Wednesday, March 6, 2019 / Notices
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the EA
for this proposal. The filing of the EA
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list and will be
notified of any meetings associated with
the Commission’s environmental review
process. Environmental commenters
will not be required to serve copies of
filed documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 3 copies
of the protest or intervention to the
Federal Energy regulatory Commission,
888 First Street NE, Washington, DC
20426.
Dated: February 28, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–03999 Filed 3–5–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER17–1568–002.
Applicants: Southwest Power Pool,
Inc.
Description: Compliance filing:
Request for Deferral of Effective Date—
VerDate Sep<11>2014
20:00 Mar 05, 2019
Jkt 247001
Order No. 831 Compliance Filing to be
effective N/A.
Filed Date: 2/28/19.
Accession Number: 20190228–5196.
Comments Due: 5 p.m. ET 3/21/19.
Docket Numbers: ER18–2342–004.
Applicants: GridLiance Heartland
LLC.
Description: Compliance filing:
GridLiance Heartland LLC—ER18–2342
Compliance Filing—Revised to be
effective 2/27/2019.
Filed Date: 2/27/19.
Accession Number: 20190227–5129.
Comments Due: 5 p.m. ET 3/20/19.
Docket Numbers: ER19–231–002.
Applicants: Dynegy Oakland, LLC.
Description: Tariff Amendment:
Amended Filing ? Request for
Commission Action to be effective 1/1/
2019.
Filed Date: 2/27/19.
Accession Number: 20190227–5128.
Comments Due: 5 p.m. ET 3/20/19.
Docket Numbers: ER19–404–001.
Applicants: Public Service Company
of Colorado.
Description: Compliance filing: 2019–
02–27 Transmission Template Update—
Compliance ER19–404 to be effective 2/
1/2019.
Filed Date: 2/27/19.
Accession Number: 20190227–5144.
Comments Due: 5 p.m. ET 3/20/19.
Docket Numbers: ER19–460–002.
Applicants: Southwest Power Pool,
Inc.
Description: Compliance filing:
Request for Deferral of Effective Date—
Order No. 841 Compliance Filing to be
effective N/A.
Filed Date: 2/28/19.
Accession Number: 20190228–5100.
Comments Due: 5 p.m. ET 3/21/19.
Docket Numbers: ER19–1120–001.
Applicants: PJM Interconnection,
L.L.C.
Description: Tariff Amendment: Eratta
re: Second Revised ISA No. 3604, Queue
No. W4–009/X4–005/AD1–113 to be
effective 1/26/2019.
Filed Date: 2/28/19.
Accession Number: 20190228–5247.
Comments Due: 5 p.m. ET 3/21/19.
Docket Numbers: ER19–1136–000.
Applicants: City of Pasadena,
California.
Description: § 205(d) Rate Filing:
Transmission Revenue Requirement
Revision to be effective 3/1/2019.
Filed Date: 2/27/19.
Accession Number: 20190227–5143.
Comments Due: 5 p.m. ET 3/20/19.
Docket Numbers: ER19–1137–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing: East
Texas Cooperatives Stated Rate
Revisions to be effective 5/1/2019.
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
Filed Date: 2/27/19.
Accession Number: 20190227–5145.
Comments Due: 5 p.m. ET 3/20/19.
Docket Numbers: ER19–1138–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, SA No. 5291, Queue No.
AC1–165 to be effective 1/28/2019.
Filed Date: 2/27/19.
Accession Number: 20190227–5150.
Comments Due: 5 p.m. ET 3/20/19.
Docket Numbers: ER19–1141–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA, SA No. 5287, Queue No.
AB2–100 to be effective 1/29/2019.
Filed Date: 2/28/19.
Accession Number: 20190228–5052.
Comments Due: 5 p.m. ET 3/21/19.
Docket Numbers: ER19–1142–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2019–02–28_Termination of SA 3169
Crittenden Wind—EAI GIA (J662) to be
effective 4/2/2019.
Filed Date: 2/28/19.
Accession Number: 20190228–5103.
Comments Due: 5 p.m. ET 3/21/19.
Docket Numbers: ER19–1143–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2019–02–28_SA 3206 Dakota Range I &
II–OTP MPFCA (J436 J437 Hankinson
Ellendale) to be effective 1/7/2019.
Filed Date: 2/28/19.
Accession Number: 20190228–5107.
Comments Due: 5 p.m. ET 3/21/19.
Docket Numbers: ER19–1144–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: § 205(d) Rate Filing:
2019–02–28_SA 3241 Deuel Harvest
Wind Energy–NSP–OTP FCA (J526) to
be effective 2/20/2019.
Filed Date: 2/28/19.
Accession Number: 20190228–5112.
Comments Due: 5 p.m. ET 3/21/19.
Docket Numbers: ER19–1145–000.
Applicants: PPL Electric Utilities
Corporation, PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing: PPL
submits revisions to the OATT, Att. H–
8G re: Tax Cuts and Jobs Act of 2017 to
be effective 6/1/2019.
Filed Date: 2/28/19.
Accession Number: 20190228–5127.
Comments Due: 5 p.m. ET 3/21/19.
Docket Numbers: ER19–1146–000.
Applicants: New England Power Pool
Participants Committee.
Description: § 205(d) Rate Filing:
March 2019 Membership Filing to be
effective 2/1/2019.
E:\FR\FM\06MRN1.SGM
06MRN1
Agencies
[Federal Register Volume 84, Number 44 (Wednesday, March 6, 2019)]
[Notices]
[Pages 8091-8092]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-03999]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP19-89-000]
Columbia Gas Transmission, LLC; Notice of Request Under Blanket
Authorization
Take notice that on February 19, 2019, Columbia Gas Transmission,
LLC (Columbia), 700 Louisiana Street, Houston, Texas 77002, filed in
Docket No. CP19-89-000, a Prior Notice Request pursuant to sections
157.205 and 157.213(b) of the Commission's regulations under the
Natural Gas Act (NGA), and Columbia's blanket certificate issued in
Docket No. CP83-76-000, requesting authorization to construct and
operate two new horizontal injection/withdrawal (I/W) storage wells and
approximately 450 feet of associated 6-inch-diameter pipeline and
appurtenances at Columbia's Pavonia Storage Field located in Ashland
County, Ohio. Columbia states the proposed wells will provide
approximately 17.4 MMcf/d of restored deliverability to the Columbia
storage system and cost approximately $10 million, all as more fully
described in the application which is on file with the Commission and
open to public inspection. The filing may also be viewed on the web at
https://www.ferc.gov using the eLibrary link. Enter the docket number
excluding the last three digits in the docket number field to access
the document. For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call toll-free, (866) 208-3676 or TTY,
(202) 502-8659.
Any questions regarding this prior notice should be directed to
Linda Farquhar, Manager, Project Determinations & Regulatory
Administration, Columbia Gas Transmission, LLC, 700 Louisiana Street,
Suite 700, Houston, Texas 77002, by phone at (832) 320-5685, by fax at
(832) 320-6685, or by email at linda_farquhar@transcanada.com.
Any person or the Commission's staff may, within 60 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to section 157.205 of
the regulations under the NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the time allowed therefore, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the allowed time for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to section 7 of the NGA.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
complete its environmental assessment (EA) and place it into the
Commission's public
[[Page 8092]]
record (eLibrary) for this proceeding; or issue a Notice of Schedule
for Environmental Review. If a Notice of Schedule for Environmental
Review is issued, it will indicate, among other milestones, the
anticipated date for the Commission staff's issuance of the EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's EA.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list and will be
notified of any meetings associated with the Commission's environmental
review process. Environmental commenters will not be required to serve
copies of filed documents on all other parties. However, the non-party
commenters will not receive copies of all documents filed by other
parties or issued by the Commission and will not have the right to seek
court review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests, and interventions in lieu of paper using the eFiling link at
https://www.ferc.gov. Persons unable to file electronically should
submit an original and 3 copies of the protest or intervention to the
Federal Energy regulatory Commission, 888 First Street NE, Washington,
DC 20426.
Dated: February 28, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-03999 Filed 3-5-19; 8:45 am]
BILLING CODE 6717-01-P