LS Power Grid New York, LLC, LS Power Grid New York Corporation I; Notice of Petition for Declaratory Order, 698-699 [2019-00516]
Download as PDF
amozie on DSK3GDR082PROD with NOTICES1
698
Federal Register / Vol. 84, No. 21 / Thursday, January 31, 2019 / Notices
Description: Notice of Non-Material
Change in Status of Buffalo Dunes Wind
Project, LLC, et. al.
Filed Date: 1/22/19.
Accession Number: 20190122–5338.
Comments Due: 5 p.m. ET 2/12/19.
Docket Numbers: ER18–1189–001;
ER18–1188–002.
Applicants: Meadow Lake Wind Farm
VI LLC, Prairie Queen Wind Farm LLC.
Description: Notice of Non-Material
Change in Status of Meadow Lake Wind
Farm VI LLC, et al.
Filed Date: 1/22/19.
Accession Number: 20190122–5324.
Comments Due: 5 p.m. ET 2/12/19.
Docket Numbers: ER18–1777–003;
ER10–1342–005.
Applicants: Meadowlark Wind I LLC,
CP Energy Marketing (US) Inc.
Description: Notice of Change in
Status of Meadowlark Wind I LLC, et al.
Filed Date: 1/22/19.
Accession Number: 20190122–5322.
Comments Due: 5 p.m. ET 2/12/19.
Docket Numbers: ER18–1935–001.
Applicants: Alabama Power
Company.
Description: Compliance filing: Gulf
NITSA Compliance Filing to be effective
1/1/2019.
Filed Date: 1/25/19.
Accession Number: 20190125–5077.
Comments Due: 5 p.m. ET 2/15/19.
Docket Numbers: ER18–1936–001.
Applicants: Alabama Power
Company.
Description: Compliance filing: Gulf
PTP Agreements (Daniel 1&2 and
Scherer 3) Compliance Filing to be
effective 1/1/2019.
Filed Date: 1/25/19.
Accession Number: 20190125–5078.
Comments Due: 5 p.m. ET 2/15/19.
Docket Numbers: ER18–1937–001.
Applicants: Alabama Power
Company.
Description: Compliance filing: Gulf
PTP Agreements (Kingfisher I and II)
Compliance Filing to be effective 1/1/
2019.
Filed Date: 1/25/19.
Accession Number: 20190125–5079.
Comments Due: 5 p.m. ET 2/15/19.
Docket Numbers: ER18–2330–001.
Applicants: Enel Green Power
Rattlesnake Creek Wind Project, LLC.
Description: Notice of Non-Material
Change in Status of Enel Green Power
Rattlesnake Creek Wind Project, LLC.
Filed Date: 1/22/19.
Accession Number: 20190122–5333.
Comments Due: 5 p.m. ET 2/12/19.
Docket Numbers: ER19–263–001.
Applicants: AMP Transmission, LLC,
PJM Interconnection, L.L.C.
Description: Tariff Amendment:
AMPT submits its response to the
VerDate Sep<11>2014
20:21 Jan 30, 2019
Jkt 247001
Commission’s 12/26/2018 Deficiency
Letter to be effective 1/1/2019.
Filed Date: 1/25/19.
Accession Number: 20190125–5107.
Comments Due: 5 p.m. ET 2/15/19.
Docket Numbers: ER19–419–001.
Applicants: Midcontinent
Independent System Operator, Inc.,
ALLETE, Inc.
Description: Tariff Amendment:
2019–01–25_SA 3217 MP–GRE ICA
Substitute (Verndale) to be effective
11/30/2018.
Filed Date: 1/25/19.
Accession Number: 20190125–5057.
Comments Due: 5 p.m. ET 2/15/19.
Docket Numbers: ER19–868–000.
Applicants: Pacific Gas and Electric
Company.
Description: § 205(d) Rate Filing:
Amendment (Supp. No. 4) to Peninsula
Corridor JPB Supplement No. 3 (RS 249)
to be effective 2/1/2019.
Filed Date: 1/25/19.
Accession Number: 20190125–5000.
Comments Due: 5 p.m. ET 2/15/19.
Docket Numbers: ER19–869–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
2824R5 KMEA & Sunflower Meter
Agent Agreement to be effective 1/1/
2019.
Filed Date: 1/25/19.
Accession Number: 20190125–5005.
Comments Due: 5 p.m. ET 2/15/19.
Docket Numbers: ER19–870–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
Westar Energy Formula Rate Revisions
to Modify Depreciation Rates to be
effective 1/1/2019.
Filed Date: 1/25/19.
Accession Number: 20190125–5063.
Comments Due: 5 p.m. ET 2/15/19.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
PO 00000
Frm 00053
Fmt 4703
Sfmt 4703
Dated: January 25, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019–00528 Filed 1–30–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL19–30–000]
LS Power Grid New York, LLC, LS
Power Grid New York Corporation I;
Notice of Petition for Declaratory Order
Take notice that on January 10, 2019,
pursuant to section 219 of the Federal
Power Act,1 Rule 207 of the Federal
Energy Regulatory Commission’s
(Commission) Rules of Practice and
Procedure, 18 CFR 385.207 (2018), LS
Power Grid New York, LLC and LS
Power Grid New York Corporation I
(collectively LSPG–NY or Petitioners),
filed a petition for a declaratory order
requesting the Commission authorize
full recovery of prudently-incurred costs
in the event that the AC Transmission
Upgrades Project, designated to LSPG–
NY and New York Power Authority, is
abandoned for reasons beyond the
Petitioners control, as more fully
explained in the petition.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Petitioner.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
1 16
E:\FR\FM\31JAN1.SGM
U.S.C. 824ds (2018).
31JAN1
Federal Register / Vol. 84, No. 21 / Thursday, January 31, 2019 / Notices
There is an ‘‘eSubscription’’ link on the
website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern time
on February 11, 2019.
Dated: January 16, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–00516 Filed 1–30–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL19–34–000]
amozie on DSK3GDR082PROD with NOTICES1
Brookfield Energy Marketing LP v. PJM
Interconnection, L.L.C.; Notice of
Complaint
Take notice that on January 18, 2019,
pursuant to sections 206, and 306 of the
Federal Power Act, 16 U.S.C. 824(e),
825(e), and Rule 206 of the Federal
Energy Regulatory Commission’s
(Commission) Rules of Practice and
Procedure, 18 CFR 385.206 (2018),
Brookfield Energy Marketing LP
(Complainant or BEMLP) filed a formal
complaint (complaint) against PJM
Interconnection, L.L.C. (Respondent or
PJM) alleging that PJM’s pseudo-tie
requirements applicable to external
resources seeking to participate in PJM’s
capacity market as applied by PJM are
unjust, unreasonable and unduly
discriminatory and preferential, all as
more fully explained in the complaint.
The Complainant certifies that copies
of the complaint has been served on the
contacts for the Respondent as listed on
the Commission’s list of Corporate
Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
VerDate Sep<11>2014
20:21 Jan 30, 2019
Jkt 247001
intervene, and protests must be served
on the Complainant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an ‘‘eSubscription’’ link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on February 7, 2019.
Dated: January 22, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019–00514 Filed 1–30–19; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG19–48–000.
Applicants: Terra-Gen CA Windpower
Development, LLC.
Description: Notice of SelfCertification of Exempt Wholesale
Generator Status of Terra-Gen CA
Windpower Development, LLC.
Filed Date: 1/11/19.
Accession Number: 20190111–5026.
Comments Due: 5 p.m. ET 2/1/19.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER11–2774–002.
Applicants: Virginia Electric and
Power Company, Dominion Energy
Generation Marketing, Inc., Dominion
Energy Nuclear Connecticut, Inc.,
Dominion Bridgeport Fuel Cell, LLC.
Description: Notice of Non-Material
Changes in Fuel Procurement
Operations of Dominion Resources
Services, Inc., on behalf of Virginia
Electric and Power Company, et al.
PO 00000
Frm 00054
Fmt 4703
Sfmt 4703
699
Filed Date: 1/10/19.
Accession Number: 20190110–5155.
Comments Due: 5 p.m. ET 1/31/19.
Docket Numbers: ER18–2449–001.
Applicants: Midcontinent
Independent System Operator, Inc.,
ALLETE, Inc.
Description: ALLETE, Inc. submits
supplement to September 18, 2018 and
November 15, 2018 tariff filings.
Filed Date: 1/10/19.
Accession Number: 20190110–5152.
Comments Due: 5 p.m. ET 1/31/19.
Docket Numbers: ER18–896–001.
Applicants: Meadow Lake Wind Farm
II LLC.
Description: Report Filing: Refund
Report Filing to be effective N/A.
Filed Date: 1/11/19.
Accession Number: 20190111–5017.
Comments Due: 5 p.m. ET 2/1/19.
Docket Numbers: ER18–2231–002.
Applicants: Duke Energy Carolinas,
LLC.
Description: Compliance filing: DEC
Revised Depreciation Rates (RS–514)
Filing (Correct Metadata) to be effective
8/1/2018.
Filed Date: 1/11/19.
Accession Number: 20190111–5099.
Comments Due: 5 p.m. ET 2/1/19.
Docket Numbers: ER19–794–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing: 3517
Plum Creek Wind, LLC GIA to be
effective 12/19/2018.
Filed Date: 1/11/19.
Accession Number: 20190111–5016.
Comments Due: 5 p.m. ET 2/1/19.
Docket Numbers: ER19–795–000.
Applicants: PacifiCorp.
Description: § 205(d) Rate Filing:
Exelon NITSA (OR D.A.) Rev 2 to be
effective 1/1/2019.
Filed Date: 1/11/19.
Accession Number: 20190111–5020.
Comments Due: 5 p.m. ET 2/1/19.
Docket Numbers: ER19–796–000.
Applicants: Duke Energy Indiana,
LLC, PJM Interconnection, L.L.C.
Description: § 205(d) Rate Filing:
Duke Energy submits Interconnection
Agreement SA No. 5254 to be effective
12/12/2018.
Filed Date: 1/11/19.
Accession Number: 20190111–5021.
Comments Due: 5 p.m. ET 2/1/19.
Docket Numbers: ER19–797–000.
Applicants: New York State Electric &
Gas Corporation, New York
Independent System Operator, Inc.
Description: § 205(d) Rate Filing: 205:
NYSEG–MAIT CRA No. 2444 to be
effective 12/17/2018.
Filed Date: 1/11/19.
Accession Number: 20190111–5027.
E:\FR\FM\31JAN1.SGM
31JAN1
Agencies
[Federal Register Volume 84, Number 21 (Thursday, January 31, 2019)]
[Notices]
[Pages 698-699]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-00516]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL19-30-000]
LS Power Grid New York, LLC, LS Power Grid New York Corporation
I; Notice of Petition for Declaratory Order
Take notice that on January 10, 2019, pursuant to section 219 of
the Federal Power Act,\1\ Rule 207 of the Federal Energy Regulatory
Commission's (Commission) Rules of Practice and Procedure, 18 CFR
385.207 (2018), LS Power Grid New York, LLC and LS Power Grid New York
Corporation I (collectively LSPG-NY or Petitioners), filed a petition
for a declaratory order requesting the Commission authorize full
recovery of prudently-incurred costs in the event that the AC
Transmission Upgrades Project, designated to LSPG-NY and New York Power
Authority, is abandoned for reasons beyond the Petitioners control, as
more fully explained in the petition.
---------------------------------------------------------------------------
\1\ 16 U.S.C. 824ds (2018).
---------------------------------------------------------------------------
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. Such notices,
motions, or protests must be filed on or before the comment date.
Anyone filing a motion to intervene or protest must serve a copy of
that document on the Petitioner.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an
original and 5 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC.
[[Page 699]]
There is an ``eSubscription'' link on the website that enables
subscribers to receive email notification when a document is added to a
subscribed docket(s). For assistance with any FERC Online service,
please email FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll
free). For TTY, call (202) 502-8659.
Comment Date: 5:00 p.m. Eastern time on February 11, 2019.
Dated: January 16, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-00516 Filed 1-30-19; 8:45 am]