Sendero Carlsbad Gateway, LLC; Notice of Schedule for Environmental Review of the Gateway Project, 53467-53468 [2018-23114]
Download as PDF
Federal Register / Vol. 83, No. 205 / Tuesday, October 23, 2018 / Notices
There is an ‘‘eSubscription’’ link on the
website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern time
on November 16, 2018.
Dated: October 16, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–23120 Filed 10–22–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. OR19–4–000]
Phillips 66 Company v. Colonial
Pipeline Company; Notice of
Complaint
khammond on DSK30JT082PROD with NOTICES
October 17, 2018.
Take notice that on October 16, 2018,
pursuant to sections 1(5), 6, 8, 9, 13, 15
and 16 of the Interstate Commerce Act,
49 U.S.C. App. 1(5), 6, 8, 9, 13, 15 and
16; section 1803 of the Energy Policy
Act of 1992 (Pub. L. 102–486, 106 Stat.
2772 (1992); Rule 206 of the Rules of
Practice and Procedure of the Federal
Energy Regulatory Commission’s
(Commission), 18 CFR 385.206 (2018);
and Rules 343.1(a) and 343.2(c) of the
Commission’s Procedural Rules
Applicable to Oil Pipeline Proceedings,
18 CFR 343.1(a) and 343.2(c) (2018),
Phillips 66 Company (Complainant)
filed a formal complaint against
Colonial Pipeline Company
(Respondent), challenging the just and
reasonableness of (1) Respondent’s costbased transportation rates in Tariff
FERC No. 99.41.0 and predecessor
tariffs; (2) Respondent’s market-based
rate authority and rates charged
pursuant to that authority; and (3)
Respondent’s charges relating to
product loss allocation and transmix, as
more fully explained in the complaint.
The Complainants certify that copies
of the complaint were served on the
contacts for Respondent as listed on the
Commission’s list of Corporate Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
VerDate Sep<11>2014
20:20 Oct 22, 2018
Jkt 247001
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE, Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
electronic review in the Commission’s
Public Reference Room in Washington,
DC. There is an ‘‘eSubscription’’ link on
the website that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on November 15, 2018.
Dated: October 17, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–23116 Filed 10–22–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP18–538–000]
Sendero Carlsbad Gateway, LLC;
Notice of Schedule for Environmental
Review of the Gateway Project
On August 9, 2018, Sendero Carlsbad
Gateway, LLC (Gateway) filed an
application in Docket No. CP18–538–
000 requesting a Certificate of Public
Convenience and Necessity pursuant to
section 7(c) of the Natural Gas Act to
construct and operate certain natural gas
pipeline facilities. The proposed project
is known as the Gateway Project
(Project), and would provide about 400
million standard cubic feet of natural
gas per day from Gateway’s newly
expanded Carlsbad Plant (a cryogenic
gas processing plant) to the Agua Blanca
intrastate pipeline owned by White
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
53467
Water Midstream, LLC. According to
Gateway, the Project would help
alleviate natural gas supply delivery
constraints in southeast New Mexico
and satisfy overall demand in the
western region of the United States.
On August 22, 2018, the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
Issuance of EA—January 11, 2019
90-day Federal Authorization Decision
Deadline—April 11, 2019
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
The Gateway Project would consist of
the following facilities:
• Approximately 23 miles of 24-inchdiameter natural gas transmission
pipeline in Eddy County, New Mexico
and Culberson County, Texas;
• a new meter station (including a
mainline block valve and pig 1 launcher)
within the existing Carlsbad Plant in
Eddy County;
• a mainline block valve at milepost
15.0 in Eddy County; and
• a pig receiver and mainline block
valve at milepost 23.3 near a White
Water Midstream, LLC meter station in
Culberson County.
Background
On August 29, 2018, the Commission
issued a Notice of Intent to Prepare An
Environmental Assessment for the
Proposed Gateway Project, And Request
for Comments on Environmental Issues
(NOI). The NOI was sent to affected
landowners; federal, state, and local
government agencies; elected officials;
environmental and public interest
groups; Native American tribes; other
interested parties; and local libraries
and newspapers.
In response to the NOI, the
Commission received comments from
1 A ‘‘pig’’ is a tool that the pipeline company
inserts into and pushes through the pipeline for
cleaning the pipeline, conducting internal
inspections, or other purposes.
E:\FR\FM\23OCN1.SGM
23OCN1
53468
Federal Register / Vol. 83, No. 205 / Tuesday, October 23, 2018 / Notices
the U.S. Department of Agriculture,
Texas Commission on Environmental
Quality, Texas Parks and Wildlife
Department, New Mexico Department of
Game and Fish, New Mexico State
Historic Preservation Office, and one
Native American tribe. The primary
issues raised by the commentors were
appropriate best management practices
for construction and restoration, special
status species, surface water, and
impacts on vegetation and wildlife. All
substantive comments will be addressed
in the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
projects are available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP18–538), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: October 17, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–23114 Filed 10–22–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
khammond on DSK30JT082PROD with NOTICES
[Docket No. CP18–508–000]
Columbia Gas Transmission, LLC;
Notice of Schedule for Environmental
Review of the Line Ka1 North
Launcher/Receiver Project
On June 20, 2018, Columbia Gas
Transmission, LLC (Columbia) filed an
application in Docket No. CP18–508–
VerDate Sep<11>2014
20:20 Oct 22, 2018
Jkt 247001
000 requesting a Certificate of Public
Convenience and Necessity pursuant to
Section 7(c) of the Natural Gas Act to
construct and operate certain natural gas
pipeline facilities. The proposed project
is known as the Line KA1 North
Launcher/Receiver Project (Project), and
would modify seven discrete points and
install two bi-directional launcher/
receivers on Columbia’s existing Line
KA1 North pipeline.
On July 5, 2018, the Federal Energy
Regulatory Commission (Commission or
FERC) issued its Notice of Application
for the Project. Among other things, that
notice alerted agencies issuing federal
authorizations of the requirement to
complete all necessary reviews and to
reach a final decision on a request for
a federal authorization within 90 days of
the date of issuance of the Commission
staff’s Environmental Assessment (EA)
for the Project. This instant notice
identifies the FERC staff’s planned
schedule for the completion of the EA
for the Project.
Schedule for Environmental Review
Issuance of EA December 5, 2018
90-day Federal Authorization Decision
Deadline March 5, 2019
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
In order to enable the use of internal
inspection tools along the KA1 North
pipeline for integrity assessment
purposes, Columbia would install one
16-inch by 12-inch launcher/receiver at
each end of the pipeline; and remove,
replace, and install various stopples,
elbows, valves, pipe segments, and
other components at a total of seven
discrete points along the pipeline in
Fayette and Madison Counties,
Kentucky.
Background
On August 3, 2018, the Commission
issued a Notice of Intent to Prepare an
Environmental Assessment for the
Proposed Line KA1 North Launcher/
Receiver Project and Request for
Comments on Environmental Issues
(NOI). The NOI was sent to affected
landowners; federal, state, and local
government agencies; elected officials;
environmental and public interest
groups; Native American tribes; other
interested parties; and local libraries
and newspapers. In response to the NOI,
the Commission received comments
from two Native American tribes. The
primary issues raised by the
commentors pertain to cultural
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
resources. All substantive comments
will be addressed in the EA.
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC
website (www.ferc.gov). Using the
‘‘eLibrary’’ link, select ‘‘General Search’’
from the eLibrary menu, enter the
selected date range and ‘‘Docket
Number’’ excluding the last three digits
(i.e., CP18–508), and follow the
instructions. For assistance with access
to eLibrary, the helpline can be reached
at (866) 208–3676, TTY (202) 502–8659,
or at FERCOnlineSupport@ferc.gov. The
eLibrary link on the FERC website also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and rule
makings.
Dated: October 16, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018–23113 Filed 10–22–18; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER19–118–000]
Innovative Solar 67, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced Innovative Solar 67,
LLC’s application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE, Washington, DC 20426,
in accordance with Rules 211 and 214
E:\FR\FM\23OCN1.SGM
23OCN1
Agencies
[Federal Register Volume 83, Number 205 (Tuesday, October 23, 2018)]
[Notices]
[Pages 53467-53468]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-23114]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP18-538-000]
Sendero Carlsbad Gateway, LLC; Notice of Schedule for
Environmental Review of the Gateway Project
On August 9, 2018, Sendero Carlsbad Gateway, LLC (Gateway) filed an
application in Docket No. CP18-538-000 requesting a Certificate of
Public Convenience and Necessity pursuant to section 7(c) of the
Natural Gas Act to construct and operate certain natural gas pipeline
facilities. The proposed project is known as the Gateway Project
(Project), and would provide about 400 million standard cubic feet of
natural gas per day from Gateway's newly expanded Carlsbad Plant (a
cryogenic gas processing plant) to the Agua Blanca intrastate pipeline
owned by White Water Midstream, LLC. According to Gateway, the Project
would help alleviate natural gas supply delivery constraints in
southeast New Mexico and satisfy overall demand in the western region
of the United States.
On August 22, 2018, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
Environmental Assessment (EA) for the Project. This instant notice
identifies the FERC staff's planned schedule for the completion of the
EA for the Project.
Schedule for Environmental Review
Issuance of EA--January 11, 2019
90-day Federal Authorization Decision Deadline--April 11, 2019
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
The Gateway Project would consist of the following facilities:
Approximately 23 miles of 24-inch-diameter natural gas
transmission pipeline in Eddy County, New Mexico and Culberson County,
Texas;
a new meter station (including a mainline block valve and
pig \1\ launcher) within the existing Carlsbad Plant in Eddy County;
---------------------------------------------------------------------------
\1\ A ``pig'' is a tool that the pipeline company inserts into
and pushes through the pipeline for cleaning the pipeline,
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------
a mainline block valve at milepost 15.0 in Eddy County;
and
a pig receiver and mainline block valve at milepost 23.3
near a White Water Midstream, LLC meter station in Culberson County.
Background
On August 29, 2018, the Commission issued a Notice of Intent to
Prepare An Environmental Assessment for the Proposed Gateway Project,
And Request for Comments on Environmental Issues (NOI). The NOI was
sent to affected landowners; federal, state, and local government
agencies; elected officials; environmental and public interest groups;
Native American tribes; other interested parties; and local libraries
and newspapers.
In response to the NOI, the Commission received comments from
[[Page 53468]]
the U.S. Department of Agriculture, Texas Commission on Environmental
Quality, Texas Parks and Wildlife Department, New Mexico Department of
Game and Fish, New Mexico State Historic Preservation Office, and one
Native American tribe. The primary issues raised by the commentors were
appropriate best management practices for construction and restoration,
special status species, surface water, and impacts on vegetation and
wildlife. All substantive comments will be addressed in the EA.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the projects are available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select
``General Search'' from the eLibrary menu, enter the selected date
range and ``Docket Number'' excluding the last three digits (i.e.,
CP18-538), and follow the instructions. For assistance with access to
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC
website also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rule makings.
Dated: October 17, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-23114 Filed 10-22-18; 8:45 am]
BILLING CODE 6717-01-P