Download as PDF Federal Register / Vol. 84, No. 44 / Wednesday, March 6, 2019 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP17–178–000] Alaska Gasline Development Corporation; Notice of Revised Schedule for Environmental Review of the Alaska LNG Project This notice identifies the Federal Energy Regulatory Commission (Commission) staff’s revised schedule for the completion of the environmental impact statement (EIS) for the Alaska Gasline Development Corporation’s (AGDC) Alaska LNG Project. The previous notice of schedule, issued on August 31, 2018, identified November 8, 2019 as the final EIS issuance date. The previous notice stated that the forecasted schedule was based upon AGDC providing complete and timely responses to any data requests. In its partial data request responses filed in January and February 2019, AGDC states that it would provide the remainder of the responses in stages through July 2019. As a result, staff has revised the schedule for issuance of the EIS. The revised schedule for the EIS is based upon AGDC meeting its commitment to provide complete responses to outstanding data requests on the dates it has identified. Staff has revised the schedule for issuance of the final EIS based on an issuance of the draft EIS in June 2019. Schedule for Environmental Review Issuance of Notice of Availability of the final EIS—March 6, 2020 90-day Federal Authorization Decision Deadline—June 4, 2020 In an additional notice issued on August 31, 2018, the Commission identified February 6, 2020 as the anticipated final order issuance for the Alaska LNG Project. Based on the revised final EIS schedule, the Commission currently anticipates issuing a final order for the project no later than: Issuance of Final Order—June 4, 2020 If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the project’s progress. Additional Information In order to receive notification of the issuance of the EIS and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you VerDate Sep<11>2014 18:35 Mar 05, 2019 Jkt 247001 spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/docsfiling/esubscription.asp. Additional information about the Project is available from the Commission’s Office of External Affairs at (866) 208–FERC or on the FERC website (www.ferc.gov). Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number excluding the last three digits (i.e., CP17–178), and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at (866) 208–3676, TTY (202) 502–8659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. Dated: February 28, 2019. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2019–03995 Filed 3–5–19; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Number: PR19–42–000. Applicants: Arkansas Oklahoma Gas Corporation. Description: Annual Report and Request for Continued Limited Waivers of Requirements to submit informational rate filing, et al. of Arkansas Oklahoma Gas Corporation. Filed Date: 2/22/19. Accession Number: 201902225228. Comments/Protests Due: 5 p.m. ET 3/ 15/19. Docket Number: PR19–27–001. Applicants: DCP Guadalupe Pipeline, LLC. Description: Tariff filing per 284.123(b),(e)+(g): Amendment to Remove Section 311 Firm Transportation to be effective 1/1/2019. Filed Date: 2/25/19. Accession Number: 201902255154. Comments Due: 5 p.m. ET 3/18/19. 284.123(g) Protests Due: 5 p.m. ET 3/ 18/19. Docket Number: PR19–43–000. PO 00000 Frm 00019 Fmt 4703 Sfmt 4703 8089 Applicants: EasTrans, LLC. Description: Tariff filing per 284.123(b)(1)+(g): EasTrans SOC Rate Certification Filing to be effective 3/31/ 2019. Filed Date: 2/27/19. Accession Number: 201902275000. Comments Due: 5 p.m. ET 3/20/19. 284.123(g) Protests Due: 5 p.m. ET 4/ 29/19. Docket Numbers: RP19–668–001. Applicants: WestGas InterState, Inc. Description: Tariff Amendment: Amendment to be effective 2/20/2019. Filed Date: 2/27/19. Accession Number: 20190227–5139. Comments Due: 5 p.m. ET 3/11/19. Docket Numbers: RP19–698–000. Applicants: Texas Eastern Transmission, LP. Description: § 4(d) Rate Filing: Negotiatad Rate—Pal Citigroup Deal 951825 eff 3–2–19 to be effective 3/2/ 2019. Filed Date: 2/27/19. Accession Number: 20190227–5001. Comments Due: 5 p.m. ET 3/11/19. Docket Numbers: RP19–699–000. Applicants: Natural Gas Pipeline Company of America. Description: § 4(d) Rate Filing: Negotiated Rate Agreement— ConocoPhillips Company to be effective 4/1/2019. Filed Date: 2/27/19. Accession Number: 20190227–5002. Comments Due: 5 p.m. ET 3/11/19. Docket Numbers: RP19–700–000. Applicants: Natural Gas Pipeline Company of America. Description: § 4(d) Rate Filing: Negotiated Rate Agreement—Macquarie Energy to be effective 4/1/2019. Filed Date: 2/27/19. Accession Number: 20190227–5003. Comments Due: 5 p.m. ET 3/11/19. Docket Numbers: RP19–701–000. Applicants: Natural Gas Pipeline Company of America. Description: § 4(d) Rate Filing: Negotiated Rate Agreement—Nicor Gas Company to be effective 4/1/2019. Filed Date: 2/27/19. Accession Number: 20190227–5004. Comments Due: 5 p.m. ET 3/11/19. Docket Numbers: RP19–702–000. Applicants: Natural Gas Pipeline Company of America. Description: § 4(d) Rate Filing: Negotiated Rate Agreement—Tenaska Marketing Ventures to be effective 4/1/ 2019. Filed Date: 2/27/19. Accession Number: 20190227–5005. Comments Due: 5 p.m. ET 3/11/19. Docket Numbers: RP19–703–000. Applicants: Dauphin Island Gathering Partners. E:\FR\FM\06MRN1.SGM 06MRN1

Agencies

[Federal Register Volume 84, Number 44 (Wednesday, March 6, 2019)]
[Notices]
[Page 8089]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-03995]



[[Page 8089]]

=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-178-000]


Alaska Gasline Development Corporation; Notice of Revised 
Schedule for Environmental Review of the Alaska LNG Project

    This notice identifies the Federal Energy Regulatory Commission 
(Commission) staff's revised schedule for the completion of the 
environmental impact statement (EIS) for the Alaska Gasline Development 
Corporation's (AGDC) Alaska LNG Project. The previous notice of 
schedule, issued on August 31, 2018, identified November 8, 2019 as the 
final EIS issuance date. The previous notice stated that the forecasted 
schedule was based upon AGDC providing complete and timely responses to 
any data requests. In its partial data request responses filed in 
January and February 2019, AGDC states that it would provide the 
remainder of the responses in stages through July 2019. As a result, 
staff has revised the schedule for issuance of the EIS. The revised 
schedule for the EIS is based upon AGDC meeting its commitment to 
provide complete responses to outstanding data requests on the dates it 
has identified. Staff has revised the schedule for issuance of the 
final EIS based on an issuance of the draft EIS in June 2019.

Schedule for Environmental Review

Issuance of Notice of Availability of the final EIS--March 6, 2020
90-day Federal Authorization Decision Deadline--June 4, 2020

    In an additional notice issued on August 31, 2018, the Commission 
identified February 6, 2020 as the anticipated final order issuance for 
the Alaska LNG Project. Based on the revised final EIS schedule, the 
Commission currently anticipates issuing a final order for the project 
no later than:

Issuance of Final Order--June 4, 2020

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies are kept informed of the 
project's progress.

Additional Information

    In order to receive notification of the issuance of the EIS and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP17-178), and follow the 
instructions. For assistance with access to eLibrary, the helpline can 
be reached at (866) 208-3676, TTY (202) 502-8659, or at 
FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: February 28, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-03995 Filed 3-5-19; 8:45 am]
 BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.