Download as PDF amozie on DSK3GDR082PROD with NOTICES1 Federal Register / Vol. 83, No. 219 / Tuesday, November 13, 2018 / Notices Filed Date: 11/5/18. Accession Number: 20181105–5197. Comments Due: 5 p.m. ET 11/26/18. Docket Numbers: ER18–2324–000. Applicants: NorthWestern Corporation. Description: Supplement (Diagram) to August 27, 2018 Request for Limited Waiver of Filed Tariff of NorthWestern Corporation. Filed Date: 11/2/18. Accession Number: 20181102–5259. Comments Due: 5 p.m. ET 11/9/18. Docket Numbers: ER19–286–000. Applicants: Southwest Power Pool, Inc. Description: § 205(d) Rate Filing: 3101R2 Heartland Consumers Power District NITSA and NOA to be effective 4/22/2018. Filed Date: 11/5/18. Accession Number: 20181105–5063. Comments Due: 5 p.m. ET 11/26/18. Docket Numbers: ER19–287–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Original ISA SA No. 5227; Queue No. AB2–158 to be effective 10/8/2018. Filed Date: 11/5/18. Accession Number: 20181105–5064. Comments Due: 5 p.m. ET 11/26/18. Docket Numbers: ER19–288–000. Applicants: Carson Hybrid Energy Storage LLC. Description: Baseline eTariff Filing: Application for Market Based Rate to be effective 12/1/2018. Filed Date: 11/5/18. Accession Number: 20181105–5076. Comments Due: 5 p.m. ET 11/26/18. Docket Numbers: ER19–289–000. Applicants: Cleco Cajun LLC. Description: Baseline eTariff Filing: Baseline new to be effective 1/5/2019. Filed Date: 11/5/18. Accession Number: 20181105–5181. Comments Due: 5 p.m. ET 11/26/18. Docket Numbers: ER19–290–000. Applicants: Pacific Gas and Electric Company. Description: § 205(d) Rate Filing: Revisions to Appendix A to the US DOE Berkeley Site Office IA (SA 63) to be effective 11/6/2018. Filed Date: 11/5/18. Accession Number: 20181105–5198. Comments Due: 5 p.m. ET 11/26/18. Docket Numbers: ER19–291–000. Applicants: ISO New England Inc., New England Power Pool. Description: ISO New England Inc., et al. submits Installed Capacity Requirement, Hydro Quebec Interconnection Capability Credits and Related Values for the 2022/2023 Capacity Commitment Period. VerDate Sep<11>2014 17:34 Nov 09, 2018 Jkt 247001 Filed Date: 11/6/18. Accession Number: 20181106–5025. Comments Due: 5 p.m. ET 11/27/18. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. 56315 [Project No. 2788–017] Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Any comments should be filed within 30 days from the date of this notice. The Commission strongly encourages electronic filing. Please file comments using the Commission’s eFiling system at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support. In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The first page of any filing should include docket number P–2788–017. For further information, contact Emily Carter at (202) 502–6512 or by email at emily.carter@ferc.gov. Goodyear Lake Hydro, LLC; Notice of Availability of Environmental Assessment Dated: November 6, 2018. Kimberly D. Bose, Secretary. Dated: November 6, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–24671 Filed 11–9–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission In accordance with the National Environmental Policy Act of 1969 and the Federal Energy Regulatory Commission’s (Commission) regulations, 18 CFR part 380, the Office of Energy Projects has reviewed the application for a subsequent license for the Colliersville Hydroelectric Project, located on the Susquehanna River, in the Town of Milford, Otsego County, New York, and has prepared an Environmental Assessment (EA) for the project. The EA contains staff’s analysis of the potential environmental impacts of the project and concludes that licensing the project, with appropriate environmental protective measures, would not constitute a major federal action that would significantly affect the quality of the human environment. A copy of the EA is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s website at https:// www.ferc.gov using the ‘‘eLibrary’’ link. PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 [FR Doc. 2018–24703 Filed 11–9–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 11426–000] T.A. Keck, III and H.S. Keck; Notice of Existing Licensee’s Failure To File a Notice of Intent To File a Subsequent License Application, and Soliciting Notices of Intent To File a License Application and Pre-Application Documents The current license for T.A. Keck, III and H.S. Keck’s (the Kecks’) Blackstone Mill Hydroelectric Project No. 11426 (Blackstone Mill Project) was issued on November 18, 1993, for a term of 30 years, ending October 31, 2023.1 The 651 See T.A. Keck, III and H.S. Keck, 65 FERC ¶ 62,149 (1993). E:\FR\FM\13NON1.SGM 13NON1 amozie on DSK3GDR082PROD with NOTICES1 56316 Federal Register / Vol. 83, No. 219 / Tuesday, November 13, 2018 / Notices kilowatt (kW) project is located on East Mahantango Creek, a tributary of the Susquehanna River near the Town of Pillow, in Dauphin County, Pennsylvania. The principal project works consist of: (1) A 102-foot-long, approximately 2.5-foot-high dam; (2) a reservoir with a surface area of about 3 acres and a total volume of about 7 acre-feet at the normal water surface elevation of approximately 470 feet mean sea level; (3) a headrace or power canal about 3,200 feet long by 20 feet wide by 5 feet deep; (4) a stone-masonry powerhouse containing two generating units rated at 50 kW and 15 kW for a total installed capacity of 65 kW; (5) an overhead 240volt transmission line about 60 feet long; and (6) appurtenant equipment and facilities. At least five years before the expiration of a license for a minor water power project in which sections 14 and 15 of the Federal Power Act were waived, the Commission’s regulations require the licensee to file with the Commission a notice of intent (NOI) that contains an unequivocal statement of the licensee’s intention to file or not to file an application for a subsequent license, details on the principal project works and installed plant capacity, and other information.2 If such a licensee does not inform the Commission that it intends to file an application for, in this case, a subsequent license for the project, the licensee may not file an application for a subsequent license, either individually or in conjunction with an entity or entities that are not currently licensees of the project.3 Because the existing license expires on October 31, 2023, the NOI was due to be filed no later than the close of business on October 31, 2018. The Kecks, the existing licensee for the Blackstone Mill Project, failed to file an NOI by this date. Any party interested in filing a license application for the Blackstone Mill Project No. 11426 must first file a Notice of Intent (NOI) 4 and pre-application document (PAD) 5 pursuant to Part 5 of the Commission’s regulations. Although the integrated licensing process (ILP) is the default pre-filing process, section 5.3(b) of the Commission’s regulations allows a potential license applicant to request to use alternative licensing procedures when it files its NOI.6 2 18 CFR 16.19(b) (2018) (citing 18 CFR 16.6(b)). Section 16.19(b) applies to licenses not subject to Parts 14 and 15 of the Federal Power Act. 3 18 CFR 16.24(b) (2018). 4 18 CFR 5.5 (2018). 5 18 CFR 5.6 (2018). 6 18 CFR 5.3(b) (2018). VerDate Sep<11>2014 17:34 Nov 09, 2018 Jkt 247001 This notice sets a deadline of 120 days from the date of this notice for interested applicants, other than the existing licensee, to file NOIs, PADs, and requests to use an alternative licensing process. Applications for a subsequent license from potential (non-licensee) applicants must be filed with the Commission at least 24 months prior to the expiration of the existing license.7 Because the existing license expires on October 31, 2023, applications for license for this project must be filed by October 31, 2021.8 Questions concerning this notice should be directed to Andy Bernick at (202) 502–8660 or andrew.bernick@ ferc.gov. Dated: November 6, 2018. Kimberly D. Bose, Secretary. [FR Doc. 2018–24701 Filed 11–9–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER19–288–000] Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization: Carson Hybrid Energy Storage LLC This is a supplemental notice in the above-referenced proceeding of Carson Hybrid Energy Storage LLC’s application for market-based rate authority, with an accompanying rate tariff, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket 7 18 CFR 16.20 (2018). the extent an interested applicant files an NOI and PAD and elects or is required to use the Commission’s ILP, a process plan will be issued within 180 days of this notice, which accelerates the steps of the ILP to allow for filing a subsequent license application by the October 31, 2021 deadline. 8 To PO 00000 Frm 00043 Fmt 4703 Sfmt 4703 authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability, is November 26, 2018. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 5 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426. The filings in the above-referenced proceeding are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for electronic review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the website that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: November 6, 2018. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2018–24670 Filed 11–9–18; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL19–11–000] American Wind Energy Association, The Wind Coalition v. Southwest Power Pool, Inc.; Notice of Complaint Take notice that on November 2, 2018, pursuant to sections 206, 306, and 309 of the Federal Power Act, 16 U.S.C. 824e, 825e, and 825h, and section 206 of the Federal Energy Regulatory Commission’s (Commission) Rules of Practice and Procedure, 18 CFR 385.206 (2018), the American Wind Energy Association and The Wind Coalition (collectively, Complainants) filed a formal complaint (complaint) against Southwest Power Pool, Inc. E:\FR\FM\13NON1.SGM 13NON1

Agencies

[Federal Register Volume 83, Number 219 (Tuesday, November 13, 2018)]
[Notices]
[Pages 56315-56316]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-24701]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 11426-000]


T.A. Keck, III and H.S. Keck; Notice of Existing Licensee's 
Failure To File a Notice of Intent To File a Subsequent License 
Application, and Soliciting Notices of Intent To File a License 
Application and Pre-Application Documents

    The current license for T.A. Keck, III and H.S. Keck's (the Kecks') 
Blackstone Mill Hydroelectric Project No. 11426 (Blackstone Mill 
Project) was issued on November 18, 1993, for a term of 30 years, 
ending October 31, 2023.\1\ The 65-

[[Page 56316]]

kilowatt (kW) project is located on East Mahantango Creek, a tributary 
of the Susquehanna River near the Town of Pillow, in Dauphin County, 
Pennsylvania.
---------------------------------------------------------------------------

    \1\ See T.A. Keck, III and H.S. Keck, 65 FERC ] 62,149 (1993).
---------------------------------------------------------------------------

    The principal project works consist of: (1) A 102-foot-long, 
approximately 2.5-foot-high dam; (2) a reservoir with a surface area of 
about 3 acres and a total volume of about 7 acre-feet at the normal 
water surface elevation of approximately 470 feet mean sea level; (3) a 
headrace or power canal about 3,200 feet long by 20 feet wide by 5 feet 
deep; (4) a stone-masonry powerhouse containing two generating units 
rated at 50 kW and 15 kW for a total installed capacity of 65 kW; (5) 
an overhead 240-volt transmission line about 60 feet long; and (6) 
appurtenant equipment and facilities.
    At least five years before the expiration of a license for a minor 
water power project in which sections 14 and 15 of the Federal Power 
Act were waived, the Commission's regulations require the licensee to 
file with the Commission a notice of intent (NOI) that contains an 
unequivocal statement of the licensee's intention to file or not to 
file an application for a subsequent license, details on the principal 
project works and installed plant capacity, and other information.\2\
---------------------------------------------------------------------------

    \2\ 18 CFR 16.19(b) (2018) (citing 18 CFR 16.6(b)). Section 
16.19(b) applies to licenses not subject to Parts 14 and 15 of the 
Federal Power Act.
---------------------------------------------------------------------------

    If such a licensee does not inform the Commission that it intends 
to file an application for, in this case, a subsequent license for the 
project, the licensee may not file an application for a subsequent 
license, either individually or in conjunction with an entity or 
entities that are not currently licensees of the project.\3\
---------------------------------------------------------------------------

    \3\ 18 CFR 16.24(b) (2018).
---------------------------------------------------------------------------

    Because the existing license expires on October 31, 2023, the NOI 
was due to be filed no later than the close of business on October 31, 
2018. The Kecks, the existing licensee for the Blackstone Mill Project, 
failed to file an NOI by this date.
    Any party interested in filing a license application for the 
Blackstone Mill Project No. 11426 must first file a Notice of Intent 
(NOI) \4\ and pre-application document (PAD) \5\ pursuant to Part 5 of 
the Commission's regulations. Although the integrated licensing process 
(ILP) is the default pre-filing process, section 5.3(b) of the 
Commission's regulations allows a potential license applicant to 
request to use alternative licensing procedures when it files its 
NOI.\6\
---------------------------------------------------------------------------

    \4\ 18 CFR 5.5 (2018).
    \5\ 18 CFR 5.6 (2018).
    \6\ 18 CFR 5.3(b) (2018).
---------------------------------------------------------------------------

    This notice sets a deadline of 120 days from the date of this 
notice for interested applicants, other than the existing licensee, to 
file NOIs, PADs, and requests to use an alternative licensing process.
    Applications for a subsequent license from potential (non-licensee) 
applicants must be filed with the Commission at least 24 months prior 
to the expiration of the existing license.\7\ Because the existing 
license expires on October 31, 2023, applications for license for this 
project must be filed by October 31, 2021.\8\
---------------------------------------------------------------------------

    \7\ 18 CFR 16.20 (2018).
    \8\ To the extent an interested applicant files an NOI and PAD 
and elects or is required to use the Commission's ILP, a process 
plan will be issued within 180 days of this notice, which 
accelerates the steps of the ILP to allow for filing a subsequent 
license application by the October 31, 2021 deadline.
---------------------------------------------------------------------------

    Questions concerning this notice should be directed to Andy Bernick 
at (202) 502-8660 or [email protected].

    Dated: November 6, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-24701 Filed 11-9-18; 8:45 am]
 BILLING CODE 6717-01-P