T.A. Keck, III and H.S. Keck; Notice of Existing Licensee's Failure To File a Notice of Intent To File a Subsequent License Application, and Soliciting Notices of Intent To File a License Application and Pre-Application Documents, 56315-56316 [2018-24701]
Download as PDF
amozie on DSK3GDR082PROD with NOTICES1
Federal Register / Vol. 83, No. 219 / Tuesday, November 13, 2018 / Notices
Filed Date: 11/5/18.
Accession Number: 20181105–5197.
Comments Due: 5 p.m. ET 11/26/18.
Docket Numbers: ER18–2324–000.
Applicants: NorthWestern
Corporation.
Description: Supplement (Diagram) to
August 27, 2018 Request for Limited
Waiver of Filed Tariff of NorthWestern
Corporation.
Filed Date: 11/2/18.
Accession Number: 20181102–5259.
Comments Due: 5 p.m. ET 11/9/18.
Docket Numbers: ER19–286–000.
Applicants: Southwest Power Pool,
Inc.
Description: § 205(d) Rate Filing:
3101R2 Heartland Consumers Power
District NITSA and NOA to be effective
4/22/2018.
Filed Date: 11/5/18.
Accession Number: 20181105–5063.
Comments Due: 5 p.m. ET 11/26/18.
Docket Numbers: ER19–287–000.
Applicants: PJM Interconnection,
L.L.C.
Description: § 205(d) Rate Filing:
Original ISA SA No. 5227; Queue No.
AB2–158 to be effective 10/8/2018.
Filed Date: 11/5/18.
Accession Number: 20181105–5064.
Comments Due: 5 p.m. ET 11/26/18.
Docket Numbers: ER19–288–000.
Applicants: Carson Hybrid Energy
Storage LLC.
Description: Baseline eTariff Filing:
Application for Market Based Rate to be
effective 12/1/2018.
Filed Date: 11/5/18.
Accession Number: 20181105–5076.
Comments Due: 5 p.m. ET 11/26/18.
Docket Numbers: ER19–289–000.
Applicants: Cleco Cajun LLC.
Description: Baseline eTariff Filing:
Baseline new to be effective 1/5/2019.
Filed Date: 11/5/18.
Accession Number: 20181105–5181.
Comments Due: 5 p.m. ET 11/26/18.
Docket Numbers: ER19–290–000.
Applicants: Pacific Gas and Electric
Company.
Description: § 205(d) Rate Filing:
Revisions to Appendix A to the US DOE
Berkeley Site Office IA (SA 63) to be
effective 11/6/2018.
Filed Date: 11/5/18.
Accession Number: 20181105–5198.
Comments Due: 5 p.m. ET 11/26/18.
Docket Numbers: ER19–291–000.
Applicants: ISO New England Inc.,
New England Power Pool.
Description: ISO New England Inc., et
al. submits Installed Capacity
Requirement, Hydro Quebec
Interconnection Capability Credits and
Related Values for the 2022/2023
Capacity Commitment Period.
VerDate Sep<11>2014
17:34 Nov 09, 2018
Jkt 247001
Filed Date: 11/6/18.
Accession Number: 20181106–5025.
Comments Due: 5 p.m. ET 11/27/18.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
56315
[Project No. 2788–017]
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY).
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Any comments should be filed within
30 days from the date of this notice.
The Commission strongly encourages
electronic filing. Please file comments
using the Commission’s eFiling system
at https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support. In
lieu of electronic filing, please send a
paper copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE, Washington, DC 20426. The first
page of any filing should include docket
number P–2788–017.
For further information, contact Emily
Carter at (202) 502–6512 or by email at
emily.carter@ferc.gov.
Goodyear Lake Hydro, LLC; Notice of
Availability of Environmental
Assessment
Dated: November 6, 2018.
Kimberly D. Bose,
Secretary.
Dated: November 6, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–24671 Filed 11–9–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380, the Office
of Energy Projects has reviewed the
application for a subsequent license for
the Colliersville Hydroelectric Project,
located on the Susquehanna River, in
the Town of Milford, Otsego County,
New York, and has prepared an
Environmental Assessment (EA) for the
project.
The EA contains staff’s analysis of the
potential environmental impacts of the
project and concludes that licensing the
project, with appropriate environmental
protective measures, would not
constitute a major federal action that
would significantly affect the quality of
the human environment.
A copy of the EA is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s website at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
PO 00000
Frm 00042
Fmt 4703
Sfmt 4703
[FR Doc. 2018–24703 Filed 11–9–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 11426–000]
T.A. Keck, III and H.S. Keck; Notice of
Existing Licensee’s Failure To File a
Notice of Intent To File a Subsequent
License Application, and Soliciting
Notices of Intent To File a License
Application and Pre-Application
Documents
The current license for T.A. Keck, III
and H.S. Keck’s (the Kecks’) Blackstone
Mill Hydroelectric Project No. 11426
(Blackstone Mill Project) was issued on
November 18, 1993, for a term of 30
years, ending October 31, 2023.1 The 651 See T.A. Keck, III and H.S. Keck, 65 FERC
¶ 62,149 (1993).
E:\FR\FM\13NON1.SGM
13NON1
amozie on DSK3GDR082PROD with NOTICES1
56316
Federal Register / Vol. 83, No. 219 / Tuesday, November 13, 2018 / Notices
kilowatt (kW) project is located on East
Mahantango Creek, a tributary of the
Susquehanna River near the Town of
Pillow, in Dauphin County,
Pennsylvania.
The principal project works consist
of: (1) A 102-foot-long, approximately
2.5-foot-high dam; (2) a reservoir with a
surface area of about 3 acres and a total
volume of about 7 acre-feet at the
normal water surface elevation of
approximately 470 feet mean sea level;
(3) a headrace or power canal about
3,200 feet long by 20 feet wide by 5 feet
deep; (4) a stone-masonry powerhouse
containing two generating units rated at
50 kW and 15 kW for a total installed
capacity of 65 kW; (5) an overhead 240volt transmission line about 60 feet
long; and (6) appurtenant equipment
and facilities.
At least five years before the
expiration of a license for a minor water
power project in which sections 14 and
15 of the Federal Power Act were
waived, the Commission’s regulations
require the licensee to file with the
Commission a notice of intent (NOI) that
contains an unequivocal statement of
the licensee’s intention to file or not to
file an application for a subsequent
license, details on the principal project
works and installed plant capacity, and
other information.2
If such a licensee does not inform the
Commission that it intends to file an
application for, in this case, a
subsequent license for the project, the
licensee may not file an application for
a subsequent license, either individually
or in conjunction with an entity or
entities that are not currently licensees
of the project.3
Because the existing license expires
on October 31, 2023, the NOI was due
to be filed no later than the close of
business on October 31, 2018. The
Kecks, the existing licensee for the
Blackstone Mill Project, failed to file an
NOI by this date.
Any party interested in filing a license
application for the Blackstone Mill
Project No. 11426 must first file a Notice
of Intent (NOI) 4 and pre-application
document (PAD) 5 pursuant to Part 5 of
the Commission’s regulations. Although
the integrated licensing process (ILP) is
the default pre-filing process, section
5.3(b) of the Commission’s regulations
allows a potential license applicant to
request to use alternative licensing
procedures when it files its NOI.6
2 18 CFR 16.19(b) (2018) (citing 18 CFR 16.6(b)).
Section 16.19(b) applies to licenses not subject to
Parts 14 and 15 of the Federal Power Act.
3 18 CFR 16.24(b) (2018).
4 18 CFR 5.5 (2018).
5 18 CFR 5.6 (2018).
6 18 CFR 5.3(b) (2018).
VerDate Sep<11>2014
17:34 Nov 09, 2018
Jkt 247001
This notice sets a deadline of 120
days from the date of this notice for
interested applicants, other than the
existing licensee, to file NOIs, PADs,
and requests to use an alternative
licensing process.
Applications for a subsequent license
from potential (non-licensee) applicants
must be filed with the Commission at
least 24 months prior to the expiration
of the existing license.7 Because the
existing license expires on October 31,
2023, applications for license for this
project must be filed by October 31,
2021.8
Questions concerning this notice
should be directed to Andy Bernick at
(202) 502–8660 or andrew.bernick@
ferc.gov.
Dated: November 6, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–24701 Filed 11–9–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER19–288–000]
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization: Carson Hybrid Energy
Storage LLC
This is a supplemental notice in the
above-referenced proceeding of Carson
Hybrid Energy Storage LLC’s
application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
7 18
CFR 16.20 (2018).
the extent an interested applicant files an
NOI and PAD and elects or is required to use the
Commission’s ILP, a process plan will be issued
within 180 days of this notice, which accelerates
the steps of the ILP to allow for filing a subsequent
license application by the October 31, 2021
deadline.
8 To
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is November
26, 2018.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an eSubscription link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: November 6, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018–24670 Filed 11–9–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL19–11–000]
American Wind Energy Association,
The Wind Coalition v. Southwest
Power Pool, Inc.; Notice of Complaint
Take notice that on November 2,
2018, pursuant to sections 206, 306, and
309 of the Federal Power Act, 16 U.S.C.
824e, 825e, and 825h, and section 206
of the Federal Energy Regulatory
Commission’s (Commission) Rules of
Practice and Procedure, 18 CFR 385.206
(2018), the American Wind Energy
Association and The Wind Coalition
(collectively, Complainants) filed a
formal complaint (complaint) against
Southwest Power Pool, Inc.
E:\FR\FM\13NON1.SGM
13NON1
Agencies
[Federal Register Volume 83, Number 219 (Tuesday, November 13, 2018)]
[Notices]
[Pages 56315-56316]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-24701]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 11426-000]
T.A. Keck, III and H.S. Keck; Notice of Existing Licensee's
Failure To File a Notice of Intent To File a Subsequent License
Application, and Soliciting Notices of Intent To File a License
Application and Pre-Application Documents
The current license for T.A. Keck, III and H.S. Keck's (the Kecks')
Blackstone Mill Hydroelectric Project No. 11426 (Blackstone Mill
Project) was issued on November 18, 1993, for a term of 30 years,
ending October 31, 2023.\1\ The 65-
[[Page 56316]]
kilowatt (kW) project is located on East Mahantango Creek, a tributary
of the Susquehanna River near the Town of Pillow, in Dauphin County,
Pennsylvania.
---------------------------------------------------------------------------
\1\ See T.A. Keck, III and H.S. Keck, 65 FERC ] 62,149 (1993).
---------------------------------------------------------------------------
The principal project works consist of: (1) A 102-foot-long,
approximately 2.5-foot-high dam; (2) a reservoir with a surface area of
about 3 acres and a total volume of about 7 acre-feet at the normal
water surface elevation of approximately 470 feet mean sea level; (3) a
headrace or power canal about 3,200 feet long by 20 feet wide by 5 feet
deep; (4) a stone-masonry powerhouse containing two generating units
rated at 50 kW and 15 kW for a total installed capacity of 65 kW; (5)
an overhead 240-volt transmission line about 60 feet long; and (6)
appurtenant equipment and facilities.
At least five years before the expiration of a license for a minor
water power project in which sections 14 and 15 of the Federal Power
Act were waived, the Commission's regulations require the licensee to
file with the Commission a notice of intent (NOI) that contains an
unequivocal statement of the licensee's intention to file or not to
file an application for a subsequent license, details on the principal
project works and installed plant capacity, and other information.\2\
---------------------------------------------------------------------------
\2\ 18 CFR 16.19(b) (2018) (citing 18 CFR 16.6(b)). Section
16.19(b) applies to licenses not subject to Parts 14 and 15 of the
Federal Power Act.
---------------------------------------------------------------------------
If such a licensee does not inform the Commission that it intends
to file an application for, in this case, a subsequent license for the
project, the licensee may not file an application for a subsequent
license, either individually or in conjunction with an entity or
entities that are not currently licensees of the project.\3\
---------------------------------------------------------------------------
\3\ 18 CFR 16.24(b) (2018).
---------------------------------------------------------------------------
Because the existing license expires on October 31, 2023, the NOI
was due to be filed no later than the close of business on October 31,
2018. The Kecks, the existing licensee for the Blackstone Mill Project,
failed to file an NOI by this date.
Any party interested in filing a license application for the
Blackstone Mill Project No. 11426 must first file a Notice of Intent
(NOI) \4\ and pre-application document (PAD) \5\ pursuant to Part 5 of
the Commission's regulations. Although the integrated licensing process
(ILP) is the default pre-filing process, section 5.3(b) of the
Commission's regulations allows a potential license applicant to
request to use alternative licensing procedures when it files its
NOI.\6\
---------------------------------------------------------------------------
\4\ 18 CFR 5.5 (2018).
\5\ 18 CFR 5.6 (2018).
\6\ 18 CFR 5.3(b) (2018).
---------------------------------------------------------------------------
This notice sets a deadline of 120 days from the date of this
notice for interested applicants, other than the existing licensee, to
file NOIs, PADs, and requests to use an alternative licensing process.
Applications for a subsequent license from potential (non-licensee)
applicants must be filed with the Commission at least 24 months prior
to the expiration of the existing license.\7\ Because the existing
license expires on October 31, 2023, applications for license for this
project must be filed by October 31, 2021.\8\
---------------------------------------------------------------------------
\7\ 18 CFR 16.20 (2018).
\8\ To the extent an interested applicant files an NOI and PAD
and elects or is required to use the Commission's ILP, a process
plan will be issued within 180 days of this notice, which
accelerates the steps of the ILP to allow for filing a subsequent
license application by the October 31, 2021 deadline.
---------------------------------------------------------------------------
Questions concerning this notice should be directed to Andy Bernick
at (202) 502-8660 or [email protected].
Dated: November 6, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-24701 Filed 11-9-18; 8:45 am]
BILLING CODE 6717-01-P