Combined Notice of Filings #1, 60838-60839 [2018-25756]
Download as PDF
60838
Federal Register / Vol. 83, No. 228 / Tuesday, November 27, 2018 / Notices
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
Issuance of EA—April 1, 2019.
90-day Federal Authorization
Decision Deadline—June 30, 2019.
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
Eastern Shore proposes to construct
and operate new natural gas pipelines
and meter and delivery stations in Kent
and Sussex Counties, Delaware, and
Wicomico and Somerset Counties,
Maryland.
The Project would consist of
construction and operation of the
following facilities:
Woodside Loop 1 Kent County, Delaware
• 4.9 miles of new 16-inch-diameter
pipeline looping its existing pipeline.
East Sussex Extension Sussex County,
Delaware
• 7.39 miles of new 8-inch-diameter
mainline extension to the existing
Milford Line;
• one aboveground pig launcher and
one pig receiver,2 and aboveground
mainline valve; and
• one new delivery metering and
regulation (M&R) station.
Millsboro Pressure Control Station
Upgrade Millsboro, Sussex County,
Delaware
• 0.35 mile of 10-inch-diameter
pipeline extension between the existing
Millsboro Pressure Control Station and
the existing Milford Line; and
• a dual run pressure control addition
to the existing Millsboro Pressure
Control Station with modifications to
the existing piping, valves, and
associated electronic transmitters.
amozie on DSK3GDR082PROD with NOTICES1
Somerset Extension Wicomico and
Somerset Counties, Maryland
• 6.83 miles of new 10-inch-diameter
pipeline extension to the existing
Parkesburg Line;
• one aboveground pig launcher and
one pig receiver, and aboveground
mainline valve; and
• one new delivery M&R station at
the Somerset Extension terminus.
1 A pipeline loop is a segment of pipe constructed
parallel to an existing pipeline to increase capacity.
2 A ‘‘pig’’ is a tool that the pipeline company
inserts into and pushes through the pipeline for
cleaning the pipeline, conducting internal
inspections, or other purposes.
VerDate Sep<11>2014
17:45 Nov 26, 2018
Jkt 247001
Background
DEPARTMENT OF ENERGY
On November 2, 2018 the
Commission issued a Notice of Intent to
Prepare an Environmental Assessment
for the Proposed Del-Mar Energy
Pathway Project, Request for Comments
on Environmental Issues, Notice of
Public Scoping Session, and Notice of
Onsite Review (NOI). The NOI was sent
to affected landowners; federal, state,
and local government agencies; elected
officials; environmental and public
interest groups; Native American tribes;
other interested parties; and local
libraries and newspapers. Comments on
the NOI should be received by the
Commission in Washington, DC on or
before 5:00 p.m. Eastern Time on
December 3, 2018. All substantive
comments received at the scoping
session or filed in the Commission’s
public record will be addressed in the
EA.
Federal Energy Regulatory
Commission
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP18–548), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: November 20, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–25804 Filed 11–26–18; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC19–27–000.
Applicants: IIF US Holding LP, IIF US
Holding 2 LP.
Description: Application for
Authorization Under Section 203 of the
Federal Power Act, et al. of IIF US
Holding LP, et al.
Filed Date: 11/16/18.
Accession Number: 20181116–5234.
Comments Due: 5 p.m. ET 12/7/18.
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG19–23–000.
Applicants: Antelope DSR 3, LLC.
Description: Notice of SelfCertification of EWG Status of Antelope
DSR 3, LLC.
Filed Date: 11/19/18.
Accession Number: 20181119–5112.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: EG19–24–000.
Applicants: San Pablo Raceway, LLC.
Description: Notice of SelfCertification of EWG Status of San Pablo
Raceway, LLC.
Filed Date: 11/19/18.
Accession Number: 20181119–5113.
Comments Due: 5 p.m. ET 12/10/18.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2630–002;
ER16–1914–002.
Applicants: NGP Blue Mountain I
LLC, Patua Acquisition Company, LLC.
Description: Supplement to
September 27, 2018 Notice of NonMaterial Change in Status of NGP Blue
Mountain I LLC, et al.
Filed Date: 11/16/18.
Accession Number: 20181116–5239.
Comments Due: 5 p.m. ET 12/7/18.
Docket Numbers: ER10–2738–006.
Applicants: The Empire District
Electric Company.
Description: Supplement to June 29,
2018 Updated Market Power Analysis of
The Empire District Electric Company.
Filed Date: 11/16/18.
Accession Number: 20181116–5264.
Comments Due: 5 p.m. ET 12/7/18.
Docket Numbers: ER19–360–000.
Applicants: American Transmission
Company LLC.
Description: Application for
Authorization for Abandoned Plant
Incentive Rate Treatment of American
Transmission Company LLC.
E:\FR\FM\27NON1.SGM
27NON1
amozie on DSK3GDR082PROD with NOTICES1
Federal Register / Vol. 83, No. 228 / Tuesday, November 27, 2018 / Notices
Filed Date: 11/16/18.
Accession Number: 20181116–5232.
Comments Due: 5 p.m. ET 12/7/18.
Docket Numbers: ER19–361–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
International Transmission Company,
Michigan Electric Transmission
Company, LLC, ITC Midwest LLC.
Description: Compliance filing: 2018–
11–19_Attachment O Compliance for
ITC Companies re Transco Adder
(EL18–140) to be effective 4/20/2018.
Filed Date: 11/19/18.
Accession Number: 20181119–5051.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: ER19–362–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
ALLETE, Inc.
Description: § 205(d) Rate Filing:
2018–11–19_SA 3211 MP–GRE IA
(Birch Lake) to be effective 11/20/2018.
Filed Date: 11/19/18.
Accession Number: 20181119–5076.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: ER19–363–000.
Applicants: Midcontinent
Independent System Operator, Inc.,
ALLETE, Inc.
Description: § 205(d) Rate Filing:
2018–11–19_SA 3212 MP–GRE ICA
(Bergen Lake) to be effective
11/20/2018.
Filed Date: 11/19/18.
Accession Number: 20181119–5078.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: ER19–364–000.
Applicants: Alabama Power
Company.
Description: § 205(d) Rate Filing:
Happy Hollow Solar Center LGIA Filing
to be effective 11/5/2018.
Filed Date: 11/19/18.
Accession Number: 20181119–5116.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: ER19–365–000.
Applicants: Public Service Company
of Colorado.
Description: § 205(d) Rate Filing:
PSCo–WAPA–TSGT Inter–Entitle–
O&M–367–Exh O–0.1.0 to be effective
11/20/2018.
Filed Date: 11/19/18.
Accession Number: 20181119–5124.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: ER19–366–000.
Applicants: Public Service Company
of Colorado.
Description: § 205(d) Rate Filing:
2018–11–19 Att N–LGIP—Xcel Queue
Reform to be effective 2/1/2019.
Filed Date: 11/19/18.
Accession Number: 20181119–5152.
Comments Due: 5 p.m. ET 12/10/18.
The filings are accessible in the
Commission’s eLibrary system by
VerDate Sep<11>2014
17:45 Nov 26, 2018
Jkt 247001
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: November 19, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–25756 Filed 11–26–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Number: PR19–14–000.
Applicants: Louisville Gas and
Electric Company.
Description: Tariff filing per
284.123(b),(e)/: Revised Statement of
Operating Conditions DDC and LAUFG
to be effective 11/1/2018.
Filed Date: 11/13/18.
Accession Number: 201811135011.
Comments/Protests Due: 5 p.m. ET
12/4/18.
Docket Number: PR19–15–000.
Applicants: Alpine High Pipeline LP.
Description: Tariff filing per
284.123(b),(e)+(g): Revised Statement of
Operating Conditions to be effective 11/
1/2018.
Filed Date: 11/13/18.
Accession Number: 201811135267.
Comments Due: 5 p.m. ET 12/4/18.
284.123(g) Protests Due: 5 p.m. ET 1/
14/19.
Docket Number: PR19–16–000.
Applicants: Lee 8 Storage Partnership.
Description: Tariff filing per
284.123(b)(2)+(g): Petition for Rate
Approval to be effective 11/14/2018.
Filed Date: 11/14/18.
Accession Number: 201811145042.
Comments Due: 5 p.m. ET 12/5/18.
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
60839
284.123(g) Protests Due: 5 p.m. ET 1/
14/19.
Docket Number: PR19–17–000.
Applicants: Black Hills Energy
Arkansas, Inc.
Description: Tariff filing per
284.123(b),(e)/: BHEA SOC Filing to be
effective 11/15/2018.
Filed Date: 11/15/18.
Accession Number: 201811155052.
Comments/Protests Due: 5 p.m. ET
12/6/18.
Docket Number: PR19–18–000.
Applicants: Rocky Mountain Natural
Gas LLC.
Description: Tariff filing per
284.123(b),(e)/: RMNG Revised SOC
Filing to be effective 11/1/2018.
Filed Date: 11/15/18.
Accession Number: 201811155053.
Comments/Protests Due: 5 p.m. ET
12/6/18.
Docket Numbers: RP19–297–000.
Applicants: Texas Eastern
Transmission, LP.
Description: eTariff filing per 1430:
TETLP Extension to file Form 501–G.
Filed Date: 11/16/18.
Accession Number: 20181116–5177.
Comments Due: 5 p.m. ET 11/21/18.
Docket Numbers: RP19–298–000.
Applicants: Columbia Gas
Transmission, LLC.
Description: § 4(d) Rate Filing: WBX
East Amendments Filing to be effective
11/16/2018.
Filed Date: 11/16/18.
Accession Number: 20181116–5179.
Comments Due: 5 p.m. ET 11/28/18.
Docket Numbers: RP19–299–000.
Applicants: Transcontinental Gas
Pipe Line Company, LLC.
Description: § 4(d) Rate Filing: Gulf
Connector Initial Rate Filing—REV to be
effective 12/1/2018.
Filed Date: 11/19/18.
Accession Number: 20181119–5000.
Comments Due: 5 p.m. ET 12/3/18.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified date(s). Protests
may be considered, but intervention is
necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
E:\FR\FM\27NON1.SGM
27NON1
Agencies
[Federal Register Volume 83, Number 228 (Tuesday, November 27, 2018)]
[Notices]
[Pages 60838-60839]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-25756]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings #1
Take notice that the Commission received the following electric
corporate filings:
Docket Numbers: EC19-27-000.
Applicants: IIF US Holding LP, IIF US Holding 2 LP.
Description: Application for Authorization Under Section 203 of the
Federal Power Act, et al. of IIF US Holding LP, et al.
Filed Date: 11/16/18.
Accession Number: 20181116-5234.
Comments Due: 5 p.m. ET 12/7/18.
Take notice that the Commission received the following exempt
wholesale generator filings:
Docket Numbers: EG19-23-000.
Applicants: Antelope DSR 3, LLC.
Description: Notice of Self-Certification of EWG Status of Antelope
DSR 3, LLC.
Filed Date: 11/19/18.
Accession Number: 20181119-5112.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: EG19-24-000.
Applicants: San Pablo Raceway, LLC.
Description: Notice of Self-Certification of EWG Status of San
Pablo Raceway, LLC.
Filed Date: 11/19/18.
Accession Number: 20181119-5113.
Comments Due: 5 p.m. ET 12/10/18.
Take notice that the Commission received the following electric
rate filings:
Docket Numbers: ER10-2630-002; ER16-1914-002.
Applicants: NGP Blue Mountain I LLC, Patua Acquisition Company,
LLC.
Description: Supplement to September 27, 2018 Notice of Non-
Material Change in Status of NGP Blue Mountain I LLC, et al.
Filed Date: 11/16/18.
Accession Number: 20181116-5239.
Comments Due: 5 p.m. ET 12/7/18.
Docket Numbers: ER10-2738-006.
Applicants: The Empire District Electric Company.
Description: Supplement to June 29, 2018 Updated Market Power
Analysis of The Empire District Electric Company.
Filed Date: 11/16/18.
Accession Number: 20181116-5264.
Comments Due: 5 p.m. ET 12/7/18.
Docket Numbers: ER19-360-000.
Applicants: American Transmission Company LLC.
Description: Application for Authorization for Abandoned Plant
Incentive Rate Treatment of American Transmission Company LLC.
[[Page 60839]]
Filed Date: 11/16/18.
Accession Number: 20181116-5232.
Comments Due: 5 p.m. ET 12/7/18.
Docket Numbers: ER19-361-000.
Applicants: Midcontinent Independent System Operator, Inc.,
International Transmission Company, Michigan Electric Transmission
Company, LLC, ITC Midwest LLC.
Description: Compliance filing: 2018-11-19_Attachment O Compliance
for ITC Companies re Transco Adder (EL18-140) to be effective 4/20/
2018.
Filed Date: 11/19/18.
Accession Number: 20181119-5051.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: ER19-362-000.
Applicants: Midcontinent Independent System Operator, Inc., ALLETE,
Inc.
Description: Sec. 205(d) Rate Filing: 2018-11-19_SA 3211 MP-GRE IA
(Birch Lake) to be effective 11/20/2018.
Filed Date: 11/19/18.
Accession Number: 20181119-5076.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: ER19-363-000.
Applicants: Midcontinent Independent System Operator, Inc., ALLETE,
Inc.
Description: Sec. 205(d) Rate Filing: 2018-11-19_SA 3212 MP-GRE
ICA (Bergen Lake) to be effective 11/20/2018.
Filed Date: 11/19/18.
Accession Number: 20181119-5078.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: ER19-364-000.
Applicants: Alabama Power Company.
Description: Sec. 205(d) Rate Filing: Happy Hollow Solar Center
LGIA Filing to be effective 11/5/2018.
Filed Date: 11/19/18.
Accession Number: 20181119-5116.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: ER19-365-000.
Applicants: Public Service Company of Colorado.
Description: Sec. 205(d) Rate Filing: PSCo-WAPA-TSGT Inter-
Entitle-O&M-367-Exh O-0.1.0 to be effective 11/20/2018.
Filed Date: 11/19/18.
Accession Number: 20181119-5124.
Comments Due: 5 p.m. ET 12/10/18.
Docket Numbers: ER19-366-000.
Applicants: Public Service Company of Colorado.
Description: Sec. 205(d) Rate Filing: 2018-11-19 Att N-LGIP--Xcel
Queue Reform to be effective 2/1/2019.
Filed Date: 11/19/18.
Accession Number: 20181119-5152.
Comments Due: 5 p.m. ET 12/10/18.
The filings are accessible in the Commission's eLibrary system by
clicking on the links or querying the docket number.
Any person desiring to intervene or protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00
p.m. Eastern time on the specified comment date. Protests may be
considered, but intervention is necessary to become a party to the
proceeding.
eFiling is encouraged. More detailed information relating to filing
requirements, interventions, protests, service, and qualifying
facilities filings can be found at: https://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676
(toll free). For TTY, call (202) 502-8659.
Dated: November 19, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-25756 Filed 11-26-18; 8:45 am]