Southern Nuclear Operating Company, Inc.; Vogtle Electric Generating Plant, Units 3 and 4; Inspections, Tests, Analyses, and Acceptance Criteria, 53321-53322 [2018-22985]

Download as PDF Federal Register / Vol. 83, No. 204 / Monday, October 22, 2018 / Notices Section IV, and as summarized in Enclosure 2 to SECY–18–0062, are authorized by law, will not present an undue risk to the public health and safety, and are consistent with the common defense and security. Also, special circumstances are present. Therefore, the Commission hereby grants Exelon’s exemptions from certain EP requirements in 10 CFR 50.47(b), 10 CFR 50.47(c)(2), and 10 CFR Part 50, Appendix E, Section IV, as discussed and evaluated in detail in the NRC staff’s safety evaluation associated with this exemption. The exemptions are effective as of 12 months (365 days) after permanent cessation of power operations. Dated at Rockville, Maryland, this 16th day of October 2018. For the Nuclear Regulatory Commission. /RA/ Kathryn M. Brock, Deputy Director, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation. [FR Doc. 2018–22986 Filed 10–19–18; 8:45 am] BILLING CODE 7590–01–P in the FOR FURTHER INFORMATION CONTACT section of this document. II. NRC Staff Determination of Completion of ITAAC • NRC’s Agencywide Documents Access and Management System (ADAMS): You may obtain publicly available documents online in the ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/ adams.html. To begin the search, select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, 301– 415–4737, or by email to pdr.resource@ nrc.gov. The ADAMS accession number for each document referenced in this document (if that document is available in ADAMS) is provided the first time that a document is referenced. • NRC’s PDR: You may examine and purchase copies of public documents at the NRC’s PDR, Room O1–F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. The NRC staff has determined that the specified inspections, tests, and analyses have been successfully completed, and that the specified acceptance criteria are met. The documentation of the NRC staff’s determination is in the ITAAC Closure Verification Evaluation Form (VEF) for each ITAAC. The VEF is a form that represents the NRC staff’s structured process for reviewing ICNs. Each ICN presents a narrative description of how the ITAAC was completed. The NRC’s ICN review process involves a determination on whether, among other things: (1) Each ICN provides sufficient information, including a summary of the methodology used to perform the ITAAC, to demonstrate that the inspections, tests, and analyses have been successfully completed; (2) each ICN provides sufficient information to demonstrate that the acceptance criteria of the ITAAC are met; and (3) any NRC inspections for the ITAAC have been completed and any ITAAC findings associated with that ITAAC have been closed. The NRC staff’s determination of the successful completion of these ITAAC is based on information available at this time and is subject to the licensee’s ability to maintain the condition that the acceptance criteria are met. If the staff receives new information that suggests the staff’s determination on any of these ITAAC is incorrect, then the staff will determine whether to reopen that ITAAC (including withdrawing the staff’s determination on that ITAAC). The NRC staff’s determination will be used to support a subsequent finding, pursuant to 10 CFR 52.103(g), at the end of construction that all acceptance criteria in the combined license are met. The ITAAC closure process is not finalized for these ITAAC until the NRC makes an affirmative finding under 10 CFR 52.103(g). Any future updates to the status of these ITAAC will be reflected on the NRC’s website at https:// www.nrc.gov/reactors/new-reactors/ oversight/itaac.html. This notice fulfills the staff’s obligations under 10 CFR 52.99(e)(1) to publish a notice in the Federal Register of the NRC staff’s determination of the successful completion of inspections, tests, and analyses. FOR FURTHER INFORMATION CONTACT: Chandu Patel, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001; telephone: 301–415–3025; email: Chandu.Patel@ nrc.gov. NUCLEAR REGULATORY COMMISSION [Docket Nos. 52–025 and 52–026; NRC– 2008–0252] Southern Nuclear Operating Company, Inc.; Vogtle Electric Generating Plant, Units 3 and 4; Inspections, Tests, Analyses, and Acceptance Criteria Nuclear Regulatory Commission. ACTION: Determination of the successful completion of inspections, tests, and analyses. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) staff has determined that the inspections, tests, and analyses have been successfully completed, and that the specified acceptance criteria are met for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4. DATES: The determination of the successful completion of inspections, tests, and analyses for VEGP Units 3 and 4 is effective October 22, 2018. ADDRESSES: Please refer to Docket ID NRC–2008–0252 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods: • Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC–2008–0252. Address questions regarding Docket IDs in Regulations.gov to Jennifer Borges; telephone: 301–287–9127; email: Jennifer.Borges@nrc.gov. For technical questions, contact the individual listed daltland on DSKBBV9HB2PROD with NOTICES SUMMARY: VerDate Sep<11>2014 18:12 Oct 19, 2018 Jkt 247001 53321 SUPPLEMENTARY INFORMATION: I. Licensee Notification of Completion of ITAAC Southern Nuclear Operating Company, Inc. (SNC), Georgia Power Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC., MEAG Power SPVJ, LLC., MEAG Power SPVP, LLC., and the City of Dalton, Georgia, (hereafter called the licensee) have submitted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) closure notifications (ICNs) under paragraph 52.99(c)(1) of title 10 of the Code of Federal Regulations (10 CFR), informing the NRC that the licensee has successfully performed the required inspections, tests, and analyses, and that the acceptance criteria are met for: VEGP Unit 3 ITAAC: 2.2.03.08b.02 (176), 2.2.03.08c.iv.04 (186), 2.2.05.07a.ii (266), 2.3.05.03a.i (343), 2.3.09.03.iii (425), 3.2.00.01c.ii (742), and 3.2.00.01d (743). VEGP Unit 4 ITAAC: 2.2.05.07a.ii (266), 3.2.00.01c.ii (742), and 3.2.00.01d (743). The ITAAC for VEGP Unit 3 are in Appendix C of the VEGP Unit 3 combined license (ADAMS Accession No. ML14100A106). The ITAAC for VEGP Unit 4 are in Appendix C of VEGP Unit 4 combined license (ADAMS Accession No. ML14100A135). PO 00000 Frm 00116 Fmt 4703 Sfmt 4703 Vogtle Electric Generating Plant Unit 3, Docket No. 5200025 A complete list of the review status for VEGP Unit 3 ITAAC, including the submission date and ADAMS Accession Number for each ICN received, the E:\FR\FM\22OCN1.SGM 22OCN1 53322 Federal Register / Vol. 83, No. 204 / Monday, October 22, 2018 / Notices ADAMS Accession Number for each VEF, and the ADAMS Accession Numbers for the inspection reports associated with these specific ITAAC, can be found on the NRC’s website at https://www.nrc.gov/reactors/newreactors/new-licensing-files/vog3icnsr.pdf. For the Nuclear Regulatory Commission. Jennifer L. Dixon-Herrity, Chief, Licensing Branch 4, Division of Licensing, Siting, and Environmental Analysis, Office of New Reactors. Vogtle Electric Generating Plant Unit 4, Docket No. 5200026 OFFICE OF PERSONNEL MANAGEMENT A complete list of the review status for VEGP Unit 4 ITAAC, including the submission date and ADAMS Accession Number for each ICN received, the ADAMS Accession Number for each VEF, and the ADAMS Accession Numbers for the inspection reports associated with these specific ITAAC, can be found on the NRC’s website at https://www.nrc.gov/reactors/newreactors/new-licensing-files/vog4icnsr.pdf. Excepted Service [FR Doc. 2018–22985 Filed 10–19–18; 8:45 am] BILLING CODE 7590–01–P Dated at Rockville, Maryland, this 17th day of October, 2018. Agency name DEPARTMENT CULTURE. OF AGRI- APPALACHIAN REGIONAL COMMISSION. DEPARTMENT OF COMMERCE .. DEPARTMENT OF DEFENSE ....... DEPARTMENT OF THE ARMY ..... daltland on DSKBBV9HB2PROD with NOTICES DEPARTMENT OF EDUCATION .. DEPARTMENT OF ENERGY ........ ENVIRONMENTAL PROTECTION AGENCY. FEDERAL TRADE COMMISSION VerDate Sep<11>2014 18:12 Oct 19, 2018 U.S. Office of Personnel Management (OPM). ACTION: Notice. AGENCY: This notice identifies Schedule A, B, and C appointing authorities applicable to a single agency that were established or revoked from May 1, 2018 to May 31, 2018. FOR FURTHER INFORMATION CONTACT: Senior Executive Resources Services, Senior Executive Services and Performance Management, Employee Services, Julia Alford, 202–606–2246, SERS@opm.gov. SUPPLEMENTARY INFORMATION: In accordance with 5 CFR 213.103, SUMMARY: Schedule A, B, and C appointing authorities available for use by all agencies are codified in the Code of Federal Regulations (CFR). Schedule A, B, and C appointing authorities applicable to a single agency are not codified in the CFR, but the Office of Personnel Management (OPM) publishes a notice of agency-specific authorities established or revoked each month in the Federal Register at www.gpo.gov/fdsys/. OPM also publishes an annual notice of the consolidated listing of all Schedule A, B, and C appointing authorities, current as of June 30, in the Federal Register. Schedule A No Schedule A Authorities to report during May 2018. Schedule B No Schedule B Authorities to report during May 2018. Schedule C The following Schedule C appointing authorities were approved during May 2018. Authorization number Organization name Position title Office of the Assistant Secretary for Congressional Relations. Office of the Secretary ................... Office of the Under Secretary for Farm Production and Conservation. Office of the Under Secretary for Food Safety. Office of Under Secretary for Natural Resources and Environment. Rural Housing Service ................... Director, Intergovernmental Affairs DA180174 05/08/2018 Director of Policy Coordination ...... Staff Assistant ................................ DA180158 DA180181 05/08/2018 05/16/2018 Confidential Assistant .................... DA180148 05/24/2018 Staff Assistant ................................ DA180169 05/24/2018 State Director ................................. State Director—Louisiana .............. Strategic Program Advisor ............. Program Analyst ............................ DA180146 DA180126 DA180185 AP180001 05/16/2018 05/30/2018 05/08/2018 05/25/2018 Special Advisor .............................. DC180123 05/08/2018 Special Assistant ............................ Special Assistant (Logistics and Materiel Readiness). DC180142 DD180086 05/25/2018 05/08/2018 Special Assistant (Strategy and Acquisition Reform). Special Assistant (Civil Works) ...... Special Assistant(Manpower and Reserve Affairs). Confidential Assistant .................... DW180031 05/16/2018 DW180032 DW180033 05/24/2018 05/16/2018 DB180046 05/24/2018 Special Assistant ............................ Executive Support Specialist ......... DE180077 DE180090 05/16/2018 05/17/2018 Senior Advisor ................................ DE180105 05/23/2018 Senior Advisor ................................ EP180061 05/10/2018 Economist ...................................... FT180004 05/02/2018 Appalachian Regional Commission Office of the Deputy Assistant Secretary. International Trade Administration Office of the Under Secretary of Defense (Acquisition, Technology, and Logistics). Office Assistant Secretary Army (Civil Works). Office Assistant Secretary Army (Manpower and Reserve Affairs). Office of Communications and Outreach. Office of Public Affairs ................... Advanced Research Projects Agency—Energy. Assistant Secretary for Environmental Management. Region 9—San Francisco, California. Office of the Chairman ................... Jkt 247001 PO 00000 Frm 00117 Fmt 4703 Sfmt 4703 E:\FR\FM\22OCN1.SGM 22OCN1 Effective date

Agencies

[Federal Register Volume 83, Number 204 (Monday, October 22, 2018)]
[Notices]
[Pages 53321-53322]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-22985]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 52-025 and 52-026; NRC-2008-0252]


Southern Nuclear Operating Company, Inc.; Vogtle Electric 
Generating Plant, Units 3 and 4; Inspections, Tests, Analyses, and 
Acceptance Criteria

AGENCY: Nuclear Regulatory Commission.

ACTION: Determination of the successful completion of inspections, 
tests, and analyses.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) staff has 
determined that the inspections, tests, and analyses have been 
successfully completed, and that the specified acceptance criteria are 
met for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4.

DATES: The determination of the successful completion of inspections, 
tests, and analyses for VEGP Units 3 and 4 is effective October 22, 
2018.

ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC-2008-0252. Address 
questions regarding Docket IDs in Regulations.gov to Jennifer Borges; 
telephone: 301-287-9127; email: [email protected]. For technical 
questions, contact the individual listed in the FOR FURTHER INFORMATION 
CONTACT section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected]. The ADAMS accession number for each 
document referenced in this document (if that document is available in 
ADAMS) is provided the first time that a document is referenced.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Chandu Patel, Office of New Reactors, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; 
telephone: 301-415-3025; email: [email protected].

SUPPLEMENTARY INFORMATION: 

I. Licensee Notification of Completion of ITAAC

    Southern Nuclear Operating Company, Inc. (SNC), Georgia Power 
Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC., MEAG 
Power SPVJ, LLC., MEAG Power SPVP, LLC., and the City of Dalton, 
Georgia, (hereafter called the licensee) have submitted Inspections, 
Tests, Analyses, and Acceptance Criteria (ITAAC) closure notifications 
(ICNs) under paragraph 52.99(c)(1) of title 10 of the Code of Federal 
Regulations (10 CFR), informing the NRC that the licensee has 
successfully performed the required inspections, tests, and analyses, 
and that the acceptance criteria are met for:
    VEGP Unit 3 ITAAC: 2.2.03.08b.02 (176), 2.2.03.08c.iv.04 (186), 
2.2.05.07a.ii (266), 2.3.05.03a.i (343), 2.3.09.03.iii (425), 
3.2.00.01c.ii (742), and 3.2.00.01d (743).
    VEGP Unit 4 ITAAC: 2.2.05.07a.ii (266), 3.2.00.01c.ii (742), and 
3.2.00.01d (743).
    The ITAAC for VEGP Unit 3 are in Appendix C of the VEGP Unit 3 
combined license (ADAMS Accession No. ML14100A106). The ITAAC for VEGP 
Unit 4 are in Appendix C of VEGP Unit 4 combined license (ADAMS 
Accession No. ML14100A135).

II. NRC Staff Determination of Completion of ITAAC

    The NRC staff has determined that the specified inspections, tests, 
and analyses have been successfully completed, and that the specified 
acceptance criteria are met. The documentation of the NRC staff's 
determination is in the ITAAC Closure Verification Evaluation Form 
(VEF) for each ITAAC. The VEF is a form that represents the NRC staff's 
structured process for reviewing ICNs. Each ICN presents a narrative 
description of how the ITAAC was completed. The NRC's ICN review 
process involves a determination on whether, among other things: (1) 
Each ICN provides sufficient information, including a summary of the 
methodology used to perform the ITAAC, to demonstrate that the 
inspections, tests, and analyses have been successfully completed; (2) 
each ICN provides sufficient information to demonstrate that the 
acceptance criteria of the ITAAC are met; and (3) any NRC inspections 
for the ITAAC have been completed and any ITAAC findings associated 
with that ITAAC have been closed.
    The NRC staff's determination of the successful completion of these 
ITAAC is based on information available at this time and is subject to 
the licensee's ability to maintain the condition that the acceptance 
criteria are met. If the staff receives new information that suggests 
the staff's determination on any of these ITAAC is incorrect, then the 
staff will determine whether to reopen that ITAAC (including 
withdrawing the staff's determination on that ITAAC). The NRC staff's 
determination will be used to support a subsequent finding, pursuant to 
10 CFR 52.103(g), at the end of construction that all acceptance 
criteria in the combined license are met. The ITAAC closure process is 
not finalized for these ITAAC until the NRC makes an affirmative 
finding under 10 CFR 52.103(g). Any future updates to the status of 
these ITAAC will be reflected on the NRC's website at https://www.nrc.gov/reactors/new-reactors/oversight/itaac.html.
    This notice fulfills the staff's obligations under 10 CFR 
52.99(e)(1) to publish a notice in the Federal Register of the NRC 
staff's determination of the successful completion of inspections, 
tests, and analyses.

Vogtle Electric Generating Plant Unit 3, Docket No. 5200025

    A complete list of the review status for VEGP Unit 3 ITAAC, 
including the submission date and ADAMS Accession Number for each ICN 
received, the

[[Page 53322]]

ADAMS Accession Number for each VEF, and the ADAMS Accession Numbers 
for the inspection reports associated with these specific ITAAC, can be 
found on the NRC's website at https://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog3-icnsr.pdf.

Vogtle Electric Generating Plant Unit 4, Docket No. 5200026

    A complete list of the review status for VEGP Unit 4 ITAAC, 
including the submission date and ADAMS Accession Number for each ICN 
received, the ADAMS Accession Number for each VEF, and the ADAMS 
Accession Numbers for the inspection reports associated with these 
specific ITAAC, can be found on the NRC's website at https://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog4-icnsr.pdf.

    Dated at Rockville, Maryland, this 17th day of October, 2018.

    For the Nuclear Regulatory Commission.
Jennifer L. Dixon-Herrity,
Chief, Licensing Branch 4, Division of Licensing, Siting, and 
Environmental Analysis, Office of New Reactors.
[FR Doc. 2018-22985 Filed 10-19-18; 8:45 am]
 BILLING CODE 7590-01-P