Connecticut Yankee Atomic Power Company, Haddam Neck Independent Spent Fuel Storage Installation, 8122-8124 [2019-03966]
Download as PDF
8122
Federal Register / Vol. 84, No. 44 / Wednesday, March 6, 2019 / Notices
outlines solicitation-specific aspects of
the project (such as the proposed
technology innovation and project
objectives with associated level of
technical risk). In the past, this Project
Pitch (previously referred to as the
Executive Summary) was an optional
submission via email as an attached two
to three-page (maximum) document and
was often in varying formats or missing
some parts of the required document
elements, which in turn caused delays
or additional corrections on behalf of
the proposer. The NSF SBIR/STTR
Phase I Project Pitch form captures the
same requested information, as outlined
in the NSF SBIR/STTR Phase I Program
solicitation, but all within one secure,
web-based form. In specific, the form
collects submitting proposer company
and team information; the proposed
technology innovation; the technical
objectives and challenges; and the
market opportunity. The form also
allows the proposer to choose (from a
drop-down menu) the most relevant
NSF SBIR/STTR Phase I technical topic
area, ensuring that the submitted Project
Pitch goes to the most appropriate
Program Director.
Respondents: Small businesses who
submit proposals to NSF’s SBIR/STTR
Phase I Program.
Estimated Number of Annual
Respondents: 2000.
Burden on the Public: 2 hours (per
response) for an annual total of 4000
hours.
Week of March 11, 2019—Tentative
Dated: February 28, 2019.
Suzanne H. Plimpton,
Reports Clearance Officer, National Science
Foundation.
For more information or to verify the
status of meetings, contact Denise
McGovern at 301–415–0681 or via email
at Denise.McGovern@nrc.gov. The
schedule for Commission meetings is
subject to change on short notice.
The NRC Commission Meeting
Schedule can be found on the internet
at: https://www.nrc.gov/public-involve/
public-meetings/schedule.html.
The NRC provides reasonable
accommodation to individuals with
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings, or
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.,
Braille, large print), please notify
Kimberly Meyer-Chambers, NRC
Disability Program Manager, at 301–
287–0739, by videophone at 240–428–
3217, or by email at Kimberly.MeyerChambers@nrc.gov. Determinations on
requests for reasonable accommodation
will be made on a case-by-case basis.
Members of the public may request to
receive this information electronically.
If you would like to be added to the
distribution, please contact the Nuclear
[FR Doc. 2019–04004 Filed 3–5–19; 8:45 am]
BILLING CODE 7555–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2019–0001]
Sunshine Act Meetings
Weeks of March 4, 11,
18, 25, April 1, 8, 2019.
PLACE: Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
STATUS: Public and Closed.
MATTERS TO BE CONSIDERED:
TIME AND DATE:
Week of March 4, 2019
Tuesday, March 5, 2019
10:00 a.m. Briefing on NRC
International Activities (Closed—
Ex. 1 & 9)
VerDate Sep<11>2014
18:35 Mar 05, 2019
Jkt 247001
There are no meetings scheduled for
the week of March 11, 2019.
Week of March 18, 2019—Tentative
Wednesday, March 20, 2019
10:00 a.m. Meeting with the
Organization of Agreement States
and the Conference of Radiation
Control Program Directors (Public)
(Contact: Paul Michalak: 301–415–
5804)
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
Week of March 25, 2019—Tentative
Thursday, March 28, 2019
9:00 a.m. Transformation at the NRC:
Innovation (Public Meeting)
(Contact: June Cai: 301–415–1771)
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
Week of April 1, 2019—Tentative
Thursday, April 4, 2019
10:00 a.m. Meeting with the Advisory
Committee on the Medical Uses of
Isotopes (Public Meeting) (Contact:
Kellee Jamerson: 301–415–7408)
This meeting will be webcast live at
the Web address—https://www.nrc.gov/.
Week of April 8, 2019—Tentative
There are no meetings scheduled for
the week of April 8, 2019.
CONTACT PERSON FOR MORE INFORMATION:
PO 00000
Frm 00052
Fmt 4703
Sfmt 4703
Regulatory Commission, Office of the
Secretary, Washington, DC 20555 (301–
415–1969), or by email at
Wendy.Moore@nrc.gov.
Dated at Rockville, Maryland, this 1st day
of March 2019.
For the Nuclear Regulatory Commission.
Denise L. McGovern,
Policy Coordinator, Office of the Secretary.
[FR Doc. 2019–04081 Filed 3–4–19; 11:15 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 72–39; NRC–2018–0256]
Connecticut Yankee Atomic Power
Company, Haddam Neck Independent
Spent Fuel Storage Installation
Nuclear Regulatory
Commission.
ACTION: Environmental assessment and
finding of no significant impact;
issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing an
environmental assessment (EA) and a
finding of no significant impact (FONSI)
for its review and approval of the
decommissioning funding plans
submitted by Connecticut Yankee
Atomic Power Company (CYAPCO) on
December 17, 2012, and December 14,
2015, for the independent spent fuel
storage installation (ISFSI) at Haddam
Neck in East Hampton, Connecticut.
DATES: The EA and FONSI referenced in
this document are available on March 6,
2019.
ADDRESSES: Please refer to Docket ID
NRC–2018–0256 when contacting the
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2018–0256. Address
questions about NRC Docket IDs in
Regulations.gov to Krupskaya Castellon;
telephone: 301–287–9221; email:
Krupskaya.Castellon@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
https://www.nrc.gov/reading-rm/
adams.html. To begin the search, select
‘‘Begin Web-based ADAMS Search.’’ For
SUMMARY:
E:\FR\FM\06MRN1.SGM
06MRN1
Federal Register / Vol. 84, No. 44 / Wednesday, March 6, 2019 / Notices
problems with ADAMS, please contact
the NRC’s Public Document Room (PDR)
reference staff at 1–800–397–4209, 301–
415–4737, or by email to pdr.resource@
nrc.gov. For the convenience of the
reader, instructions about obtaining
materials referenced in this document
are provided in the Availability of
Documents section.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
Pamela Longmire, Office of Nuclear
Material Safety and Safeguards, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–7465, email:
Pamela.Longmire@nrc.gov.
SUPPLEMENTARY INFORMATION:
planning regulations (76 FR 35512). The
final rule amended the NRC regulation,
10 CFR 72.30, which concerns financial
assurance and decommissioning for
ISFSIs. This regulation now requires
each holder of, or applicant for, a
license under 10 CFR part 72 to submit,
for NRC review and approval, a DFP.
The purpose of the DFP is to
demonstrate the licensee’s financial
assurance, i.e., that funds will be
available to decommission the ISFSI.
The NRC staff is reviewing the DFPs
submitted by CYAPCO on December 17,
2012, and December 14, 2015.
Specifically, the NRC must determine
whether CYAPCO’s DFPs contain the
information required by 10 CFR 72.30(b)
and 10 CFR 72.30(c) and whether
CYAPCO has provided reasonable
assurance that funds will be available to
decommission the ISFSI.
I. Introduction
The NRC is considering the approval
of the decommissioning funding plans
(DFPs) for the Haddam Neck ISFSI.
CYAPCO submitted an initial DFP and
an updated DFP for NRC review and
approval by letters dated December 17,
2012 (ADAMS Accession No.
ML12363A024), and December 14, 2015
(ADAMS Accession No. ML16020A209),
respectively. The NRC staff has
prepared a final EA (ADAMS Accession
No. ML19053A429) in support of its
review of CYAPCO’s DFPs, in
accordance with the NRC regulations in
part 51 of title 10 of the Code of Federal
Regulations (10 CFR), ‘‘Environmental
Protection Regulations for Domestic
Licensing and Related Regulatory
Functions,’’ which implement the
National Environmental Policy Act of
1969, as amended (42 U.S.C. 4321 et
seq.). Based on the EA, the NRC staff has
determined that approval of the DFPs
for the Haddam Neck ISFSI will not
significantly affect the quality of the
human environment, and accordingly,
the staff has concluded that a FONSI is
appropriate. The NRC staff further finds
that preparation of an environmental
impact statement (EIS) is not warranted.
Description of the Proposed Action
The proposed action is the NRC’s
review and approval of CYAPCO’s DFPs
submitted in accordance with 10 CFR
72.30(b) and 72.30(c). To approve the
DFPs, the NRC evaluates whether the
decommissioning cost estimate (DCE)
adequately estimates the cost to conduct
the required ISFSI decommissioning
activities prior to license termination,
including identification of the volume
of onsite subsurface material containing
residual radioactivity that will require
remediation to meet the license
termination criteria in 10 CFR 20.1402
or 10 CFR 20.1403. The NRC also
evaluates whether the aggregate dollar
amount of CYAPCO financial
instruments provides adequate financial
assurance to cover the DCE and that the
financial instruments meet the criteria
of 10 CFR 72.30(e). Finally, the NRC
evaluates whether the effects of the
following events have been considered
in CYAPCO’s submittal: (1) Spills of
radioactive material producing
additional residual radioactivity in
onsite subsurface material; (2) facility
modifications; (3) changes in authorized
possession limits; and (4) actual
remediation costs that exceed the
previous cost estimate, consistent with
10 CFR 72.30(c).
The proposed action does not require
any changes to the ISFSI’s licensed
routine operations, maintenance
activities, or monitoring programs, nor
does it require any new construction or
land-disturbing activities. The scope of
the proposed action concerns only the
NRC’s review and approval of
CYAPCO’s DFPs. The scope of the
proposed action does not include, and
will not result in, the review and
approval of any decontamination or
decommissioning activity or license
II. Environmental Assessment
Background
The Haddam Neck ISFSI is located in
East Hampton, Connecticut. CYAPCO is
authorized by the NRC, under License
No. SFGL–21, to store spent nuclear fuel
at the Haddam Neck ISFSI.
The NRC requires its licensees to plan
for the eventual decommissioning of
their licensed facilities prior to license
termination. On June 17, 2011, the NRC
published a final rule in the Federal
Register amending its decommissioning
VerDate Sep<11>2014
18:35 Mar 05, 2019
Jkt 247001
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
8123
termination for the ISFSI or any other
part of Haddam Neck.
Need for the Proposed Action
The proposed action provides a
means for the NRC to confirm that
CYAPCO will have sufficient funding to
cover the costs of decommissioning the
ISFSI, including the reduction of the
residual radioactivity at the ISFSI to the
level specified by the applicable NRC
license termination regulations
concerning release of the property (10
CFR 20.1402 or 10 CFR 20.1403).
Environmental Impacts of the Proposed
Action
The NRC’s approval of the DFPs will
not change the scope or nature of the
operation of the ISFSI and will not
authorize any changes to licensed
operations or maintenance activities.
The NRC’s approval of the DFPs will not
result in any changes in the types,
characteristics, or quantities of
radiological or non-radiological
effluents released into the environment
from the ISFSI, or result in the creation
of any solid waste. Moreover, the
approval of the DFPs will not authorize
any construction activity or facility
modification. Therefore, the NRC staff
concludes that the approval of
CYAPCO’s DFPs is a procedural and
administrative action that will not result
in any significant impact to the
environment.
Section 106 of the National Historic
Preservation Act of 1966, as amended
(54 U.S.C. 30618) (NHPA), requires
Federal agencies to consider the effects
of their undertakings on historic
properties. In accordance with the
NHPA implementing regulations at 36
CFR part 800, ‘‘Protection of Historic
Properties,’’ the NRC’s approval of
CYAPCO’s DFPs constitutes a Federal
undertaking. The NRC, however, has
determined that the approval of the
DFPs is a type of undertaking that does
not have the potential to cause effects
on historic properties, assuming such
historic properties were present,
because the NRC’s approval of
CYAPCO’s DFPs will not authorize or
result in changes to licensed operations
or maintenance activities, or changes in
the types, characteristics, or quantities
of radiological or non-radiological
effluents released into the environment
from the ISFSI, or result in the creation
of any solid waste. Therefore, in
accordance with 36 CFR 800.3(a)(1), no
consultation is required under Section
106 of the NHPA.
Under Section 7 of the Endangered
Species Act of 1973 (16 U.S.C. 1531 et
seq.) (ESA), prior to taking a proposed
action, a Federal agency must determine
E:\FR\FM\06MRN1.SGM
06MRN1
8124
Federal Register / Vol. 84, No. 44 / Wednesday, March 6, 2019 / Notices
whether (i) endangered and threatened
species or their critical habitats are
known to be in the vicinity of the
proposed action and if so, whether (ii)
the proposed Federal action may affect
listed species or critical habitats. The
NRC has determined that the proposed
action will have no effect on any listed
species or their critical habitats because
the NRC’s approval of CYAPCO’s DFPs
will not authorize or result in changes
to licensed operations or maintenance
activities, or changes in the types,
characteristics, or quantities of
radiological or non-radiological
effluents released into the environment
from the ISFSI, or result in the creation
of any solid waste.
Alternative to the Proposed Action
In addition to the proposed action, the
NRC evaluated the no-action alternative.
The no-action alternative is to deny
CYAPCO’s DFPs. A denial of a DFP that
meets the criteria of 10 CFR 72.30(b) or
72.30(c) does not support the regulatory
intent of the 2011 rulemaking. As noted
in the EA for the 2011 rulemaking
(ADAMS Accession No. ML090500648),
not promulgating the 2011 final rule
would have increased the likelihood of
additional legacy sites. Thus, denying
CYAPCO’s DFPs, which the NRC has
found to meet the criteria of 10 CFR
72.30(b) and 72.30(c), will undermine
the licensee’s decommissioning
planning. On this basis, the NRC has
concluded that the no-action alternative
is not a viable alternative.
Agencies and Persons Consulted
The NRC staff consulted with other
agencies and parties regarding the
environmental impacts of the proposed
action. The NRC provided a draft of its
EA to the Connecticut Department of
Energy and Environmental Protection
(State) by letter dated September 2, 2016
(ADAMS Accession No. ML17139C482),
and gave the State 30 days to respond.
The State did not respond. The NRC
also consulted with the Fish and
Wildlife Service by letter dated
September 2, 2016 (ADAMS Accession
No. ML16250A476). However, the NRC
staff has determined that consultation
under ESA Section 7 is not required
because the proposed action is
administrative/procedural in nature and
will not affect listed species or critical
habitat (ADAMS Accession No.
ML17135A062).
III. Finding of No Significant Impact
The NRC staff has determined that the
proposed action, the review and
approval of CYAPCO’s initial and
updated DFPs, submitted in accordance
with 10 CFR 72.30(b) and 72.30(c), will
not authorize or result in changes to
licensed operations or maintenance
activities, or changes in the types,
characteristics, or quantities of
radiological or non-radiological
effluents released into the environment
from the ISFSI, or result in the creation
of any solid waste. Moreover, the
approval of the DFPs will not authorize
any construction activity, facility
modification, or any other landdisturbing activity. The NRC staff has
concluded that the proposed action is a
procedural and administrative action
and as such, that the proposed action
will not have a significant effect on the
quality of the human environment.
Therefore, the NRC staff has determined
not to prepare an EIS for the proposed
action but will issue this FONSI.
IV. Availability of Documents
The following documents, related to
this notice, can be found using any of
the methods provided in the following
table. Instructions for accessing ADAMS
were provided under the ADDRESSES
section of this document.
ADAMS
Accession
No.
Date
Document
December 17, 2012 ...................................
December 14, 2015 ...................................
February 1, 2009 .......................................
May 15, 2017 ............................................
September 2, 2016 ....................................
September 2, 2016 ....................................
Submission of CYAPCO decommissioning funding plan ...........................................
Submission of CYAPCO triennial decommissioning funding plan ..............................
Environmental Assessment for Final Rule—Decommissioning Planning ...................
Note to File re Sct 7 Consultations for ISFSI DFPs ...................................................
Consultation Letter: ML16250A526–RLSO .................................................................
Letter to M. Miller re: U.S. Nuclear Regulatory Commission Preliminary Determination of No Effects Regarding the Haddam Neck Plant Independent Spent Fuel
Storage Installation Decommissioning Funding Plan.
NRC staff’s Final EA for the approval of the decommissioning funding plan ............
February 20, 2019 .....................................
Dated at Rockville, Maryland, on February
28, 2019.
For the Nuclear Regulatory Commission.
John McKirgan,
Chief, Spent Fuel Licensing Branch, Division
of Spent Fuel Management, Office of Nuclear
Material Safety and Safeguards.
[FR Doc. 2019–03966 Filed 3–5–19; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 72–35; NRC–2018–0258]
Energy Northwest, Columbia
Generating Station, Independent Spent
Fuel Storage Installation
Nuclear Regulatory
Commission.
AGENCY:
VerDate Sep<11>2014
18:35 Mar 05, 2019
Jkt 247001
Environmental assessment and
finding of no significant impact;
issuance.
ACTION:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing an
environmental assessment (EA) and a
finding of no significant impact (FONSI)
for its review and approval of the
decommissioning funding plans
submitted by Energy Northwest (EN) on
December 17, 2012, and December 15,
2015, for the independent spent fuel
storage installation (ISFSI) at Columbia
Generating Station in Richland,
Washington.
DATES: The EA and FONSI referenced in
this document are available on March 6,
2019.
ADDRESSES: Please refer to Docket ID
NRC–2018–0258 when contacting the
SUMMARY:
PO 00000
Frm 00054
Fmt 4703
Sfmt 4703
ML12363A024
ML16020A209
ML090500648
ML17135A062
ML17139C482
ML16250A476
ML19053A429
NRC about the availability of
information regarding this document.
You may obtain publicly-available
information related to this document
using any of the following methods:
• Federal Rulemaking Website: Go to
https://www.regulations.gov and search
for Docket ID NRC–2018–0258. Address
questions about NRC Docket IDs in
Regulations.gov to Krupskaya Castellon;
telephone: 301–287–9221; email:
Krupskaya.Castellon@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may obtain publiclyavailable documents online in the
ADAMS Public Documents collection at
E:\FR\FM\06MRN1.SGM
06MRN1
Agencies
[Federal Register Volume 84, Number 44 (Wednesday, March 6, 2019)]
[Notices]
[Pages 8122-8124]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-03966]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 72-39; NRC-2018-0256]
Connecticut Yankee Atomic Power Company, Haddam Neck Independent
Spent Fuel Storage Installation
AGENCY: Nuclear Regulatory Commission.
ACTION: Environmental assessment and finding of no significant impact;
issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an
environmental assessment (EA) and a finding of no significant impact
(FONSI) for its review and approval of the decommissioning funding
plans submitted by Connecticut Yankee Atomic Power Company (CYAPCO) on
December 17, 2012, and December 14, 2015, for the independent spent
fuel storage installation (ISFSI) at Haddam Neck in East Hampton,
Connecticut.
DATES: The EA and FONSI referenced in this document are available on
March 6, 2019.
ADDRESSES: Please refer to Docket ID NRC-2018-0256 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC-2018-0256. Address
questions about NRC Docket IDs in Regulations.gov to Krupskaya
Castellon; telephone: 301-287-9221; email: Krupskaya.Castellon@nrc.gov.
For technical questions, contact the individual listed in the FOR
FURTHER INFORMATION CONTACT section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For
[[Page 8123]]
problems with ADAMS, please contact the NRC's Public Document Room
(PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email to
pdr.resource@nrc.gov. For the convenience of the reader, instructions
about obtaining materials referenced in this document are provided in
the Availability of Documents section.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Pamela Longmire, Office of Nuclear
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001; telephone: 301-415-7465, email:
Pamela.Longmire@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is considering the approval of the decommissioning funding
plans (DFPs) for the Haddam Neck ISFSI. CYAPCO submitted an initial DFP
and an updated DFP for NRC review and approval by letters dated
December 17, 2012 (ADAMS Accession No. ML12363A024), and December 14,
2015 (ADAMS Accession No. ML16020A209), respectively. The NRC staff has
prepared a final EA (ADAMS Accession No. ML19053A429) in support of its
review of CYAPCO's DFPs, in accordance with the NRC regulations in part
51 of title 10 of the Code of Federal Regulations (10 CFR),
``Environmental Protection Regulations for Domestic Licensing and
Related Regulatory Functions,'' which implement the National
Environmental Policy Act of 1969, as amended (42 U.S.C. 4321 et seq.).
Based on the EA, the NRC staff has determined that approval of the DFPs
for the Haddam Neck ISFSI will not significantly affect the quality of
the human environment, and accordingly, the staff has concluded that a
FONSI is appropriate. The NRC staff further finds that preparation of
an environmental impact statement (EIS) is not warranted.
II. Environmental Assessment
Background
The Haddam Neck ISFSI is located in East Hampton, Connecticut.
CYAPCO is authorized by the NRC, under License No. SFGL-21, to store
spent nuclear fuel at the Haddam Neck ISFSI.
The NRC requires its licensees to plan for the eventual
decommissioning of their licensed facilities prior to license
termination. On June 17, 2011, the NRC published a final rule in the
Federal Register amending its decommissioning planning regulations (76
FR 35512). The final rule amended the NRC regulation, 10 CFR 72.30,
which concerns financial assurance and decommissioning for ISFSIs. This
regulation now requires each holder of, or applicant for, a license
under 10 CFR part 72 to submit, for NRC review and approval, a DFP. The
purpose of the DFP is to demonstrate the licensee's financial
assurance, i.e., that funds will be available to decommission the
ISFSI. The NRC staff is reviewing the DFPs submitted by CYAPCO on
December 17, 2012, and December 14, 2015. Specifically, the NRC must
determine whether CYAPCO's DFPs contain the information required by 10
CFR 72.30(b) and 10 CFR 72.30(c) and whether CYAPCO has provided
reasonable assurance that funds will be available to decommission the
ISFSI.
Description of the Proposed Action
The proposed action is the NRC's review and approval of CYAPCO's
DFPs submitted in accordance with 10 CFR 72.30(b) and 72.30(c). To
approve the DFPs, the NRC evaluates whether the decommissioning cost
estimate (DCE) adequately estimates the cost to conduct the required
ISFSI decommissioning activities prior to license termination,
including identification of the volume of onsite subsurface material
containing residual radioactivity that will require remediation to meet
the license termination criteria in 10 CFR 20.1402 or 10 CFR 20.1403.
The NRC also evaluates whether the aggregate dollar amount of CYAPCO
financial instruments provides adequate financial assurance to cover
the DCE and that the financial instruments meet the criteria of 10 CFR
72.30(e). Finally, the NRC evaluates whether the effects of the
following events have been considered in CYAPCO's submittal: (1) Spills
of radioactive material producing additional residual radioactivity in
onsite subsurface material; (2) facility modifications; (3) changes in
authorized possession limits; and (4) actual remediation costs that
exceed the previous cost estimate, consistent with 10 CFR 72.30(c).
The proposed action does not require any changes to the ISFSI's
licensed routine operations, maintenance activities, or monitoring
programs, nor does it require any new construction or land-disturbing
activities. The scope of the proposed action concerns only the NRC's
review and approval of CYAPCO's DFPs. The scope of the proposed action
does not include, and will not result in, the review and approval of
any decontamination or decommissioning activity or license termination
for the ISFSI or any other part of Haddam Neck.
Need for the Proposed Action
The proposed action provides a means for the NRC to confirm that
CYAPCO will have sufficient funding to cover the costs of
decommissioning the ISFSI, including the reduction of the residual
radioactivity at the ISFSI to the level specified by the applicable NRC
license termination regulations concerning release of the property (10
CFR 20.1402 or 10 CFR 20.1403).
Environmental Impacts of the Proposed Action
The NRC's approval of the DFPs will not change the scope or nature
of the operation of the ISFSI and will not authorize any changes to
licensed operations or maintenance activities. The NRC's approval of
the DFPs will not result in any changes in the types, characteristics,
or quantities of radiological or non-radiological effluents released
into the environment from the ISFSI, or result in the creation of any
solid waste. Moreover, the approval of the DFPs will not authorize any
construction activity or facility modification. Therefore, the NRC
staff concludes that the approval of CYAPCO's DFPs is a procedural and
administrative action that will not result in any significant impact to
the environment.
Section 106 of the National Historic Preservation Act of 1966, as
amended (54 U.S.C. 30618) (NHPA), requires Federal agencies to consider
the effects of their undertakings on historic properties. In accordance
with the NHPA implementing regulations at 36 CFR part 800, ``Protection
of Historic Properties,'' the NRC's approval of CYAPCO's DFPs
constitutes a Federal undertaking. The NRC, however, has determined
that the approval of the DFPs is a type of undertaking that does not
have the potential to cause effects on historic properties, assuming
such historic properties were present, because the NRC's approval of
CYAPCO's DFPs will not authorize or result in changes to licensed
operations or maintenance activities, or changes in the types,
characteristics, or quantities of radiological or non-radiological
effluents released into the environment from the ISFSI, or result in
the creation of any solid waste. Therefore, in accordance with 36 CFR
800.3(a)(1), no consultation is required under Section 106 of the NHPA.
Under Section 7 of the Endangered Species Act of 1973 (16 U.S.C.
1531 et seq.) (ESA), prior to taking a proposed action, a Federal
agency must determine
[[Page 8124]]
whether (i) endangered and threatened species or their critical
habitats are known to be in the vicinity of the proposed action and if
so, whether (ii) the proposed Federal action may affect listed species
or critical habitats. The NRC has determined that the proposed action
will have no effect on any listed species or their critical habitats
because the NRC's approval of CYAPCO's DFPs will not authorize or
result in changes to licensed operations or maintenance activities, or
changes in the types, characteristics, or quantities of radiological or
non-radiological effluents released into the environment from the
ISFSI, or result in the creation of any solid waste.
Alternative to the Proposed Action
In addition to the proposed action, the NRC evaluated the no-action
alternative. The no-action alternative is to deny CYAPCO's DFPs. A
denial of a DFP that meets the criteria of 10 CFR 72.30(b) or 72.30(c)
does not support the regulatory intent of the 2011 rulemaking. As noted
in the EA for the 2011 rulemaking (ADAMS Accession No. ML090500648),
not promulgating the 2011 final rule would have increased the
likelihood of additional legacy sites. Thus, denying CYAPCO's DFPs,
which the NRC has found to meet the criteria of 10 CFR 72.30(b) and
72.30(c), will undermine the licensee's decommissioning planning. On
this basis, the NRC has concluded that the no-action alternative is not
a viable alternative.
Agencies and Persons Consulted
The NRC staff consulted with other agencies and parties regarding
the environmental impacts of the proposed action. The NRC provided a
draft of its EA to the Connecticut Department of Energy and
Environmental Protection (State) by letter dated September 2, 2016
(ADAMS Accession No. ML17139C482), and gave the State 30 days to
respond. The State did not respond. The NRC also consulted with the
Fish and Wildlife Service by letter dated September 2, 2016 (ADAMS
Accession No. ML16250A476). However, the NRC staff has determined that
consultation under ESA Section 7 is not required because the proposed
action is administrative/procedural in nature and will not affect
listed species or critical habitat (ADAMS Accession No. ML17135A062).
III. Finding of No Significant Impact
The NRC staff has determined that the proposed action, the review
and approval of CYAPCO's initial and updated DFPs, submitted in
accordance with 10 CFR 72.30(b) and 72.30(c), will not authorize or
result in changes to licensed operations or maintenance activities, or
changes in the types, characteristics, or quantities of radiological or
non-radiological effluents released into the environment from the
ISFSI, or result in the creation of any solid waste. Moreover, the
approval of the DFPs will not authorize any construction activity,
facility modification, or any other land-disturbing activity. The NRC
staff has concluded that the proposed action is a procedural and
administrative action and as such, that the proposed action will not
have a significant effect on the quality of the human environment.
Therefore, the NRC staff has determined not to prepare an EIS for the
proposed action but will issue this FONSI.
IV. Availability of Documents
The following documents, related to this notice, can be found using
any of the methods provided in the following table. Instructions for
accessing ADAMS were provided under the ADDRESSES section of this
document.
------------------------------------------------------------------------
ADAMS Accession
Date Document No.
------------------------------------------------------------------------
December 17, 2012............ Submission of CYAPCO ML12363A024
decommissioning
funding plan.
December 14, 2015............ Submission of CYAPCO ML16020A209
triennial
decommissioning
funding plan.
February 1, 2009............. Environmental ML090500648
Assessment for Final
Rule--Decommissionin
g Planning.
May 15, 2017................. Note to File re Sct 7 ML17135A062
Consultations for
ISFSI DFPs.
September 2, 2016............ Consultation Letter: ML17139C482
ML16250A526-RLSO.
September 2, 2016............ Letter to M. Miller ML16250A476
re: U.S. Nuclear
Regulatory
Commission
Preliminary
Determination of No
Effects Regarding
the Haddam Neck
Plant Independent
Spent Fuel Storage
Installation
Decommissioning
Funding Plan.
February 20, 2019............ NRC staff's Final EA ML19053A429
for the approval of
the decommissioning
funding plan.
------------------------------------------------------------------------
Dated at Rockville, Maryland, on February 28, 2019.
For the Nuclear Regulatory Commission.
John McKirgan,
Chief, Spent Fuel Licensing Branch, Division of Spent Fuel Management,
Office of Nuclear Material Safety and Safeguards.
[FR Doc. 2019-03966 Filed 3-5-19; 8:45 am]