Download as PDF Federal Register / Vol. 83, No. 238 / Wednesday, December 12, 2018 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP19–19–000] amozie on DSK3GDR082PROD with NOTICES1 Magnolia LNG, LLC; Notice of Application Take notice that on November 19, 2018, Magnolia LNG, LLC (Magnolia LNG), 1001 McKinney, Suite 600, Houston, Texas 77002, filed an application in Docket No. CP19–19–000, pursuant to Section 3(a) of the Natural Gas Act and the Federal Energy Regulatory Commission’s (Commission) regulations seeking an amendment to the authorization granted by the Commission on April 15, 2016, in Docket No. CP14–347–000. Through its amendment application, Magnolia LNG seeks authorization from the Commission to increase the total liquefied natural gas production capacity of its liquefaction project from the currently authorized 8 million tons per annum (MTPA) to 8.8 MTPA, or 1.4 billion cubic feet per day. The facilities are located in Lake Charles, Calcasieu Parish, Louisiana, as more fully described in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this application should be directed to Kinga Doris, Magnolia LNG, LLC, 1001 McKinney, Suite 600, Houston, Texas 77002, (713) 815–6921; or David L. Wochner, K&L Gates LLP, 1601 K Street, NW, Washington, DC 20006, (202) 778– 9000, David.Wochner@klgates.com. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental VerDate Sep<11>2014 18:39 Dec 11, 2018 Jkt 247001 Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 3 copies of filings made in the proceeding with the Commission and must provide a copy to the applicant and to every other party. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, and will be notified of any meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission and will not have the right PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 63849 to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the eFiling link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 3 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. Comment Date: December 27, 2018. Dated: December 6, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–26894 Filed 12–11–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric corporate filings: Docket Numbers: EC18–137–000. Applicants: Vermont Transco LLC. Description: Response to October 9, 2018 Deficiency Letter of Vermont Transco LLC. Filed Date: 10/24/18. Accession Number: 20181024–5167. Comments Due: 5 p.m. ET 12/13/18. Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG19–29–000. Applicants: Crocker Wind Farm, LLC. Description: Notice of SelfCertification of Exempt Wholesale Generator Status of Crocker Wind Farm, LLC. Filed Date: 12/3/18. Accession Number: 20181203–5142. Comments Due: 5 p.m. ET 12/24/18. Docket Numbers: EG19–30–000. Applicants: Wheelabrator Concord Company, L.P. Description: Self-Certification of Exempt Wholesale Generator Status of Wheelabrator Concord Company, L.P. Filed Date: 12/3/18. Accession Number: 20181203–5236. Comments Due: 5 p.m. ET 12/24/18. Docket Numbers: EG19–31–000. Applicants: Vermillion Power, L.L.C. Description: Self-Certification of EG or FC of Vermillion Power, L.L.C. Filed Date: 12/3/18. Accession Number: 20181203–5265. Comments Due: 5 p.m. ET 12/24/18. Take notice that the Commission received the following electric rate filings: E:\FR\FM\12DEN1.SGM 12DEN1

Agencies

[Federal Register Volume 83, Number 238 (Wednesday, December 12, 2018)]
[Notices]
[Page 63849]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-26894]



[[Page 63849]]

=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP19-19-000]


Magnolia LNG, LLC; Notice of Application

    Take notice that on November 19, 2018, Magnolia LNG, LLC (Magnolia 
LNG), 1001 McKinney, Suite 600, Houston, Texas 77002, filed an 
application in Docket No. CP19-19-000, pursuant to Section 3(a) of the 
Natural Gas Act and the Federal Energy Regulatory Commission's 
(Commission) regulations seeking an amendment to the authorization 
granted by the Commission on April 15, 2016, in Docket No. CP14-347-
000. Through its amendment application, Magnolia LNG seeks 
authorization from the Commission to increase the total liquefied 
natural gas production capacity of its liquefaction project from the 
currently authorized 8 million tons per annum (MTPA) to 8.8 MTPA, or 
1.4 billion cubic feet per day. The facilities are located in Lake 
Charles, Calcasieu Parish, Louisiana, as more fully described in the 
application which is on file with the Commission and open to public 
inspection. The filing may also be viewed on the web at https://www.ferc.gov using the eLibrary link. Enter the docket number excluding 
the last three digits in the docket number field to access the 
document. For assistance, contact FERC at [email protected] or 
call toll-free, (866) 208-3676 or TTY, (202) 502-8659.
    Any questions regarding this application should be directed to 
Kinga Doris, Magnolia LNG, LLC, 1001 McKinney, Suite 600, Houston, 
Texas 77002, (713) 815-6921; or David L. Wochner, K&L Gates LLP, 1601 K 
Street, NW, Washington, DC 20006, (202) 778-9000, 
[email protected].
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 3 copies of filings made in the proceeding with the Commission 
and must provide a copy to the applicant and to every other party. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, and will be 
notified of any meetings associated with the Commission's environmental 
review process. Environmental commentors will not be required to serve 
copies of filed documents on all other parties. However, the non-party 
commentors will not receive copies of all documents filed by other 
parties or issued by the Commission and will not have the right to seek 
court review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 3 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE, Washington, 
DC 20426.
    Comment Date: December 27, 2018.

    Dated: December 6, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-26894 Filed 12-11-18; 8:45 am]
 BILLING CODE 6717-01-P


This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.