Combined Notice of Filings #1, 61153-61154 [2018-25925]
Download as PDF
Federal Register / Vol. 83, No. 229 / Wednesday, November 28, 2018 / Notices
identified as the Greater Wenatchee
Irrigation District. Water would be
delivered from the District’s Veedol
Tank via an approximately 0.7-milelong, 12-inch-diameter buried steel pipe
to a new lower reservoir. The proposed
project would consist of: An upper 5- to
40-foot-high, 7,500-foot-long zoned
earth/rockfill ring dam enclosing the 70acre upper reservoir with storage
capacity of 2,000 acre-feet; a lower 35foot-high, 540-foot-long zoned earth/
rockfill primary dam and 10-foot-high,
830-foot-long earthen supplemental dam
enclosing the 80-acre lower reservoir
with storage capacity of 2,600 acre-feet;
a 600-foot-long, 14-foot-diameter
unlined or concrete-lined low pressure
tunnel; a 30-foot-diameter, 50-foot-high
concrete surge tank; two 5,200-foot-long,
10-foot-diameter steel penstocks; a
powerhouse with a 220-foot-high, 65foot-diameter steel and concrete shaft,
and two 150-megawatt (MW) reversible
pump-turbines/motor-generators for a
total installed capacity of 300 MW; a
1,200-foot-long, 17-foot-diameter
concrete-lined tailrace tunnel; a 230kilovolt (kV), 3.7-mile-long transmission
line interconnecting with the existing
Puget Sound Energy Rocky ReachCascade transmission line, and a
possible second transmission line
interconnecting with the existing 230kV Bonneville Power Administration
Rocky Reach-Columbia transmission
line 500 feet from the powerhouse.
The estimated average annual
generation of the project would be
473,040 megawatt-hours.
Applicant Contact: Matthew Shapiro,
CEO, Gridflex Energy, LLC, 1210 W.
Franklin St. #2, Boise, ID 837021, phone
(208) 246–9925.
FERC Contact: Peter McBride, (202)
502–8132, peter.mcbride@ferc.gov.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
VerDate Sep<11>2014
16:19 Nov 27, 2018
Jkt 247001
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426.
The first page of any filing should
include docket number P–14892–000.
More information about this project,
including a copy of the application, can
be viewed or printed on the eLibrary
link of Commission’s website at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14892) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: November 21, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–25923 Filed 11–27–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER13–1667–004.
Applicants: Battery Utility of Ohio,
LLC.
Description: Notice of Change in
Status of Battery Utility of Ohio, LLC.
Filed Date: 11/20/18.
Accession Number: 20181120–5221.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER17–1609–002.
Applicants: Carroll County Energy
LLC.
Description: Notice of Non-Material
Change in Status of Carroll County
Energy LLC.
Filed Date: 11/20/18.
Accession Number: 20181120–5254.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER18–2516–000.
Applicants: Willow Springs Solar,
LLC.
Description: Amendment to
September 28, 2018 Willow Springs
Solar, LLC tariff filing.
Filed Date: 11/20/18.
Accession Number: 20181120–5219.
Comments Due: 5 p.m. ET 11/27/18.
Docket Numbers: ER19–104–001.
Applicants: El Paso Electric Company.
Description: Tariff Amendment:
Concurrence of EPE to APS Service
Agreement No. 367 to be effective
9/7/2018.
Filed Date: 11/20/18.
Accession Number: 20181120–5167.
Comments Due: 5 p.m. ET 12/11/18.
PO 00000
Frm 00010
Fmt 4703
Sfmt 4703
61153
Docket Numbers: ER19–381–000.
Applicants: Power Holding LLC.
Description: Baseline eTariff Filing:
Application for Market Based Rate to be
effective 11/21/2018.
Filed Date: 11/20/18.
Accession Number: 20181120–5175.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER19–382–000.
Applicants: Duke Energy Carolinas,
LLC.
Description: § 205(d) Rate Filing: DECCity of Concord NITSA (SA–150)
Amendment to be effective 1/1/2019.
Filed Date: 11/20/18.
Accession Number: 20181120–5176.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER19–383–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Revisions to OATT and OA re
Regulation Market Clearing Price to be
effective 1/21/2019.
Filed Date: 11/20/18.
Accession Number: 20181120–5182.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER19–384–000.
Applicants: Pacific Gas and Electric
Company.
Description: Request for One-time
Limited Tariff Waiver, et al. of Pacific
Gas and Electric Company under ER19–
384.
Filed Date: 11/20/18.
Accession Number: 20181120–5218.
Comments Due: 5 p.m. ET 11/30/18.
Docket Numbers: ER19–385–000.
Applicants: NRG Power Marketing
LLC.
Description: Application to Recover
Fuel Procurement Costs of NRG Power
Marketing, LLC.
Filed Date: 11/20/18.
Accession Number: 20181120–5223.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER19–386–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Amendment to ISA, SA No. 2278,
Queue# None (Consent) to be effective
4/1/2010.
Filed Date: 11/21/18.
Accession Number: 20181121–5054.
Comments Due: 5 p.m. ET 12/12/18.
Docket Numbers: ER19–387–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA and CSA, SA Nos. 5231
and 5232; Queue No. AC1–048/AC2–
053 to be effective 10/23/2018.
Filed Date: 11/21/18.
Accession Number: 20181121–5061.
Comments Due: 5 p.m. ET 12/12/18.
Take notice that the Commission
received the following qualifying
facility filings:
E:\FR\FM\28NON1.SGM
28NON1
61154
Federal Register / Vol. 83, No. 229 / Wednesday, November 28, 2018 / Notices
Docket Numbers: QF18–452–000.
Applicants: North American Natural
Resources, Inc.
Description: Refund Report of North
American Natural Resources, Inc.
Filed Date: 11/20/18.
Accession Number: 20181120–5217.
Comments Due: 5 p.m. ET 12/11/18.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: November 21, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–25925 Filed 11–27–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP15–138–005]
Notice of Application: Transcontinental
Gas Pipe Line Company, LLC
Take notice that on November 14,
2018, Transcontinental Gas Pipe Line
Company, LLC (Transco), P.O. Box
1396, Houston, TX 77251–1396, filed an
application under section 7(c) of the
Natural Gas Act (NGA) requesting
authorization to amend its certificate of
public convenience and necessity,
granted by the Commission on February
3, 2017 in Docket No. CP15–138, which
authorized the Atlantic Sunrise Project.
Herein, Transco requests authorization
to amend its Atlantic Sunrise Project
certificate to allow any of the existing
compressor units at Compressor Station
605 and Compressor Station 610 to be
operated above their currently
certificated horsepower. Transco states
that the total horsepower utilized at
Compressor Station 605 will not exceed
the station’s total certificated
horsepower of 30,000 horsepower and
VerDate Sep<11>2014
16:19 Nov 27, 2018
Jkt 247001
that the total horsepower utilized at
Compressor Station 610 will not exceed
the station’s total certificated
horsepower of 40,000 horsepower, all as
more fully set forth in the application
which is on file with the Commission
and open to public inspection. The
filing may also be viewed on the web at
https://www.ferc.gov using the eLibrary
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TTY, (202)
502–8659.
Any questions regarding the
application should be directed to Bill
Hammons at Transcontinental Gas Pipe
Line Company, LLC, Post Office Box
1396, Houston, TX 77251 or at (713)
215–2130.
Pursuant to section 157.9 of the
Commission’s rules (18 CFR 157.9),
within 90 days of this Notice, the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
3 copies of filings made in the
proceeding with the Commission and
PO 00000
Frm 00011
Fmt 4703
Sfmt 4703
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list and will be
notified of any meetings associated with
the Commission’s environmental review
process. Environmental commentors
will not be required to serve copies of
filed documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission and will not have the right
to seek court review of the
Commission’s final order.
As of the February 27, 2018 date of
the Commission’s order in Docket No.
CP16–4–001, the Commission will
apply its revised practice concerning
out-of-time motions to intervene in any
new Natural Gas Act section 3 or section
7 proceeding.1 Persons desiring to
become a party to a certificate
proceeding are to intervene in a timely
manner. If seeking to intervene out-oftime, the movant is required to show
good cause why the time limitation
should be waived, and should provide
justification by reference to factors set
forth in Rule 214(d)(1) of the
Commission’s Rules and Regulations.2
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the eFiling link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 3 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
1 Tennessee Gas Pipeline Company, L.L.C., 162
FERC 61,167 at 50 (2018).
2 18 CFR 385.214(d)(1).
E:\FR\FM\28NON1.SGM
28NON1
Agencies
[Federal Register Volume 83, Number 229 (Wednesday, November 28, 2018)]
[Notices]
[Pages 61153-61154]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-25925]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER13-1667-004.
Applicants: Battery Utility of Ohio, LLC.
Description: Notice of Change in Status of Battery Utility of Ohio,
LLC.
Filed Date: 11/20/18.
Accession Number: 20181120-5221.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER17-1609-002.
Applicants: Carroll County Energy LLC.
Description: Notice of Non-Material Change in Status of Carroll
County Energy LLC.
Filed Date: 11/20/18.
Accession Number: 20181120-5254.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER18-2516-000.
Applicants: Willow Springs Solar, LLC.
Description: Amendment to September 28, 2018 Willow Springs Solar,
LLC tariff filing.
Filed Date: 11/20/18.
Accession Number: 20181120-5219.
Comments Due: 5 p.m. ET 11/27/18.
Docket Numbers: ER19-104-001.
Applicants: El Paso Electric Company.
Description: Tariff Amendment: Concurrence of EPE to APS Service
Agreement No. 367 to be effective 9/7/2018.
Filed Date: 11/20/18.
Accession Number: 20181120-5167.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER19-381-000.
Applicants: Power Holding LLC.
Description: Baseline eTariff Filing: Application for Market Based
Rate to be effective 11/21/2018.
Filed Date: 11/20/18.
Accession Number: 20181120-5175.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER19-382-000.
Applicants: Duke Energy Carolinas, LLC.
Description: Sec. 205(d) Rate Filing: DEC-City of Concord NITSA
(SA-150) Amendment to be effective 1/1/2019.
Filed Date: 11/20/18.
Accession Number: 20181120-5176.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER19-383-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Revisions to OATT and OA re
Regulation Market Clearing Price to be effective 1/21/2019.
Filed Date: 11/20/18.
Accession Number: 20181120-5182.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER19-384-000.
Applicants: Pacific Gas and Electric Company.
Description: Request for One-time Limited Tariff Waiver, et al. of
Pacific Gas and Electric Company under ER19-384.
Filed Date: 11/20/18.
Accession Number: 20181120-5218.
Comments Due: 5 p.m. ET 11/30/18.
Docket Numbers: ER19-385-000.
Applicants: NRG Power Marketing LLC.
Description: Application to Recover Fuel Procurement Costs of NRG
Power Marketing, LLC.
Filed Date: 11/20/18.
Accession Number: 20181120-5223.
Comments Due: 5 p.m. ET 12/11/18.
Docket Numbers: ER19-386-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Amendment to ISA, SA No.
2278, Queue# None (Consent) to be effective 4/1/2010.
Filed Date: 11/21/18.
Accession Number: 20181121-5054.
Comments Due: 5 p.m. ET 12/12/18.
Docket Numbers: ER19-387-000.
Applicants: PJM Interconnection, L.L.C.
Description: Sec. 205(d) Rate Filing: Original ISA and CSA, SA
Nos. 5231 and 5232; Queue No. AC1-048/AC2-053 to be effective 10/23/
2018.
Filed Date: 11/21/18.
Accession Number: 20181121-5061.
Comments Due: 5 p.m. ET 12/12/18.
Take notice that the Commission received the following qualifying
facility filings:
[[Page 61154]]
Docket Numbers: QF18-452-000.
Applicants: North American Natural Resources, Inc.
Description: Refund Report of North American Natural Resources,
Inc.
Filed Date: 11/20/18.
Accession Number: 20181120-5217.
Comments Due: 5 p.m. ET 12/11/18.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: November 21, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-25925 Filed 11-27-18; 8:45 am]